September 17, 2002, E.C.B. Control
No. 33/99/227
Between: |
Gorman Bros. Lumber Ltd. and
Dunfield Holdings Inc.
Claimants |
And: |
Her Majesty the
Queen in Right of the Province of British Columbia
as Represented by the Minister of Transportation
and Highways
Respondent |
Before: |
Sharon I. Walls,
Vice Chair
Diane M. Delves, AACI, P.App., Board Member
Martin A. Linsley FCA, FCIP, CBV, Board Member |
Appearances: |
Robert S. Cosburn,
Counsel for the Claimants
Alan V.W. Hincks, Counsel for the Respondent |
REASONS FOR DECISION
1. INTRODUCTION
[1] The claimants, Gorman
Bros. Lumber Ltd. and Dunfield Holdings Inc., are related
companies that operate a sawmill operation in Westbank,
British Columbia. It is a family run business that began
in 1951 with two brothers, Ross and John Gorman. At
the time of the hearing it had 270 employees plus almost
200 people involved in logging operations on a subcontractor
basis. There was evidence that in recent years (during
the 1990's) the mill site had expanded production from
close to 60 million board feet per year to close to
90 million board feet per year, an increase of approximately
50%.
[2] In this decision we
have generally referred to the two claimants collectively.
In the early 1990's the lumber mill operation was located
on two lots, the mill site on the north-west side of
Highway 97, and the subject property on the south-east
side of Highway 97 that was used for storage of chips,
sawdust and lumber. The mill site was owned by the claimant
Dunfield Holdings and leased to the claimant Gorman
Bros. which ran the sawmill business. The subject property
across the highway from the mill site was owned by the
claimant Gorman Bros. Beginning in 1994 the claimant
Gorman Bros. had leased approximately one hectare (2.5
acres) on a third property that was adjacent to the
west boundary of the mill site and owned by Mr. Doerr.
The claimants used the leased land on the Doerr parcel
for log storage. In June 1997 the claimant Dunfield
Holdings purchased the entire 23.5 hectare (58 acre)
Doerr parcel and used a portion of it for log storage
and lumber storage.
[3] The respondent, Her
Majesty the Queen in right of the Province of British
Columbia as represented by the Minister of Transportation
and Highways and the Ministry of Transportation and
Highways, (the "Ministry") required 0.965
hectares (2.385 acres) of the lot on the south-east
side of Highway 97 (the "subject property")
for a new Glenrosa interchange and overpass on Highway
97 (the "project"). This partial taking under
the Expropriation Act, R.S.B.C. 1996, c. 125
(the "Act") occurred on February 11, 1999.
The work on the project occurred in the summer of 1999
and was completed by November, 1999.
[4] Although the taking
and the project occurred in 1999, preliminary design
work on the project had begun a decade earlier in 1989.
In 1993, the design for the project contemplated the
acquisition of the whole subject property on the south-east
side of Highway 97. However, the project was suspended
in 1993 and again in 1996 for budgetary reasons. When
the project was reinstated in 1997, the value engineering
assessment and review released in February 1998 recommended
a design for the project that required only a partial
acquisition of the subject property.
[5] The claimants' purchase
of the Doerr parcel in June 1997 was at an agreed sale
price of $2,000,000. The claimants say that although
the project was on hold when they were negotiating this
sale, the Doerr parcel was purchased to provide replacement
land near the mill site for the subject property. At
this time they understood that when the project was
eventually built, the whole of the subject property
would be required. When Mr. Doerr insisted on selling
his land in 1997 the claimants say that as a result
of the anticipated effect of the project on their business
they were required to acquire the entire Doerr parcel
for a price that was greater than its market value.
The claimants claim the amount that they have paid for
the Doerr parcel that they say was in excess of its
market value.
[6] As a result of the
project, the claimants lost direct legal access from
Highway 97 to both the subject property and the mill
site. With respect to the subject property direct highway
access has been replaced by access via the new Glenrosa
overpass that is part of the project.
[7] The claimants say that
the more significant effect is the loss of direct access
to the mill site from Highway 97. Before the project
all traffic for the mill could turn from the highway
into a large driveway near the office building. From
the entrance driveway there were different routes for
different types of vehicles. Following the project,
access to the mill site required an exit from Highway
97 via the new interchange that was part of the project
and the new Glenrosa Road. However, there was no road
access from Glenrosa Road to the mill site and the Ministry
owned the land between Glenrosa Road and the mill site.
This land had previously been residential lots to the
north of the mill site that had been acquired by the
Ministry as a result of the project and were surplus
to the Ministry's requirements. The new mill access
had to be built across this surplus land. There was
some discussion from the beginning that the claimants
might acquire some of this surplus land in part exchange
for the subject property and one of the uses for the
surplus land would be to supply replacement access.
However, in the end, the partial taking was expropriated
and an advance payment was made without any land exchange.
Late in the day the Ministry offered the claimants a
choice: the Ministry would retain the surplus land (at
least for some time) and build a public road across
it to the mill site with an entrance near the existing
office building or the Ministry could sell the surplus
land to Gorman Bros. so that it could build a private
road across this land and incorporate the remainder
of the surplus land into its mill site.
[8] In March 1999, the
claimants chose to acquire the surplus land described
as the consolidated exchange parcel and to construct
a new access driveway to its existing office building
over this parcel. The parties agreed on a formula for
establishing the price for the consolidated exchange
parcel and this sum is not at issue. The claimants state
that the access route to the mill site now results in
the mixing of industrial and civilian traffic and in
response to safety concerns the claimants wish to construct
a new office building near the new entrance to the site.
They claim for the depreciated cost of the old office
building which will be redundant and torn down.
