September 30, 1999, E.C.B. No. 30/94/174
(68 L.C.R. 137)
Between: |
William
P. Harshenin
Claimant |
And: |
And:
Her Majesty The Queen in Right of the Province of
British Columbia as Represented by the Minister
of Transportation and Highways and the Ministry
of Transportation and Highways
Respondent |
Before: |
Robert
W. Shorthouse
Chair |
Appearances: |
William
P. Harshenin, In Person
Robert Musto, Counsel For The Respondent |
REASONS FOR DECISION
1. INTRODUCTION
The claimant, William P. Harshenin,
is the registered owner in fee simple of land located
at 2011 Broadwater Road near Castlegar, B.C., legally
described as Parcel Identifier 011-959-657, Lot 21,
Block 18, District Lot 237, Kootenay District, Plan
2933 ("Lot 21"). Lot 21 is situated in Robson,
B.C., just north of Castlegar, on the north side of
the Columbia River, at the corner of Broadwater Road
and Pass Creek Road. In the early 1970s the claimant
built and occupied a home on Lot 21. He continues to
reside there with his wife, Diane Harshenin. The claimant
is also the registered owner of a life estate in land
located at 2021 Raspberry Road, legally described as
Parcel Identifier 011-937-904, Lot 20, Block 18, District
Lot 237, Kootenay District, Plan 2933 ("Lot 20").
Lot 20 is contiguous to and west of Lot 21. The claimant's
daughter, Darlene Harshenin, is the registered fee simple
owner of Lot 20. She lives in a mobile home situated
there. Additionally, the claimant has a life estate
in and easement over land legally described as Lot 22,
Block 18, District Lot 237, Kootenay District, Plan
2933 ("Lot 22"). The claimant's son, Matthew
Wayne Harshenin, is the registered fee simple owner
of Lot 22 and lives on the property.
In 1994 the respondent, Her Majesty
the Queen in Right of the Province of British Columbia
as represented by the Minister of Transportation and
Highways, embarked on a project to construct and improve
highway accesses to the new Robson Bridge spanning the
Columbia River, which opened for traffic in November
1994. During September 1994 the respondent formally
expropriated a small portion of Lot 21 in order to improve
the intersection of Broadwater Road and Pass Creek Road
in connection with that project. Broadwater Road (sometimes
also referred to as the "Robson Access Road")
provides the main access to the Bridge from the east.
Paving work began on Broadwater Road in the vicinity
of Lot 21 in the fall of 1994 but was left uncompleted
until the spring of 1995.
The claimant filed with the board
an application for determination of compensation (the
"Form A") on October 6, 1994, asserting claims
for, among other things, the market value of that portion
of Lot 21 which was taken, diminution in value to the
claimant's remaining land, and disturbance damages.
Subsequent discussions between the parties resulted
in last minute settlement of a number of the claims
originally in contention. What the board has been left
to determine primarily is the claimant's claim for compensation
for damages to his residence on Lot 21 allegedly caused
by the action of heavy vehicle traffic over the partially
repaved surface of Broadwater Road in late 1994 and
early 1995. A secondary issue remaining is the claimant's
claim for what is described as "injurious affection"
to his life estate in Lot 20. To avoid any confusion
in terminology under the applicable legislation, I prefer
to characterize this claim as being one for reduction
in market value. No claim was pursued with respect to
the claimant's interests in Lot 22.
I heard these compensation claims
alone in my capacity as chair of the board and in exercising
the powers and jurisdiction of the board pursuant to
section 26(5) of the Expropriation Act, R.S.B.C.
1996, c. 125 (the "Act"). Mr. Harshenin gave
evidence on his own behalf and acted as his own counsel
in the proceeding. The other witnesses for the claimant
were two building contractors, Harold Nevokshonoff and
Mike Makordoff, who had provided contract proposals
for repairs to the claimant's residence. Witnesses for
the respondent were the highway project supervisor,
Michael Newton, who testified concerning the roadwork
adjacent to Lot 21, and a professional engineer, Elmer
Verigin, who testified concerning an inspection report
he prepared on the claimant's residence.
2. BACKGROUND
2.1 The Claimant and
His Property
The claimant is a qualified carpenter
who has worked in the construction industry for more
than 30 years, initially in Victoria and the Lower Mainland
of British Columbia but predominantly in the Castlegar
area. He testified that he has a good general knowledge
of residential construction and, in addition to carpentry,
has some experience in wiring, plumbing, bricklaying
and other associated trades. At the time of the compensation
hearing, the claimant was unemployed.
The lands which are the subject of
these proceedings were purchased by the claimant's father,
Pete Sam Harshenin, about 1960. Fee simple title to
the lands, including Lot 21, was transferred to the
claimant by his father in October 1971. At that time
the claimant was living and working in Surrey, British
Columbia, but moved back to the Castlegar area with
his family in or about July 1972. In September 1988,
the claimant transferred title to Lot 22, subject to
a life estate and easement in his favour, to his son.
In October 1988, the claimant transferred title to Lot
20, subject to the life estate in his favour, to his
daughter.
2.2 The Claimant's Residence
The claimant constructed a two-level
wood frame, single family residence on Lot 21, beginning
in the fall of 1972. The residence is located at the
rear of Lot 21, well back from the driveway access point
to Broadwater Road. The main floor living area consists
of three bedrooms, a bathroom, kitchen, dining area
and living room with a brick fireplace in the living
room. There is also a covered walkway and enclosed sundeck
on this level. A large portion of the full basement
is above ground. The finished portion consists of a
recreation room, bedroom, bathroom and laundry room
plus a furnace room. There is a brick fireplace in the
basement to which a wood air tight stove is connected.
