"Point in Time" Regulation Content

Utilities Commission Act

Cryptocurrency Power Regulation

B.C. Reg. 163/2024

NOTE: Links below go to regulation content as it was prior to the changes made on the effective date. (PIT covers changes made from September 19, 2009 to "current to" date of the regulation.)
SECTIONEFFECTIVE DATE
Section 1 October 20, 2025
Section 2 October 20, 2025

 Section 1 definition of "paused project" BEFORE repealed by BC Reg 164/2025, effective October 20, 2025.

"paused project" means a new high-voltage cryptocurrency project that is the subject of one of the following agreements:

(a) the system impact study agreement dated December 1, 2021;

(b) the system impact study agreement dated January 28, 2022;

(c) the system impact study agreement dated June 15, 2022;

(d) the system impact study agreement dated June 20, 2022;

 Section 1 definition of "proposed project" was added by BC Reg 164/2025, effective October 20, 2025.

 Section 2 (part) BEFORE amended by BC Reg 164/2025, effective October 20, 2025.

2   During the period beginning on the date this regulation comes into force and ending 18 months after that date, the authority must not do any of the following:

 Section 2 (b) (ii) BEFORE amended by BC Reg 164/2025, effective October 20, 2025.

(ii) by entering into a facilities study agreement in relation to a paused project.