2. THE CLAIM FOR COMPENSATION
[9] The claimants are making
the following claims for compensation:
1. |
market value of the partial
taking and injurious affection to the remainder
of the subject property |
$ 232,500.00 |
2. |
compensation for the purchase
of the Doerr parcel that is in excess of market
value |
$ 820,000.00 |
3. |
compensation for
the depreciated value of the office building |
$ 640,000.00 |
4. |
disturbance damages
or business losses for various expenses arising
from the taking including |
|
|
Reid Crowther engineering
invoices |
$ 38,969.73 |
|
John MacDonald legal
invoices |
$ 26,543.64 |
|
Emil Anderson road construction
invoices |
$ 34,094.45 |
|
Pro rata Property Purchase
tax (PPT) for Doerr parcel |
$ 15,580.00 |
|
PPT for consolidated
exchange parcel |
$ 7,220.00 |
|
miscellaneous expenses |
$ 57,239.25 |
|
Total |
$1,872,147
rounded |
[10] The respondent has
made the following advance payments:
1. |
market value of
the partial taking and injurious affection to
the remainder on February 9, 1999 |
$ 119,000.00 |
2. |
compensation for
the purchase of the Doerr parcel that is in excess
of market value including pro rata share of PPT |
nil |
3. |
compensation for
the depreciated value of the office building |
nil |
4. |
disturbance damages
for various expenses |
|
|
payment
made for the lawyer John MacDonald's invoice dated
September 9, 1999 on October 22, 1999 |
$
1,832.79 |
|
payment
made for some Reid Crowther engineering invoices
from 1999 on April 11, 2000 |
$
6,038.10 |
|
Total |
$126,870.89 |
The Ministry also paid monies or provided
credits as part of two settlements with the claimants:
one made in 1996 when the project had been put on hold
for a second time and the other made in 1999 for the
agreed value of the consolidated exchange parcel minus
the cost of constructing a public road. In addition,
at an earlier stage, there were claims by Ron and Jenifer
Gorman and Ross and Eunice Gorman whose personal land
had also been affected by the project. (Ron Gorman is
the son of Ross Gorman one of the two brothers who founded
the business in 1951.) The two couples own parcels of
land to the north of the mill on which they reside.
These claims have also settled.
3. THE ISSUES
[11] One of the issues
in this case on which there was considerable difference
of opinion was the market value of the partial taking
and injurious affection to the remainder of the subject
property.
[12] At the heart of the
two other main issues in this case -- the loss on the
purchase of the Doerr parcel and the loss on the existing
office building -- was the tension between the uncertainty
surrounding the project over a ten year period at the
same time as the claimants' business was expanding.
During this time the project was put on hold twice,
once for over two years and the second time for approximately
a year. There were changes in the interchange design
over the ten years and in the end it became one of the
first Design/Construct projects built by the Ministry.
This meant that uncertainty about the design and the
necessary requirements continued until after the project
was completed. We accept that the protracted delays
and changing requirements created considerable uncertainty
and inconvenience for the owners of properties that
were to be taken, including the claimants.
[13] During much of this
period when the project was under consideration the
sawmill business of Gorman Bros. was expanding. We were
told that production had expanded by approximately 50%
during the 1990's. The claimants submit that the acquisition
of both the Doerr parcel in 1997 and the consolidated
exchange parcel in 1999 were made necessary because
of the project. However, because of the significant
increase in the number of board feet produced per year,
the claimants also needed more land to store both logs
and lumber. There were also changes in the Forest Practices
Code that required more storage space for logs. It is
difficult to separate out those threads of causation
that were to do with the partial taking of the subject
property and the changes in access on the one hand (especially
when the circumstances surrounding these two factors
kept shifting), from the desire for the claimants for
more land. As a result, the circumstances and events
over the 10 year period have to be carefully reviewed.
[14] Thus, the issues of
the claims in relation to the purchase of the Doerr
parcel and the existing office building both depend
on causation and whether the claimants are entitled
to compensation from the respondent under sections 34
or 40 of the Act. Were the purchases of these properties
directly attributable to the partial taking or the disturbance
or did they result from the construction or use of the
works for which the land was expropriated? Or was there
another explanation? If the purchases were due to the
taking or the project, have the claimants suffered any
losses?
[15] There are also substantial
claims for other expenses and losses, many of which
relate to the purchase of the Doerr parcel or the consolidated
exchange parcel. Other expenses and losses relate to
the subject property and to access issues more generally.
Similarly these claims depend on whether they are due
to the partial taking or the disturbance or the project.
4. BACKGROUND
[16] During the hearing
we heard extensive evidence from Doug Tracey, who was
the Project Manager for the claimants. There were also
a large number of relevant documents in evidence.
4.1 Property
[17] The subject property
on the south-east side of Highway 97 from which the
partial taking was made is legally described as:
PID 024-225-967
Lot A
District Lots 3188 and 4056
Osoyoos Division, Yale District
Plan KAP62186
[18] The parcel was irregular
but approximately triangular in shape with Highway 97
running along the hypotenuse. Before the taking the
subject property was 3.69 hectares (9.118 acres). The
partial taking from the northern part of the parcel
was 0.965 hectares (2.38 acres), leaving a remainder
of 2.725 hectares (6.74 acres).
[19] Before the taking
there was a small area of about 0.2 hectares (0.6 acres)
of the subject property bordering the highway that was
at grade with the highway. This area was about midway
on the subject property's highway frontage. It was opposite
the access to the claimants' mill site, and served as
the access to the subject property from the highway,
as well as storage area for wood chips. Mr. Parkhill,
the claimants' appraiser, described this as the highway
sector. There was also a bench area, approximately 1.6
hectares (4.0 acres) in size, located about 11 metres
(35 feet) above the highway. This bench, which the claimants
used for the storage of lumber, was reached by a winding
internal driveway. There was evidence that certain types
of wood needed to be air dried and that this bench was
suitable for air drying. Mr. Parkhill called this the
high utility sector. The remaining 1.8 hectares (4.5
acres) of the subject property consisted of steep slopes
that had limited use and was therefore known as the
low utility sector.