Two partly finished rooms adjacent are used as a workshop
and a garage. There is also an attached carport.
The evidence was that the claimant
did most of the work on the residence himself with the
assistance of his immediate family in order to save
costs. He testified that, apart from the excavation
of the site, the spraying of the ceiling, and the necessary
electrical and natural gas connections, he had made
use of his considerable practical experience to select
the construction materials and build the home. Among
other tasks, he poured the foundations and slab, framed,
roofed and insulated the residence, secured the floor
joists and flooring, and did the drywalling, painting,
panelling and tiling. He had, he said, also installed
the kitchen cabinets, built the double fireplace, applied
a waterproof coating to the sundeck, and prepared and
applied the exterior stucco. The claimant during his
testimony gave a detailed account of all the construction
materials and methods he employed. However, a consideration
of these, where relevant, might more usefully be deferred
to that section of the decision which will examine the
claimant's claims for damages to his residence.
The construction of the residence
continued from the fall of 1972 until the early fall
of 1973, when the claimant and his family moved in.
At that point and in some cases for years thereafter,
certain interior and exterior finishing work still remained
to be done. For example, the bathroom plumbing work
was not complete, slate tiles had not been installed
on the fireplace hearth and windows had not been inserted
in the workshop. On the exterior, the stucco work remained
unfinished. No final coat of stucco has ever been applied.
2.3 The Expropriation
and Subsequent Roadwork
On September 9, 1994, the respondent
issued an expropriation notice and a certificate of
approval of expropriation with respect to its partial
taking of Lot 21 for the purpose of constructing and
improving highway access to the Robson Bridge. Title
to the lands which were taken, amounting to some 404
square metres (0.0998 acres) adjacent to Pass Creek
Road, vested in the respondent on September 27, 1994.
The respondent made an advance payment with respect
to the land taken on September 14, 1994.
According to the evidence of Mr. Newton,
the respondent's project at the intersection adjacent
to Lot 21 involved widening the shoulders and creating
a pass lane on Broadwater Road, improving the turning
radius on Pass Creek Road, and paving the reconstructed
portions. The highway approaches closer to the new Robson
Bridge were already paved to finished grade when the
bridge opened to traffic on November 1, 1994. However,
the timing of the project in the immediate vicinity
of Lot 21 was such that, with the onset of winter weather,
the respondent was only able to complete a bottom lift
of asphalt pavement in October 1994 and had to defer
paving the top lift until the following late spring.
This left a difference in elevation between the pavements
which the respondent says amounted to 5.0 cm. but which
the claimant says was more like three inches (7.62 cm.)
In any event, it was necessary for the respondent to
create a construction joint in the nature of an asphalt
ramp or taper which would tie in the new bottom lift
to the finished pavement on Broadwater Road in front
of Lot 21 and minimize the impact on vehicle traffic.
According to Mr. Verigin, whose evidence on this point
was not disputed, the construction joint was located
about 80 feet west of a perpendicular line through the
centre of the claimant's residence and intersecting
the roadway south of the residence.
It is clear from the evidence that,
at some point during the succeeding winter, the taper
began to wear out and pot holes developed causing the
"bump" in the construction joint to become
more pronounced. The claimant testified that the situation
worsened particularly with the spring thaw. He also
introduced photographic evidence to support his assertion
that the respondent had put in two tapered ramps across
the width of the roadway, leaving an untapered gap measuring
perhaps eight feet between them. In a letter to the
editor of The Castlegar Sun published in early
March 1995 and entered in evidence at the hearing, the
claimant described what he said was the effect on heavy
truck traffic at that location as follows:
"The trucks were hitting the
ramp with all their wheels 50 percent of the time
and the rest of the time with 50 percent of their
wheels. The other wheels would hit the space between
the two ramps (like a speed bump)."
In turn, the claimant described what
he said was the impact on his residence and his family
life:
"Now, not only are the dishes
rattling, the whole house is rattling. Sleep as we
knew it is a thing of the past. The house is getting
cracks in the drywall, stucco and fireplaces."
The claimant brought his complaints
to the attention of the respondent, which made efforts
during late March to do some temporary patching. However,
the permanent final lift of asphalt pavement was not
completed until some time in May 1995.
2.4 The Partial Settlement
of Claims
During the week preceding the start
of the compensation hearing, the parties reached a settlement
respecting a number of the claimant's claims. In addition
to the sum of $13,618 previously advanced, the respondent
on July 7, 1998 delivered to the claimant a cheque for
$26,439.82. However, the respondent initially misstated
the monetary terms of settlement in an accompanying
letter to the claimant and in a partial release of claim
which, together with a consent dismissal order, it prepared
and which the claimant mistakenly signed. The respondent
corrected its error in a letter of July 9, 1998, but
that error appears to have left a lingering suspicion
in the mind of the claimant who, by the conclusion of
the compensation hearing, was still reluctant to sign
a new and corrected partial release of claim. During
the compensation hearing, it also became clear that
the parties disagreed somewhat as to the scope of the
settlement since the claimant continued to advance at
least one claim which the respondent said had already
been settled.
In these circumstances, I consider
it necessary to set out my view with respect to the
settlement. I find as a fact that the parties did reach
a binding settlement of all claims in dispute in this
matter, except those which are expressly excluded in
the partial release of claim. The respondent provided
to the claimant an itemized list of all those claims
which were encompassed by the settlement. They included
compensation for the market value of the land taken,
for the reduction in market value to the remainder,
for disturbance damages to trees, a culvert, the drainage
system and the driveway on Lot 21, for certain costs
incurred by the claimant for engineering services, telephone
and travel, and for accrued interest on the claims which
were settled.
