| Copyright © King's Printer, Victoria, British Columbia, Canada | Licence Disclaimer |
| B.C. Reg. 242/2016 M417/2016 | Deposited October 20, 2016 |
[Last amended March 20, 2020 by B.C. Reg. 61/2020]
1 In this regulation:
"Act" means the Utilities Commission Act;
"Apollo Transmission System" means the transmission system owned by Apollo Forest Products Ltd. on the date this regulation comes into force;
"biomass fuel processing project" means the project to construct and operate a biomass fuel processing, screening and handling facility located adjacent to the biomass thermal generation facility;
"biomass thermal generation facility" means the 40 MW biomass thermal generation facility approximately 6 km north of the authority's Fort St. James No. 2 Substation.
[am. B.C. Reg. 61/2020, ss. (a) and (b).]
2 Apollo Forest Products Ltd. and its successors and assigns are exempt from Part 3 of the Act in respect of
(a) the Apollo Transmission System,
(b) the provision of service respecting the transmission of electricity from the biomass thermal generation facility to the authority's transmission system, and
(c) the provision of service respecting the transmission of electricity from the authority's transmission system to the biomass fuel processing project.
[am. B.C. Reg. 61/2020, ss. (c) to (e).]
[Provisions relevant to the enactment of this regulation: Utilities Commission Act, R.S.B.C. 1996, c. 473, s. 22.]
Copyright © King's Printer, Victoria, British Columbia, Canada