[20] Most of the subject
property is zoned I-3, Forest Industrial, but 20% of
the subject property that forms a strip along the southern
boundary, very approximately 40 metres by 175 metres
(and with no highway frontage), is zoned C-4, Service
Commercial. In the Official Community Plan (OCP) the
whole of the subject property was designated Industrial.
There were services available at the boundary of the
subject property but for sanitary sewer and Reid Crowther
estimated $35,000 to extend the sewer to the property.
There would also be some cost to hook into the gas pipe
line that crossed the property.
[21] There were a number
of legal encumbrances registered on the subject property.
There was a BC Gas right of way through the southern
portion of the subject property. This right of way prevented
construction or placement of any type of structure or
pavement on the right of way. There also was a 15-foot
wide right of way for the Westbank Irrigation District
that ran east-west in the northern portion of the subject
property. This right of way prevented any permanent
structures on the right of way. There was a 20-foot
easement running along part of the western boundary
of the subject property from the mid point where the
subject property has access to Highway 97 to the south-western
corner. This easement was to provide access to the lot
to the south of the subject property but was never constructed
because the topography was too steep. The internal driveway
from the highway access to the bench area was used instead.
4.2 Project
[22] As indicated above, we heard
evidence that there was preliminary design work for
an interchange at a position slightly to the north of
the eventual interchange as early as 1989, although
it was not pursued at that time because of public opposition.
In 1990, Urban Systems Ltd., a consulting engineer firm,
was retained by the Respondent to examine other possible
locations. As early as 1991 the Urban Systems Ltd. design
using the location of the interchange that was eventually
built showed that the whole of the subject property
would be required. Further work was done on this design
but in May 1993 the project was suspended for budgetary
reasons. In September 1995 the project was reinstated
and the design was updated. The design still showed
that the entire subject property would be required.
In June and July 1996 it was again determined that the
project would not proceed for budgetary reasons. In
April 1997, funding for the project was restored to
complete the design and to finish acquiring the necessary
properties. In February 1998, a value engineering report
of the project recommended a design that required only
a portion of the subject property. In August 1998 the
Respondent determined that the project would be built
using the Design/Construct method, which meant that
the contractor was responsible for both the design and
the construction to approved Ministry standards. This
allowed the project to be fast tracked as some aspects
of construction could start before the final detailed
design was complete. Mr. Tracey indicated that they
first found out that only part of the subject property
would be required at an open house meeting near the
end of 1998.
[23] The successful contractor
on the project, Emil Anderson Construction Ltd., was
selected in March 1999 and the project was completed
by November 1999.
4.3 Taking
[24] The partial taking
was 2.38 acres from the northern portion of the subject
property. The land that was taken was zoned I-3 and
included most of the right of way for the Westbank Irrigation
District. It also included a small portion of the easement
along the western boundary that provided access to the
lot to the south of the subject property. According
to Mr. Parkhill the partial taking consisted of the
0.6 acres that were at grade with Highway 97 and provided
access to the subject property as well as 1.78 acres
of the steep low utility sector.
[25] After the taking the
remainder was 6.74 acres. This part of the subject property
was zoned both I-3 and C-4 and contained the BC Gas
right of way. Mr. Parkhill described the remainder as
consisting of the 4.0 acres of the high utility sector
(the bench land used for storage) and 2.74 acres of
the steep low utility sector. However, Mr. Parkhill
indicated that the storage capacity of the remainder
had been increased beyond the pre-existing 4.0 acre
bench as a result of work done related to the project.
The easement that provided access to the lot to the
south of the subject property had to be relocated.
4.4 Claimants' Use
of the Doerr Parcel
[26] The Doerr property
was approximately 58 acres and was adjacent to the western
boundary of the claimants' mill site. Approximately
25.5 acres of the northern portion of the Doerr property
were in the ALR and about 16 acres of this portion were
planted as vineyards. In addition, there was an area
of 4.5 acres in the north-west corner of the Doerr property
that was excluded from the ALR but bounded on two sides
by land that was in the ALR. Thus, approximately 28
acres were outside the ALR and the ALR associated property.
Some of the non ALR property was forested and steeply
sloped such that approximately 10 acres had low utility.
This leaves about 18 acres of the parcel that had some
potential as industrial land being outside the ALR and
outside the steeply sloped area that was eventually
subject to a non-disturbance covenant. In January 1997
it was zoned RU 2 Rural and was designated Rural Resource
on the OCP. The only legal access at that time was a
panhandle about 107 feet in width to Highway 97 at the
south boundary of the property. However, access through
this panhandle was not practical because of very steep
slopes at more than 50% gradient and the presence of
Hardy's Slough, a protected wildlife area. There was
access over crown land via a gravel road that left the
highway 330 feet to the south of the Doerr parcel. However,
this road had a 16% gradient and was not suitable for
tractors or trucks. By agreement, Mr. Doerr historically
accessed his land by using the claimants' logging road
across the mill site.
[27] In June 1989 at a
meeting between the Ministry and Gorman Bros. to discuss
the effect of the project on the claimants, the notes
by someone from the Ministry indicated that the main
problem for Gorman Bros. if the subject property was
taken was the loss of a place for storing wood chips.
The notes also reflected a discussion of a land trade
and Gorman Bros.' intended use of any land so acquired
for parking and lumber storage.
[28] The Ministry presented
plans in June 1991 showing a revised location for the
project in approximately the same place as was eventually
built.