Those claims expressly excluded from
the partial release of claim which were not settled
and in respect of which no compensation has been paid
concern the alleged damages to the improvements (that
is to say, the residence) on Lot 21, alleged reduction
in market value to the claimant's life estate in Lot
20, interest on the two foregoing items, and reasonable
legal, appraisal and other costs (other than, presumably,
the costs already paid on account of engineering services,
telephone and travel). Each of the outstanding claims
will be addressed in turn.
3. DAMAGE TO THE RESIDENCE
ON LOT 21
3.1 Observed Defects
There is ample evidence from both
parties to confirm that various portions of the finishes
to the claimant's residence on Lot 21 exhibited defects
in the period leading up to the compensation hearing.
Those defects are not expressly addressed in the claimant's
statement of claim or the respondent's reply, both of
which were filed with the board prior to the time when
it is now alleged that the damage occurred. The pleadings
have not since been amended. However, the list of observed
defects is perhaps most succinctly set out in the inspection
report prepared by Mr. Verigin. That inspection was
carried out on June 3, 1998 in the presence of the claimant
and in my view captures with reasonable accuracy what
the claimant subsequently testified to as being the
scope of the damage to his residence. The list is as
follows:
(1) |
Loosening or lifting
of the floor, underlay and/or sheathing of the
main floor assembly, causing creaks in the floor
and damage to the linoleum flooring. |
(2) |
Similar movement
in the floor assembly of the west deck and north
walkway causing cracks in the seams of the waterproof
deck coating with resulting leaks. |
(3) |
Cracks in the
interior finishes including walls, ceilings and
gypsum board valances. |
(4) |
Loosening and
cracking of exterior stucco finishes on the residence. |
(5) |
Damage to the
drainage system which carries site drainage, foundation
drainage and roof drainage away from the residence. |
(6) |
Cracking of the
masonry core and finish face of the fireplace. |
(7) |
Lifting of the
floor tile in the basement hallway adjacent to
the recreation room. |
(8) |
Drooping of the
ceiling tile along the north wall of the recreation
room. |
During the compensation hearing the
claimant referred in passing to other items of damage
he attributed to the respondent's roadwork but in respect
of which he said he was making no claim, notably leaks
in the entry roof to his residence and in the roof of
a detached woodshed on Lot 21, and cracks in the chimney
and in a shower stall. It should also be noted that
the fifth enumerated item dealing with the drainage
system is one which was settled prior to the commencement
of the hearing.
3.2 The Issues
Two issues for determination arise
from the claimant's claim for compensation in respect
of the observed defects. The first is a question of
causation. Is the evidence sufficient to prove, on a
balance of probabilities, that they were not the result
of pre-existing problems of house design and construction
but were instead caused by impact vibrations set off
by heavy truck traffic hitting the construction joint
in the surface of the roadway? If the first issue is
resolved in the claimant's favour, the second issue
to be addressed is one of quantum. Is there sufficient
evidence upon which to quantify the claimant's damages?
3.3 The Claimant's Case
The claimant's case rests primarily
on the testimony of the claimant himself about the construction
of his residence in the early 1970s, the effect of truck
traffic on Broadwater Road during the respondent's uncompleted
highway project in late 1994 and early 1995, and the
defects in his residence which he says he began to observe
during the period when the temporary construction joint
was in place. Unlike the respondent, the claimant did
not commission an independent expert to inspect the
residence and report on observable deficiencies or damage.
He did not have at his disposal any studies in the nature
of traffic counts or seismic readings at the location.
Although the claimant did retain an engineering firm
to conduct soil analyses in order to determine whether
impact vibrations of the kind complained of could have
been transmitted, the engineering report which resulted
was not tendered in evidence at the hearing. The claimant
did, however, introduce a number of photographs which
he had taken both during and after the period of the
roadwork depicting damage to his residence to support
his assertion that there was a direct causal link between
the two. He also submitted in evidence a scholarly article
on construction vibrations published in a geotechnical
journal.
The thrust of the claimant's testimony
regarding his residence was to endeavour to prove that
it had been well constructed in compliance with, and
in some cases exceeding, building code requirements
and that it exhibited no significant faults prior to
the period of the respondent's roadwork. It is, in my
view, sufficient to focus on construction details pertaining
to those elements of the residence where defects were
identified for which compensation has been claimed,
notably the tiled floor and ceiling of the recreation
room, the main floor area, the covered deck, the gyproced
walls, ceilings and valances, the fireplace, and the
exterior stucco. The claimant's evidence with respect
to each of these elements is summarized in turn.
The claimant described the care he
had taken in pouring the eight inch thick foundations
and the four inch thick concrete slab on four inches
of compacted gravel under the main portion of the house
to avoid cracks from developing.
He explained that he had salvaged
the main floor joists from a nearby breakwater and,
to give added strength and stability, had installed
them on 12 inch rather than 16 inch centres as required
by the building code. He had used special "ardox"
nails to fasten the diagonally sheeted shiplap to the
floor joists and, in turn, to nail particleboard through
the shiplap directly into the floor joists. He had,
he said, laid down heavy flooring paper to separate
the subfloor from the underlay. The object was to avoid
any later "nail pops", lifting of the floor,
and resulting squeaks.
With respect to the covered deck which
also provided the roof over the workshop area, the claimant
testified that he had used similar construction materials
and techniques before applying a waterproof deck finish
known as "spantex".
In constructing the walls and ceiling
of the residence, the claimant indicated that he had
used standard framing and sheathing materials and had
insulated those areas with paperbacked fibreglas batt
insulation under a 1/2 inch drywall finish. Even though
he acknowledged that the building code required it,
the claimant testified that he did not install a polyethylene
vapour barrier in the walls or ceiling out of concern
that it would seal in the house too tightly.
