"Point in Time" Regulation Content

Energy Resource Activities Act

Renewable Energy Projects Regulation

B.C. Reg. 28/2026

NOTE: Links below go to regulation content as it was prior to the changes made on the effective date. (PIT covers changes made from September 19, 2009 to "current to" date of the regulation.)
SECTIONEFFECTIVE DATE
Section 6 March 24, 2026
Part 4 March 24, 2026
Section 46 March 24, 2026
March 24, 2026

 Section 6 (1) (a) BEFORE amended by BC Reg 42/2026, effective March 24, 2026.

(a) the owner in fee simple of land within 1.5 km of a project area;

 Section 6 (2) (e) BEFORE amended by BC Reg 42/2026, effective March 24, 2026.

(e) a summary of the nature, geographic area and timing of the impacts on quality of life that would reasonably be expected to occur within 1.5 km of a project area;

 Part 4 BEFORE re-enacted by BC Reg 42/2026, effective March 24, 2026.

Part 4 — Security

Security

14   Section 25 (1), (3), (4) (b) and (5) [security] of the Fee, Levy and Security Regulation, B.C. Reg. 8/2014, applies in relation to renewable energy projects.

 Section 46 (1) BEFORE amended by BC Reg 42/2026, effective March 24, 2026.

(1) This section applies in relation to

(a) Parts 5 to 8, and

(b) Division 1 of Part 9.

 Section 47 (2) (b.1) was added by BC Reg 42/2026, effective March 24, 2026.

 Section 47 (3) BEFORE amended by BC Reg 42/2026, effective March 24, 2026.

(3) A person is not required to comply with this regulation, other than section 49, before October 1, 2026 in relation to a specified existing project.