[29] At a subsequent meeting
in June 1991 between representatives of the Ministry
and Gorman Bros. the Ministry's notes of the meeting
report that Gorman Bros. was considering purchasing
part of Mr. Doerr's land and there was a discussion
of Mr. Doerr's difficulties with accessing the property.
The Doerr parcel had originally been owned by Ross Gorman
who continues to own land north of the mill site. The
notes suggest that Ross Gorman had subdivided his land
to create the Doerr parcel in such a way that there
was no practical access for the Doerr property.
[30] In October 1991 at
a meeting between the Ministry, Urban Systems, the consulting
engineering firm retained by the Ministry, and Gorman
Bros., the Ministry's minutes reflect that Mr. Tracey
said Gorman Bros. was interested in acquiring some or
all of the Doerr property depending on cost. Mr. Tracey
went on to report that the Doerr property was currently
for sale at $1,000,000, but that in his opinion it was
overpriced since it was not prime agricultural land,
and even if it was, $550,000-$650,000 would be a more
realistic price. He also said that the claimants needed
more log storage area.
[31] The project was suspended
in May 1993 for budgetary reasons.
[32] In September 1993
Mr. Doerr wrote the provincial Ombudsman complaining
that the postponement of the project meant that the
access that he was going to get from the Ministry was
also delayed. This letter indicates that Mr. Doerr had
been trying to get access from the Regional District
since at least 1990 and that he had an ongoing file
with the Ombudsman about access to his property. In
November 1993, the claimants entered into negotiations
with Mr. Doerr to lease some of his land for additional
space to store logs. The proposed area to be leased
was adjacent to that part of the mill site in which
the claimants already stored logs. Mr. Tracey gave evidence
that the need for more land for log storage was occasioned
by general increases in mill production requiring more
logs and at least two changes in the Forest Practices
Code. In the spring when the ground was wet, there was
a prohibition on equipment entering forest land. During
that time no logs could be cut or removed for transport
to the mill. One of the changes in the Forest Practices
Code was that this break-up period of non-logging in
the spring was lengthened by two months. Consequently,
a greater number of logs had to be stock piled so that
mill production was not slowed down. The second more
minor change in practice involved the procedures for
scaling or measuring the volume of logs that were being
processed. On a random basis the mill must measure the
weight and volumes of a selection of logs in order to
calculate stumpage fees. In order to measure the volumes
of the log sample it must be spread out on the ground.
At one time, as soon as the log sample had been scaled,
the mill could remove the logs and proceed to mill them.
The change required the claimants to leave a sample
spread out on the ground for a certain period of time
so that the Crown could check the mill's calculations.
[33] These changes resulted
in more land for log storage being required. We were
not provided with the specific dates when the changes
became effective. However, the claimants' log inventory
volume more than doubled between March 31, 1993 (about
50,000 cubic metres) and March 31, 1995 (more than 105,000
cubic metres). Volumes on March 31, 1996 and 1997 were
about 87,000 and 100,000 cubic metres respectively.
[34] The documentary evidence
shows that in November 1993 when Gorman Bros and Mr.
Doerr were negotiating a lease of part of the Doerr
land, they also discussed the possibility of the claimants
purchasing the Doerr land. It was reported that Mr.
Doerr was not interested in selling all of the land
at this time. However, he was concerned that if he only
sold the south part to the claimants that he would lose
the only legal access and have no access for the northern
part containing the vineyards. In December 1993 Gorman
Bros. asked the Ministry to inform Mr. Doerr that a
new legal access for his property would be provided
as shown on the plan when the project was completed,
which would provide access to the northern ALR sector.
One week later there was a letter from the Ministry
to Mr. Doerr that referred to a telephone conversation
with him and enclosed a drawing showing the new proposed
property line for his property. The letter went on to
say that the details of relative elevation were not
known and that it was not clear when the funding to
proceed with the project would be in place. This letter
was copied to Gorman Bros. but the evidence was unclear
as to whether Gorman Bros. had ever received it.
[35] As indicated above,
in January 1994, the claimants and Mr. Doerr did enter
into a two year lease for approximately 2.5 acres of
the Doerr land for the storage of logs. This land was
the subject of a temporary industrial use permit and
the rent was $25,000 a year. There was a provision for
a month to month tenancy to continue after the term
of the lease had expired in January 1996 as long as
both parties agreed. There was also a provision for
the claimants to clear the land of all logs and debris
at the end of the lease.
[36] In late July 1995
the project was reinstated.
[37] Beginning in February
1996, since the term of the lease had expired, Gorman
Bros. and Mr. Doerr attempted to negotiate a purchase
of the southern portion of the Doerr land. There were
a number of documents in evidence that detailed the
positions each party took during the negotiations. The
area that Gorman Bros. wished to purchase was 6.46 hectare
(15.96 acre) of non ALR land and included the 2.5 acres
that had been leased. Not all of this approximately
16 acre site was reported to be usable, since there
was some steeply sloped forested land to the south and
west of the usable sections. Mr. Doerr's initial offer
to sell this sector was for $895,000, reduced in stages
to $775,000, while the claimants offered to pay $650,000.
In both parties' offers the purchase price was to be
made over time. There were a number of conditions or
terms in the proposed sale including the following:
- That the property be subdivided and rezoned for
industrial use;
- That new legal access would be provided to the remainder
of the Doerr parcel in connection with the project;
- That the Ministry confirm its intent to acquire
the subject property;
- That Gorman Bros. have a right of first refusal
on the remainder of the Doerr parcel;
- That Gorman Bros. would indemnify Mr. Doerr against
any potential liability.