The claimant said little about the
construction of the double fireplace, other than to
confirm that he had had previous masonry and bricklaying
experience. Similarly, in doing the exterior stucco
work, the claimant had drawn on his experience in an
earlier project. He testified that he had prepared the
exterior walls in the usual way, using building paper
and stucco wire before mixing the masonry cement, sand,
and water in a wheelbarrow and applying a first "scratch"
coat. He said a second coat was applied a year or two
later. The finish coat has never been applied.
Although the claimant did acknowledge
some cracks, squeaks or other small defects in the finishes
to the residence prior to the respondent's roadwork,
he testified that it was only when heavy vehicle traffic
began pounding the construction joint on Broadwater
Road opposite his residence that he began to observe
real damage. As the claimant explained it, the opening
of the new Robson Bridge had the effect of redirecting
the flow of truck traffic past his residence that previously
went through downtown Castlegar -- much of it enroute
to a major pulp mill in the area. At first, the claimant
testified, he experienced light bulbs blowing out, floor
tiles in the recreation room beginning to lift, and
ceiling tiles beginning to sag. He began to notice the
occasional squeak in the floor and cracks in the joints
of the waterproof deck coating where rain and blowing
snow could enter.
By March of 1995, he said, the greater
volume and speed of this traffic was contributing to
the breakup of the tapered ramps, creating more drastic
"bumping", and in turn, generating vibrations
strong enough to do significant damage to his residence.
According to the claimant, it was after a four square
foot section of exterior stucco near the main entry
door to his residence fell off, on or about March 15,
1995, that the claimant telephoned the respondent's
highway manager to complain. By early April, he said,
hairline cracks that had formed around the door frames
and windows some time after the construction joint was
initially created had opened drastically.
At the outset of the hearing the claimant
submitted that his claim for compensation for damages
to his residence on Lot 21 was in the sum of $16,650
together with an additional 10 per cent or $1,666 for
inconvenience. The claimant later sought to put in evidence
three contract proposals he had obtained for repairing
the damages to his residence. However, the respondent
objected to the admissibility of those proposals unless
the contractors who had prepared them were made available
for cross-examination. Ultimately, two of those contractors
attended at the hearing as witnesses and were qualified
as experts in the field of house construction and repair.
Their contract proposals were entered in evidence.
The first witness, Harold Nevokshonoff
of Nevo Construction Ltd., had prepared a contract proposal
dated December 4, 1996. It proposed to replace existing
carpet and vinyl flooring as well as 3/8 inch plywood,
screw down the flooring in the entire house, fill cracks
in and repaint the walls and ceilings, seal joints in
and repaint the sundeck, and replace the stucco which
had fallen off. The quoted price for this work was $10,200.
Mr. Nevokshonoff appeared to have little recollection
of the nature and extent of the damage, did not provide
a breakdown of the costs of these various items, and
was not certain whether the quotation included an amount
for goods and services tax.
The second witness, Mike Makordoff
of Shermak Construction Co. Ltd., had provided a proposal
dated December 2, 1996. His quotation included repairing
the stucco where required, filling and sanding all cracks
on the walls and applying one coat of paint to those
areas, and sealing the joints on the sundeck floor and
walkway and applying a coat of spantex. Mr. Makordoff's
proposed remedial work to the floors differed from that
of Mr. Nevokshonoff. With respect to the carpeted areas,
his proposal was to remove all underlay and carpet,
install black building paper under 3/8 inch plywood,
screw down the plywood to the existing joists, and then
reinstall (but not replace) the underlay and carpet.
With respect to the existing linoleum, Mr. Makordoff
proposed installing 3/8 inch plywood over the affected
areas, screwing the plywood down to the existing joists,
and laying new linoleum. The quoted price was $16,000
plus goods and services tax of $1,120 for a total of
$17,120. Mr. Makordoff testified that, since having
provided the quotation, he had closed his company and
disposed of his business records. Therefore, he also
was unable to give a breakdown of the costs for the
various proposed items of repair.
3.4 The Respondent's
Case
The respondent says the claimant bears
the onus of proving that the observed defects in his
residence were the result of the respondent's roadwork
and not some other underlying factor. According to the
respondent, this is not a situation where the fact of
damage points clearly to its cause. Rather, it is one
where probative evidence is required. In the respondent's
submission, the claimant has failed to adduce such evidence,
either with respect to the state of his residence both
before and after creation of the temporary construction
joint in the highway or with respect to the alleged
impact of traffic hitting that joint. The respondent
says the claimant had every opportunity to marshall
expert evidence on these matters but chose not to do
so.
The respondent's case relies primarily
on the inspection report of Mr. Verigin, who was qualified
at the hearing as an expert in residential wood frame
construction. The respondent submits that the inspection
report provides more plausible explanations than those
offered by the claimant for the various defects observed
in the claimant's residence.
Mr. Verigin testified that his approach
had been to inspect the residence in company with the
claimant, confirm the construction materials and methods
which the claimant said he had used, listen to the claimant's
explanations for the defects noted, and make his own
observations as to their nature and probable cause.
Mr. Verigin said that all investigations under the finishes
of the residence were made with the claimant removing
the finish and that all photographs which appear in
the report were made with the knowledge of the claimant.
No destructive investigations were made and no instrumentation
readings of any kind were taken.
