Utilities Commission Act

Direction to the British Columbia Utilities Commission Respecting Undertaking Costs

Definitions

1   In this direction:

"Act" means the Utilities Commission Act;

"DSM regulatory account" means the regulatory account of the authority established under commission order G-55-95;

"undertaking costs" means all costs incurred by the authority to implement an undertaking within a class defined in section 4 (3) (a), (b), (c) or (d) of the Greenhouse Gas Reduction (Clean Energy) Regulation.

Application

2   This direction is issued to the commission under section 3 of the Act.

Undertaking costs

3   The commission must allow the authority to defer to the DSM regulatory account amounts equal to the undertaking costs.