The documentary evidence indicated
that all the conditions proposed by both parties appear
to have been agreed but for the price. The Ministry
did provide a letter confirming its intention to purchase
the subject property. Meanwhile the Ministry and the
claimants were exchanging correspondence about the potential
for gravel on the part of the Doerr parcel that the
claimants were attempting to buy. The Ministry hoped
to use any gravel that was found for the project and
this possibility was being considered by Gorman Bros.
as a factor in the purchase price. However, these negotiations
were ultimately unsuccessful and broke down in late
May 1996 according to Mr. Parkhill. We were provided
with no details as to the reason for the breakdown.
The lease of the 2.5 acres continued on a month to month
basis.
[38] In late June 1996
funding for the project was frozen pending a capital
program review and the Ministry reimbursed Gorman Bros.
for funds spent to date. It is not clear whether any
of the invoices from appraisers, lawyers and engineers
related to the Doerr parcel.
[39] On March 11, 1997,
Mr. Doerr wrote the claimants that he intended to list
his property for sale and he wanted the leased land
cleared of logs by June 1, 1997. On June 9, 1997 the
claimants made a written offer to Mr. Doerr to purchase
his property for $2,000,000 and a cheque for this sum
was enclosed. A formal agreement of purchase and sale
was signed between the claimant Dunfield Holdings Inc.
and Hans Doerr dated June 11, 1997. It provided for
a sale price of $2,000,000 and was contingent on the
rezoning of all of the land south of the area in the
ALR (approximately 28 acres) to I-3 Industrial. There
was a provision for rental payments to be paid until
closing. Gorman Bros.' application for rezoning to the
Regional District dated June 12, 1997 stated that part
of the land was required for log storage and that the
mill's inventory of logs had doubled since 1993 because
of changes in the Forest Practices Code and increased
production. The land in the ALR would remain as an operating
vineyard. A media release from Gorman Bros. dated June
13, 1997 announced the acquisition of the Doerr lands
and stated that the property was acquired for on site
log storage that was made necessary by changes in the
Forest Practices Code extending the logging shut down
period by two months. Later in the media release Mr.
Tracey added another reason as follows:
"This purchase was also made
expecting that the [project] would eventually occur,
we just did not know when. Our land purchase will
reduce the impact of this project on Gorman Bros.
The announcement of this project resuming, just one
day later, was a real surprise."
[40] In April 1997 the
project received funding again to complete the design
of the interchange and to acquire more properties. It
appears that Gorman Bros. only learned that the project
was going ahead when a public announcement was made
on June 11, 1997.
[41] The purchase of the
Doerr parcel completed on September 30, 1997. One of
the conditions of the rezoning was that a non-disturbance
covenant was registered on title with respect to 8.3
acres that had slopes of 30% or greater of the total
of 28 acres that were zoned I-3. This covenant prohibited
construction or removal of any soil or vegetation of
trees without written consent of the Regional District.
Changes were made on part of the I-3 zoned property
to accommodate more log storage. In the spring of 1999
an area of the I-3 zoned property was also cleared and
levelled for chip or lumber storage but it had only
been used for lumber as of the date of the hearing.
Since the taking, chips have been trucked from the site
on a daily basis and there has been no stockpiling of
chips on the mill site. When the project was finally
constructed during the summer of 1999, the Ministry
did not in the end provide a new access to the Doerr
parcel, presumably because its ownership by the claimants
meant that access could continue through the mill site.
4.5 Access to the
Mill Site and the Consolidated Exchange Parcel
[42] The claimants lost
their existing access to the mill from Highway 97 as
a result of the project. The new access had to be from
Glenrosa Road and the interchange that was part of the
project. A short new road called Dunfield Road, a public
road, was constructed by the Ministry from Glenrosa
Road. This new public road provides access to two new
driveways to the Ron and Jenifer Gorman property and
the Ross and Eunice Gorman property. The claims for
Ron and Jenifer Gorman and Ross and Eunice Gorman have
settled and are not before us. Dunfield Road also provides
access for the mill via a new private road that ends
close to the existing office. The new private road for
the mill site crosses the consolidated exchange parcel
as well as an area of land beside Dunfield Road that
used to belong to Ross and Eunice Gorman called the
panhandle. There is also no claim before us for the
value of the panhandle property.
[43] The consolidated exchange
parcel consisted of surplus residential lots between
the project and the mill site that the Ministry did
not need. The parcel was approximately 1.79 hectares
(4.4 acres). The name that was eventually used to describe
this parcel the "consolidated exchange parcel"
was chosen because at an early stage in the proceedings
there was discussion between the parties that this parcel
might be exchanged for part of the subject property.
In the end, nothing was in fact exchanged. The claimants
asked that the taking of the subject property occur
by formal expropriation and the Ministry made an advance
payment for this partial taking. In turn the Ministry
offered the claimants a choice of two options for access
and the claimants chose to purchase the consolidated
exchange parcel according to an agreed formula.
[44] Before the taking,
the access from Highway 97 to the mill site on the north-west
side of the highway was by means of a large driveway
located beside the office building. Vehicles heading
north had a left turn lane on the highway where they
could wait for a pause in the oncoming traffic. Vehicles
heading south turned right off the highway into the
driveway. All vehicles entered through this driveway.
Visitors to the site could turn left from the driveway
immediately after leaving the highway and park in front
of the office building. Employees drove slightly further
on the driveway and entered a parking lot to the right
and up an incline. Logging trucks drove along the same
driveway past the office building and followed an internal
road that took them to the scales and the log storage
area. Trucks to take away the finished product such
as chips and lumber also entered through the same driveway
and after passing to the right of the office building
followed a different internal road that took them to
the required storage locations. Industrial vehicles
such as fork lifts, loaders and trucks used the internal
road system but had relatively minimal contact with
civilian visitors to the office building.