A central focus of the inspection
report was on moisture content in the residence both
during and after its construction. For example, the
report questioned the use of floor joists which had
earlier formed part of a breakwater. The claimant confirmed
that they had been under water for approximately 10
years previously. Mr. Verigin observed that wood in
contact with water evaporating from a water surface
and from the elements such as a wharf would have a high
water content and would need to be adequately dried
before use. Beyond that, the report notes the claimant
had only activated the furnace after the residence was
completed and he and his family had moved in. This was
nearly a year after construction began. According to
Mr. Verigin, it is standard building practice to have
heat in the residence during the later stages of construction
in order to bring all the moisture content of materials
to the same level as that which will occur in the finished
use of the residence. The object is to avoid shrinkage
which could result in lifting of the floor system with
resulting squeaks and cracking at the corners of framed
walls, windows and ceilings.
The report also identifies the claimant's
acknowledged lack of a vapour barrier on the heated
side of insulation next to the drywall finishes as a
likely source of observed defects in the walls and ceilings.
As the report explains it, heated air moving to the
exterior would result in condensation in the wall and
ceiling spaces as it came in contact with the cold.
This, in turn, would cause seasonal expansion and contraction
of the finish material as well as the framing. In Mr.
Verigin's opinion, the absence of a vapour barrier in
the ceiling over the workshop, combined with lack of
ventilation of the dead air space between the insulation
and underside of the covered sundeck, would have created
a particularly acute problem. It would, he said, have
resulted in a great deal of movement in the joists,
shiplap and underlay, undermining the integrity of the
joints in the waterproof membrane on the deck and perhaps
also causing the ceiling finish in the workshop to fail.
Mr. Verigin reported that the claimant told him cracks
had already developed in the joints of the spantex waterproofing
in 1989 and that he had simply applied more spantex
over the failed joints without further preparation.
According to Mr. Verigin's inspection
report, other faulty construction techniques also likely
contributed to the defects which he observed. His additional
comments on those elements of the residence exhibiting
damage may perhaps best be dealt with in the same order
followed when summarizing the claimant's case.
Although the claimant, as he testified,
may have taken care in pouring the concrete slab in
the basement, Mr. Verigin suggests that the failure
to install an expansion joint where the slab meets the
downstairs hallway to allow for the normal shrinkage
of concrete may account for the lifting of floor tiles
in the recreation room.
With respect to the main floor area,
the unusual practice of nailing the particleboard underlay
through the shiplap directly into the floor joists made
"nail pops" and lifting of the floor more
probable with shrinkage of the joists.
With respect to the sundeck, failure
to follow the customary practice of either providing
drains in the middle of the floor or sloping the deck
to a scupper at the edges left water standing which
over time probably deteriorated the surface.
The vertical cracks which Mr. Verigin
noted at the top of each window indicated to him that
the drywall joint was also located there rather than,
as is normal practice, at a stronger point some distance
over the header. The cracks visible at the edges of
the valances were also said to be, in part at least,
the likely result of lack of proper support in their
construction. As for sagging ceiling tiles, the inspection
report observed that the tiles appeared to be unsupported
at the joint of ceiling to wall.
Mr. Verigin said he was unable to
determine the age of the vertical cracks in the rough
masonry core of the fireplace and the hairline cracks
in the brick facing. However, since the claimant evidently
advised him that it was his practice to "hot fire"
the chimney to remove the accumulation of soot from
time to time, Mr. Verigin concluded that this practice
might be the cause of the cracks. As he explained it,
when chimneys are "hot fired", the temperature
becomes too hot for the normal expansion of the surrounding
masonry.
Finally, with respect to the exterior
stucco, Mr. Verigin stated that he had been told by
the claimant that every corner of the stucco wall already
had a vertical crack prior to the time when the respondent
began its highway construction in the vicinity. According
to the inspection report, such cracks are normal to
a stucco finish in non acrylic applications. Beyond
that, the report suggested that improper mixing and
application of the first or "scratch" coat,
improper bonding of the second coat to the first, and
the absence of a final stucco coat application might
all have contributed to a natural action whereby a portion
of the second coat ultimately failed. Mr. Verigin speculated
that, if the highway construction was the source of
the failure, he would have expected considerably more
of the stucco to have fallen off.
Since Mr. Verigin had not inspected
the residence prior to 1994, he said he could only draw
on his experience of deficiencies in other buildings
constructed under his supervision in order to reach
conclusions as to their likely cause in the present
instance. He testified that, although he had done no
seismic testing, he had turned his mind to the question
of whether vibrations emanating from the highway could
reasonably have loosened structures in the house or
caused it to settle. He reached the conclusion that
this was not a viable explanation in the circumstances.
The respondent submits that, even
if a causal link could be proven between the roadwork
and some elements of damage to the residence, the claimant
has failed to quantify his reasonable damages in such
a way as to make an award of compensation feasible.
Neither of the contractors who provided quotations for
repair and testified at the hearing concerning them
made any allocation of costs as between the various
items of damage claimed. Neither quotation referred
to repair of the masonry core and finish face of the
fireplace while one of them, that of Mr. Nevokshonoff,
contemplated replacement of existing carpet, vinyl flooring
and underlay even though the claimant at the hearing
did not appear to be suggesting that such replacement
was needed. Furthermore, in the respondent's submission,
the claimant's monetary claim for the cost of repair
has failed to make any adjustment either for those pre-existing
defects in the residence which the claimant himself
acknowledged or for any betterment to the residence
which would result. As to the additional claim for 10%
of the cost of repair for inconvenience, the respondent
says this is a claim in the nature of non-pecuniary
damages which is unknown to the law. In support of that
proposition, the respondent cites the judgment of the
British Columbia Court of Appeal in Patterson v.
British Columbia (Ministry of Transportation and Highways)
(1997), 62 L.C.R. 89 at pp. 103-107.
3.5 The Board's Determination
After considering all of the evidence
and argument on the question, I conclude that the claimant
has failed to prove, on the balance of probabilities,
that the observed defects in his residence were the
result of the respondent's roadwork. Because I agree
with the respondent that the claimant has the onus of
proof, it is unfortunate, in my view, that the claimant
did not avail himself of independent expert evidence
concerning his residence and the alleged effect on it
of impact vibrations from the highway. It is also unfortunate,
given the difficulties in presenting a case of this
nature, that the claimant was not legally represented
at the compensation hearing. The claimant had retained
legal counsel from the time of the expropriation but
that counsel had ceased to act two weeks before the
hearing was set to begin. The claimant explained his
decision not to retain new counsel by saying that he
did not wish at that point to do anything which might
delay getting his case before the board.
In reaching my conclusion, I accept
as a general proposition that impact vibrations could
cause damage to a residential structure of the kind
observed here. This is confirmed by John F. Wiss, the
author of "Construction Vibrations: State-of-the-Art"
in the February 1981 number of the Journal of the
Geotechnical Engineering Division, an article tendered
in evidence by the claimant. The author identifies the
type of building, type of soil, distance from the source
of vibrations, and the cumulative effect of vibration
as being among the criteria to be considered. Although
damage is more often the observed result of heavy construction
work such as pile driving and excavation blasts, it
is clear that the action of heavy machinery and of traffic
may also do damage in some circumstances. What is lacking
in the present instance, however, is some evidence to
demonstrate the probability that impact vibrations caused
by trucks hitting a two or three inch high construction
joint in the highway would be transmitted through the
soil with sufficient strength and frequency so as to
cause various items of damage to a residence situated
some 80 feet away.
It is not always the case that expert
evidence is required to prove damage to property associated
with highway construction. In Bill's Frontier Restaurant
Ltd. v. British Columbia (1994), 53 L.C.R. 175 at
pp. 191-192, the board considered a claim for roof repair
to a restaurant building situated in the immediate vicinity
of highway work. The owners' allegation, which was unsupported
by any formal report, was that vibrations from highway
machinery caused the four year old roof to crack from
one end to the other, resulting in leaks and water damage
in the restaurant. However, there was evidence that
the roof had not leaked prior to the time that heavy
machinery was working in the area. Furthermore, the
resident superintendent of the construction project
testified to the presence of heavy caterpillar tractors
and pneumatic compactors weighing from 13 to 40 tons,
working within 30 feet of the restaurant. The anticipated
effect was such that owners, he said, were often warned
of the vibration and were told to remove glasses and
other items from their shelves. He added that he had
known footings to crack as a result of the vibration.
The board found the superintendent to be an informed
and neutral witness and accepted his evidence of the
vibration caused by heavy machinery working close to
the restaurant. It held that the owners in this case
had met the onus of proving their loss and awarded them
compensation for the roof damage. However, in my view,
the Bill's Frontier Restaurant decision is clearly
distinguishable from the present matter both in its
factual context (for example, the proximity of the building
to the roadwork and the nature of heavy equipment in
use) and in the supporting evidence which the owners
were able to adduce.
Only the respondent produced an expert
report in these proceedings and that report set out
alternative explanations for every one of the items
of damage which the claimant has attributed to the respondent's
roadwork. Although some of Mr. Verigin's conclusions
entered the realm of speculation, I found his evidence
on the whole to be well documented and highly persuasive.
In my opinion, the report provides cogent reasons for
not holding the respondent liable, on a balance of probabilities,
for the itemized damages to the residence. The claimant
appeared not always to be in agreement with what Mr.
Verigin reported him as having said, particularly about
earlier defects in the residence -- for example, pre-existing
wall and ceiling cracks, cracks in the waterproof decking,
and cracks in the exterior stucco. However, on such
matters, I prefer the evidence of Mr. Verigin over that
of the claimant. The earlier defects, while not in themselves
fatal to the claimant's case, did create a difficulty
which only better evidence might have helped to overcome.
Because the threshold question of
causation has not been answered in the claimant's favour,
it is unnecessary to consider the second question of
quantum of damage. Assuming that quantum had remained
an issue, however, I have already noted the deficiencies
in the evidence provided by the claimant going to such
matters as the itemized cost of repair and any adjustments
for pre-existing defects and for betterment. What has
not been noted thus far, but should perhaps be added,
is that the two contractors called to testify by the
claimant about their quotations for repair were not
especially helpful to the claimant's case, particularly
when under cross-examination. They tended, in fact,
to support Mr. Verigin's opinions in some matters. Mr.
Nevokshonoff said working with stucco required specialized
skill and he expressed some doubt as to whether the
claimant in this instance had properly applied the stucco
coats. Mr. Makordoff agreed with the respondent that
it was inappropriate to use wet wood from a breakwater
for floor joists rather than kiln-dried lumber. He also
confirmed the standard practice, not followed by the
claimant, of putting heat in the residence prior to
occupancy in order to dry out the various elements.
Both contractors identified the lack of a proper vapour
barrier in the house as being the possible source of
some of the claimant's problems.
Accordingly, the claimant's claim
for compensation from the respondent in respect of the
defects to his residence situated on Lot 21 is denied.
4. REDUCTION IN VALUE TO
THE LIFE ESTATE IN LOT 20
4.1 Scope of the Claim
At the outset of the compensation
hearing, the claimant asserted two distinct monetary
claims arising out of his interest as the registered
owner of a life estate in Lot 20. The first claim was,
in effect, for the reduction in market value of Lot
20 which the claimant says was diminished by $4,000
as a result of the respondent's highway project. The
second claim was for damage to the mobile home on Lot
20 occupied by his daughter. The amount claimed by the
claimant in this respect was $1,850.