[45] As we have already
described, the Ministry presented plans for the project
in June 1991 showing the revised location. At the same
time the Ministry began to acquire the 29 residential
properties to the north of the mill site for the project.
From the beginning it was understood that some of these
properties would be surplus to the Ministry's requirements.
In October 1991 the Ministry's minutes of a meeting
with Gorman Bros. report discussion about a possibility
of a land exchange with Gorman Bros. whereby Gorman
Bros. would acquire surplus land north of the mill site
from the Ministry in exchange for the subject property.
Mr. Tracey is reported as saying that some of the functions
located on the subject property, such as parking, lumber
storage, a boneyard for old equipment, and possibly
even the chip storage site, could be relocated to what
would become the consolidated exchange parcel.
[46] The project was suspended
in May 1993 for budgetary reasons.
[47] By the fall of 1993,
the documents show that the Ministry had acquired 25
of a total of 29 residential properties north of the
mill site. Gorman Bros. hoped to lease some of these
properties that had already been purchased by the Ministry
on a temporary basis until the project went ahead. Gorman
Bros. stated that they wished to use these properties
for employee parking and storage of rough lumber and
steel. A rezoning to industrial use was necessary before
this could happen. The three or four residents who had
not yet been bought out by the Ministry (at a point
in time when the project was suspended and it was not
known when it would resume) objected to this. Despite
Gorman Bros.' efforts to negotiate with the neighbours,
it was eventually forced to abandon its plans to rezone
and lease these properties on a temporary basis. Nonetheless,
Gorman Bros. appeared to have been able to use one of
the properties nearest the mill site for storage. In
March 1994 when the project continued to be on hold
Gorman Bros. bought one of these four properties since
the owner wanted to vacate the property. Gorman Bros.
sold this property back to the Ministry in 1996 when
the Ministry once again had funding.
[48] In late July 1995
the project was reinstated.
[49] In February 1996,
there were documents reiterating the proposal for a
land exchange between the claimants and the Ministry.
However, the Ministry stated that it was not possible
to know how much land would be surplus until a grading
plan was done. There were plans from Reid Crowther prepared
at this time showing possible access routes for Gorman
Bros. through the proposed consolidated exchange parcel.
[50] In late June 1996
funding for the project was frozen pending a capital
program review and the Ministry reimbursed Gorman Bros.
for funds spent to date including accounts rendered
by Reid Crowther in the approximate amount of $18,000.
In April 1997 the project received funding again.
[51] In the fall of 1998
the claimants communicated that they wished the required
portions of the subject property to be formally expropriated
(instead of by section 3 agreement or by a land exchange)
but offered to accept the land that would become the
consolidated exchange parcel in place of cash advance
payments. The Ministry decided to follow the Act and
make an advance payment for the partial taking. The
claimants nonetheless pushed the Ministry to sell them
the consolidated exchange parcel. Negotiations about
the transfer of the consolidated exchange parcel continued
for some months. The documents indicate that the Ministry
hoped to use the transfer of the consolidated exchange
parcel as an inducement to achieve final settlement
of the claimants' claim. The claimants in turn pointed
out that the Ministry needed the claimants' co-operation
in providing new easements to the Ron and Jenifer Gorman
property to the north of the mill site and to the Tingstad
property to the south of the subject property. The claimants
indicated that they would cooperate in providing these
easements so long as the Ministry transferred the consolidated
exchange parcel. Later they emphasized that access to
the mill must not be interrupted and the consolidated
exchange parcel was necessary for the access.
[52] Although initial designs
for the new access road used the consolidated exchange
parcel only, by late February 1999 the claimants had
decided that they wanted to add another piece of land
owned by Ross and Eunice Gorman called the "panhandle".
The claimants wanted the new private road to be routed
through the panhandle first, and then through the consolidated
exchange parcel to the former boundary of the mill site.
The use of the panhandle meant that the private road
for the mill site would be longer than if it was through
the consolidated exchange parcel only. However, this
route facilitated access for the two personal properties
owned by Ross and Eunice Gorman and Ron and Jenifer
Gorman as well as providing more land area for the mill
site for uses other than the private road such as employee
parking. The claimants had the engineers Reid Crowther
do several layouts and configurations to determine the
best possible use of the land that was available.
[53] After negotiations
had gone on for some time, on March 12, 1999, the Ministry
decided to offer the claimants a choice. For the first
time the Ministry offered to build a public road across
the consolidated exchange parcel without conveying the
consolidated exchange parcel to the claimants. This
option would not incorporate the panhandle as the claimants
had recently proposed. The second option was that the
claimants could acquire the consolidated exchange parcel
and construct a private road themselves using the panhandle
area as well. Mr. Tracey testified that the plans for
the hypothetical public road that the Ministry offered
to build on the consolidated exchange parcel showed
the road taking up so much room that there was virtually
no land left on either side. And of course in this scenario
the claimants would not necessarily ever acquire the
land left over in any event. On March 26, 1999 the claimants
chose to purchase the consolidated exchange parcel from
the Ministry so that they could build a private road
from the new Dunfield Road through the panhandle and
the consolidated exchange parcel to the former boundary
of the mill site.
[54] The parties agreed
on a formula to establish the net price for the consolidated
exchange parcel. The valuation of the consolidated exchange
parcel was approximately $675,000. From this the parties
have agreed to deduct the value of the land needed for
the hypothetical road on the consolidated exchange parcel
(0.60 hectares or 1.48 acres at approximately $222,500)
and the agreed cost to construct the hypothetical public
road across the consolidated exchange parcel (approximately
$259,000). We note that the a public road such as the
hypothetical public road is required to be wider and
to be built to a higher construction standard than a
private road such as the one that was eventually built
by the claimants. When these amounts were deducted the
net value of the consolidated exchange parcel was approximately
$193,000. We repeat that the formula for arriving at
this sum is agreed and is not before us for consideration.
Gorman Bros. has signed a promissory note dated June
29, 1999 that sets out that any net payment by Gorman
Bros. for the consolidated exchange parcel, as determined
by the formula, is to be made within a certain time
frame following the release of this decision, or an
appeal from this decision. The letters that are attached
to the promissory note state that the claimants agree
"upon the transfer of the consolidated exchange
parcel on the agreed terms that the Ministry has complied
with its obligation to replace the access taken with
reasonable access". The claimants have not agreed
to release other claims; they pointed out that it was
premature to release all claims at this stage before
the Design/Construct project had been built.
[55] The claimants built
the new private road. They had to use considerable quantities
of fill to make the site level with the mill site. Given
the need for large trucks to use the private road the
level of the road was important. The evidence was that
as a result of the Design/Construct approach used in
the project the Ministry had to have more land available
than it eventually needed. The thin strips along the
edge of the highway that eventually turned out to be
surplus were called the "shaded" area. The
parties made an agreement at some stage that the Ministry
would turn over some of this shaded area to the claimants
at a price to be agreed. The claimants built some of
the new access road on this shaded area that they hoped
would be transferred to them in due course. The shaded
area had not yet been transferred at the time of the
hearing because of delays caused by the requirements
of providing rights of way for BC Hydro and other utilities.
Again compensation for the shaded area is not in issue
since the parties have made a separate agreement. However,
there are disturbance damages that are claimed in relation
to the shaded area.
[56] Following the completion
of the project, access to the mill site now requires
vehicles to exit from Highway 97 via the new interchange
that was part of the project. After using the new private
road to cross the panhandle area logging trucks veer
right up an internal roadway to the scales and log storage
area where they unload. Other vehicles turn left after
crossing the panhandle area and continue on the new
private road. Visitors or employees can park in parking
lots on the panhandle and the consolidated exchange
parcel to the left of the private road. Trucks for lumber
and chips travel along the new private road to storage
areas for these products. There is a large new lumber
storage shed, which is located half on the original
mill site and half on the consolidated exchange parcel.
There are also new kilns for drying lumber on the consolidated
exchange parcel. In addition, photos show that there
are large quantities of finished product (lumber) stacked
wherever there is room on both the original mill site
and the consolidated exchange parcel.
[57] The claimants now
state that the long private road through that part of
the mill site that was the consolidated exchange parcel
to the existing office building results in industrial
vehicles mingling with the vehicles of visitors en route
to the office building, or with the visitors themselves,
if they park near the entrance and attempt to walk to
the office building. There was evidence that as many
as 100 trucks a day enter the site; an average of about
50 logging trucks a day (with more in the late fall
and winter when they are building the inventory for
the spring break up season); an average of about 30
trucks a day for chips and an average of 10 trucks a
day for lumber. The claimants say that this mixing of
loaders, fork lifts and trucks with civilian traffic
raises concerns about safety. As a result the claimants
wish to construct a new office building beside the parking
lot near the new entrance to the site.
5. MARKET VALUE OF THE
PARTIAL TAKING
[58] Dennis Parkhill of
Kent-Macpherson Appraisals provided appraisal evidence
for the claimants. The Ministry relied on Reid Umlah
of Hooker, Umlah, Craig, Lum, Real Estate Appraisers
and Consultants Ltd. for appraisal evidence. Both appraisers
used the direct comparison approach to value the property
before and after the taking. The positions of each party,
based on the appraisal evidence, may be summarized as
follows:
|
Claimants |
Ministry |
|
Before |
After |
Before |
After |
Direct Comparison Approach |
$873,500 |
$641,000 |
$456,000 |
$337,000 |
Value per Gross Acre |
$ 95,791 |
$ 95,202 |
$ 50,000 |
$ 50,000 |
Estimate of Compensation |
|
$232,500 |
|
$119,000 |
5.1 Highest and Best
Use
[59] The claimants' appraiser,
Mr. Parkhill, provided a highest and best use for the
4.6 acres of the subject property that was usable (out
of the total of 9.118 acres). In his opinion the highest
and best use of this portion was "the current air
dry lumber and chip storage use, in connection with
the
mill operation" pending redevelopment
"to independent light industrial/service commercial
[use]". After the taking he dropped the service
commercial option as a result of the loss of highway
access. Mr. Umlah, for the respondent, concluded that
the highest and best use for the subject property both
before and after the taking was "for limited and
industrial based uses such as storage and similar ancillary
industrial uses".
[60] Mr. Umlah treated
the subject property as a whole and emphasized the steep
topography and lack of services as constraints on its
use. In contrast, Mr. Parkhill highlighted the two flat
areas of the subject property that were usable before
the taking and the highest and best use of these two
areas if the mill was closed.
[61] Despite the steep
terrain of the subject property, we accept that there
were two significant areas before the taking that were
usable. The smaller of these was at grade with the highway
and formed part of the access, while the other was a
4.0 acre bench area 35 feet higher than the highway
and reached by an internal driveway. We are also satisfied
that the cost to bring the missing services to the property
was in the region of $30,000 to $40,000.
[62] Clearly Mr. Parkhill's
highest and best use depended on the subject property
having good highway access. The existing access permit
dating from November, 1985 stated that it was granted
on condition that the subject property be used for lumber
storage and a 372 square metre fabrication shop only
and that any change in ownership rendered the permit
void. In his report Mr. Parkhill suggested that his
choice of light industrial and service commercial use
did not include those uses that could be categorized
as tourist or retail commercial. Mr. Parkhill conceded
that he had not checked as to the likelihood of a purchaser
acquiring an access permit for his highest and best
use. However, we note that the mill site had an access
permit for the same location on the other side of the
highway and it received more traffic than the subject
property. We are satisfied that the subject property
maintaining highway access on a sale to a hypothetical
purchaser is a reasonable assumption for Mr. Parkhill
to have made.