The respondent took issue with the
claimant's assertion of a claim in respect of the mobile
home. In the respondent's submission, this claim was
encompassed within the partial settlement which occurred
shortly before the hearing began. The claimant, as I
understood him, ultimately agreed that this was the
case and did not pursue the claim. Accordingly, the
claim to be determined is based simply on reduction
in market value as described above.
4.2 The Issues
Potentially, several issues for determination
arise from the claimant's claim for compensation in
respect of his life estate in Lot 20. First, since the
parties agree that the respondent did not take any steps
pursuant to the Act to expropriate Lot 20 or any part
of it, the threshold question becomes whether in these
circumstances there is any right to compensation. This,
in turn, appears to require a consideration of section
40(6) of the Act. Second, assuming there is a right
to compensation, does the claimant's life estate have
a market value? Third, if it does, is there evidence
to prove that there has been a reduction in that value?
Finally, does the evidence show, on a balance of probabilities,
that any such reduction was caused by the respondent's
highway project in the vicinity?
4.3 The Claimant's Case
Since at the compensation hearing
the claimant himself did not address a number of the
issues identified above, I have referred where necessary
to his Form A application. With respect to the threshold
question of entitlement to compensation, it would appear
that the claimant relies on the assertion that Lot 20
and Lot 21 as well as Lot 22 are adjoining and contiguous
and are used for residential purposes by the claimant
to provide homes for himself and his family. Presumably,
these allegations of fact form a basis for contending
that the claimant's case falls within section 40(6)
of the Act which provides:
40. |
(6) |
For
the purposes of this section, expropriation of
part of the land of an owner occurs only if |
|
|
(a) |
he or she retains
land contiguous to the expropriated land, or |
|
|
(b) |
he or she owns
land close to the land that was expropriated,
the value of which was enhanced by unified ownership
with the land expropriated. |
The claimant did not suggest that
his life estate interest in Lot 20 was marketable in
the conventional sense, nor did he commission a market
appraisal of that interest. He appeared to be proceeding
in the belief that the life estate provided him with
some reversionary right to the fee simple of Lot 20
should his daughter predecease him.
With respect to the claimant's claim
that his interest in Lot 20 has been reduced in value
as a result of the expropriation from Lot 21 and the
construction of the works by the respondent, the Form
A makes reference to a number of alleged consequential
effects. These include more difficult, dangerous and
restricted access, loss of privacy, the loud and constant
noise of increased heavy truck traffic, the adverse
effect of a high and unsightly gravel bank replacing
previous views of forest and the Columbia River, and
the impact of the respondent's future snow removal activities
and use of chemicals on or near the highway. It is also
alleged that the expropriation, in addition to resulting
in a smaller parcel size for Lot 21, adversely impacts
the usability, developability and value of the other
lands owned by the claimant's family, including Lot
20.
The claimant produced in evidence
a copy of a decision notice issued by the court of revision
with respect to the 1996 property assessment for Lot
20. Originally the assessment had been fixed at $40,900
for the land and $37,700 for the buildings resulting
in a taxable value of $78,600. On appeal by the claimant
the court of revision reduced the assessment to $38,400
for the land and $36,200 for the buildings resulting
in a taxable value of $74,600. It is the $4,000 difference
between the original and revised assessments on which
the claimant relies in his claim for reduction in market
value.
4.4 The Respondent's
Case
The respondent contends that, because
there has been no expropriation from Lot 20, no compensation
is payable in relation to the claimant's claim for reduction
in market value to his life estate. What occurred in
this instance was a partial taking of Lot 21 and, according
to the respondent, any claim for compensation with respect
to Lot 20 must first meet one of two alternative tests
set out in section 40(6). The respondent submits that
neither test is met. First, although it is an agreed
fact that Lot 20 is contiguous to Lot 21, the respondent
says that Lot 20 is not contiguous to the expropriated
portion of Lot 21 and therefore fails to satisfy section
40(6)(a). The respondent relies on the following interpretation
of "contiguous" provided by the Manitoba Court
of Queen's Bench in Re Municipal Act Re Assessment
Appeal of Vermeulen (1958), 65 Man. R. 308 at p.
312:
Contiguous must be given its ordinary
meaning which is "touching, in contact; meeting
or joining at the surface or border; in actual contact."
Second, although Lot 20 is close to
the land that was expropriated, satisfying the first
part of section 40(6)(b), the respondent says there
is no evidence that its value was enhanced by unified
ownership with the land expropriated. Therefore, the
second part of that test is not met. The respondent
relies on discussion of the applicable principles by
the Judicial Committee of the Privy Council in Sisters
of Charity of Rockingham v. The King (1922), 67
D.L.R. 210.
The respondent casts doubt on whether
a life estate such as that held by the claimant in Lot
20 has a market value in the sense that such an interest
could be sold or traded. Even if it does, the respondent
submits there is no useful evidence here upon which
to value that interest or any alleged reduction in its
value that is directly attributable to the taking or
that has resulted from the construction or use of the
works for which the expropriated land was acquired.
As in the case of damages to the residence, the respondent
says the claimant has failed to discharge his onus of
proof. Although the claimant could have instructed an
appraiser to consider the question, no appraisal evidence
was produced.
According to the respondent, the only
evidence of quantum, which is that derived from the
decision of the court of revision, should be accorded
no weight. That decision, the respondent maintains,
related only to the re-assessment of Lot 20 for taxation
purposes, had nothing to do with the life estate interest,
and provided no indication as to why the taxable value
was reduced by $4,000.
4.5 The Board's Determination
I have concluded that, whether or
not the claimant at law has a right to compensation
under section 40(6), his claim arising from an alleged
reduction in market value to his life estate in Lot
20 cannot succeed in any case because of a lack of probative
evidence on the valuation issues involved.
That being so, it is not strictly
necessary for me to decide whether, for the purpose
of section 40(6)(a), Lot 20 could be said to be "contiguous"
to the expropriated land. In that respect I would merely
observe that there is some case authority to suggest
that the language of that provision may be given a broader
interpretation in the expropriation context than that
adopted in Re Vermeulen: see Wilson v. City
of Sudbury (1971), 1 L.C.R. 37( Ont. L.C.B.) at
pp. 381-2; McPhail's Equipment Co. v. Surrey (City)
(1995), 57 L.C.R. 57 (B.C.E.C.B.) at pp. 67-69.
Equally, it is unnecessary to decide
whether, for the purpose of section 40(6)(b), the value
of Lot 20 could be said to have been enhanced by unified
ownership with the land expropriated. Given the nature
of a life estate, it is at least arguable that Lots
20 and 21 are held under something like unified ownership
and that some increment of value to Lot 20, reflected
perhaps in highest and best use, results from its combination
with Lot 21. However, the question of enhanced value
is one upon which, in my view, relevant valuation evidence
would be needed.
On the question of valuation, I am
satisfied from my reading of appraisal authorities that
the claimant's interest in the nature of a life estate
possesses value, although not for the reason indicated
by the claimant. As I endeavoured to point out during
the hearing, the claimant was mistaken at law in his
apparent belief that the value of his interest derives
primarily from his right to fee simple ownership in
the event his daughter predeceases him. In that case,
I am of the view that the fee simple would pass in accordance
with the terms of his daughter's will or, alternatively,
in accordance with the law of intestacy.
A "life estate" has been
defined as "the total rights of use, occupancy,
and control, limited to the lifetime of a designated
party" who is referred to as the "life tenant":
see Appraisal Institute, The Appraisal of Real Estate,
Canadian Edition (1992), p. 114. Where the life tenant
is in occupation of the property and pays no rent, the
value may be based on rent savings to the tenant over
the tenant's predicted remaining life, using actuarial
tables and an appropriate discount rate. Life estates
can be mortgaged. There may also be income accruing
to the holder of a life estate from the property. The
curious feature of the life estate enjoyed by the claimant
in this instance is that there was nothing to suggest
that the claimant has actually exercised the rights
of use or occupancy over Lot 20. That property appears
to have been exclusively occupied and used by his daughter
since the late 1980s. Nevertheless, the life estate
undoubtedly gives the claimant a large measure of actual
control over Lot 20 during his lifetime, including the
prospect of occupancy and use should he so wish in the
future.
What is at issue here is the "market
value" of the claimant's interest, as that term
is defined in the Act, and any reduction in that value.
Section 32 of the Act provides:
32. |
The market value
of an estate or interest in land is the amount
that would have been paid for it if it had been
sold at the date of expropriation in the open
market by a willing seller to a willing buyer. |
Although I am inclined to agree with
the respondent that there is likely not much of a market
for life estates in the real world, this does not preclude
a market valuation using accepted appraisal techniques.
The definition of market value in the context of an
expropriation presupposes the presence of notional buyers
and sellers in a notional open market. As I understand
it, the appraiser would normally proceed to estimate
the market value of Lot 20 as its unencumbered fee simple
value but, because in this instance the property is
encumbered by a life estate, the market value of the
fee simple interest would necessarily be discounted.
The difference between the encumbered and unencumbered
fee simple value would represent the market value of
the life estate. A similar appraisal exercise might
be undertaken to estimate any reduction in market value
such as has been alleged in this instance.
Unfortunately for the claimant, his
claim for reduction in market value of his life estate,
however small, appears not to have been referred to
a qualified expert in real estate appraisal for consideration
and, consequently, no appraisal evidence was produced.
The only evidence brought to bear on the issue of valuation
by the claimant is the property assessment information
contained in the decision of the court of revision.
I agree with the respondent that this information is
not a reliable indicator of fee simple market value
and is no indicator at all of the market value of a
life estate. There is also a complete absence of evidence
to link the downward revision in taxable value of Lot
20 by the court of revision to the impact of the respondent's
highway project. As for the various alleged negative
impacts of that project set forth in the claimant's
Form A, no evidence was led at the hearing to support
those allegations.
For all of the foregoing reasons,
the claimant's claim for compensation for reduction
in market value to this life estate in Lot 20 is denied.
5. INTEREST
Because the claimant has been awarded
no compensation for the two claims which he pursued
to hearing -- damages to his residence and injurious
affection to his life estate -- it follows that no interest
is payable by the respondent to the claimant with respect
to those claims under section 46 of the Act.
6. COSTS
As I indicated earlier, the parties
have not settled the issue of costs. The claimant maintains
his claim for reasonable legal, appraisal and other
costs necessarily incurred for the purpose of asserting
his claim for compensation or damages pursuant to section
45 of the Act. The claimant, in pursuing his claim,
ultimately succeeded in obtaining through settlement
additional compensation beyond the amount of the initial
advance payment. Nevertheless, the claimant having failed
to obtain an award of compensation with respect to those
remaining claims which he pursued to hearing, I am of
the view that section 45(5) applies to this matter,
giving the board a discretion as to costs. In my opinion,
those claims should never have been brought before the
board without better evidence and preparation. However,
neither party addressed the issue of costs during the
compensation hearing, and I am reluctant to fix an award
in all of the circumstances without first giving the
parties an opportunity to present evidence and argument
on point. Accordingly, I make no order as to costs,
pending a further application should one become necessary.
|