[63] The respondent submits
that the highest and best use should emphasize the existing
use, given Mr. Tracey's evidence that the subject property
was a vital part of the sawmill's land base. We do not
accept this submission. The market value of the subject
property is defined in section 32 of the Act as the
amount that would have been paid if it had been sold
in an open market by a willing seller to a willing buyer.
The highest and best use of the subject property is
a key ingredient of this hypothetical model and should
not be based on the present owner's needs.
[64] Mr. Parkhill was asked
in cross-examination about the Level 2 Environmentally
Sensitive Area to the south of the subject property,
including the southern part of the subject property
that was zoned C-4. Mr. Parkhill said that he did not
talk to anyone about this because the subject property
already had C-4 zoning. A development permit would be
necessary and possibly a covenant for the designated
area.
[65] Mr. Parkhill noted
that the existing Industrial designation and Industrial
zoning is linked to the claimant's sawmill operation.
If the mill is closed then, in his opinion, it is probable
that the Regional Board would consider a change in zoning
to light industrial or service commercial. He came to
this conclusion after consideration of the location
of the site in relation to downtown Westbank and the
use of other properties in the area. We accept Mr. Parkhill's
opinion on the highest and best use of the two areas
of the subject property that are usable on the appraiser's
assumption.
5.2 Market Valuation
-- Before the Taking
5.2.1 The Evidence
[66] Mr. Parkhill used
14 comparable sales that occurred between February 1993
and December 1999 to obtain an extracted land value
range between $79,835 and $381,818 per acre. After adjustments
for time derived from statistics and a number of paired
sales he obtained a range between $83,096 and $436,738
per acre. Mr. Parkhill considered that different parts
of the subject property had different valuations; the
relatively small section of 0.6 acres beside Highway
97 and at grade with the highway was the most valuable;
the four acres of bench land that were used for storage
were the next most valuable and finally the steep portions
of the lot and the portions encumbered with easements
and rights of way were the least valuable. After considering
size, location, access and relative utility of the comparables
in relation to each of these three sections of the subject
property, Mr. Parkhill estimated the valuation of these
sections before the taking as follows:
Before the Taking |
Highway 97 sector |
0.600 acres @ $250,000 per
acre |
$150,000 |
High utility sector |
4.000 acres @ $162,500 per
acre |
$650,000 |
Low utility sector |
4.518 acres @ $16,250 per acre |
$ 73,418 |
Total market value
estimate |
9.118 acres @
$95,791 per acre |
$873,418
or $873,500 rounded |
[67] Mr. Umlah relied on
8 market sales that occurred between March 1993 and
April 1998. These ranged in value between $34,483 and
$232,564 per acre. Two of these sales were also used
by Mr. Parkhill. After comparing the subject property
to each of these comparables and considering such factors
as size, location and topography, Mr. Umlah concluded
an average valuation of $50,000 per acre for the subject
property. His valuation for the subject property before
the taking was $456,000 rounded.
5.2.2 Analysis
[68] The main difference
between the appraisers is that Mr. Parkhill has identified
those parts of the subject property that are useful,
given them a more valuable highest and best use and
then analyzed the value of each sector separately. Although
he estimates that half of the subject property is worth
very little, his identification of the two sectors that
are usable and his separate valuation of them leads
to a greater valuation for the overall property. Mr.
Umlah's more general approach that does not clearly
identify how much of the land is usable has led him
to a lower valuation.
[69] The respondent submits
that Mr. Parkhill's approach in valuing each of the
three sectors separately appears similar to one that
was rejected by the board in Sequoia Springs West
Development Corp. v. British Columbia (Minister of Transportation
and Highways) (2000), 69 L.C.R. 1 (B.C.E.C.B.) at
para 65. In Sequoia, the claimant's appraiser
"treated the 187 acre subject property as divided
into two theoretical parcels, one of 107 acres for all
the areas with single family lots and one of 81 acres
for the areas of multi-family units". Having made
this hypothetical subdivision of the subject property,
the size adjustments of the claimant's appraiser for
the three selected comparables were smaller than those
of the respondent's appraiser, who was in fact Mr. Parkhill.
The board in Sequoia said that they did not agree
with this adjustment by the claimant's appraiser that
was dependent on dividing the subject property into
two theoretical and smaller parts. The board in its
conclusion of value used the size adjustment of the
respondent's appraiser who treated the subject property
in its entirety as a 187 acre parcel.
[70] In this case, Mr.
Parkhill has treated the subject property as having
three different sectors with respect to use. The respondent
points out that since Mr. Parkhill's adjustments in
the present case (other than for time) are qualitative
and not explicit, it is difficult to ascertain if the
different sectors have been improperly overvalued as
separate parcels of smaller size than the whole 9.118
acre subject property. We agree with Sequoia that what
is being sold is the entire subject property and any
adjustments that are made should reflect this. We note,
however, that Mr. Parkhill's report states that he has
valued each sector as attached to the remainder of the
parcel. He testified that if the 0.6 acre Highway 97
sector had been sold on its own it would have sold at
a higher unit value than $250,000 an acre. His comparables
appear to support this evidence. We accept Mr. Parkhill's
approach as being distinguishable from the approach
that was criticized in Sequoia and find his description
of each sector of assistance in valuing the property.
[71] Most of Mr. Umlah's
comparables have a much higher sale price per acre than
the $50,000 per acre that he concluded for the subject,
five of them having a sale price that exceeded $100,000
per acre. While he indicated that the subject property's
characteristics suggested a somewhat lower valuation
than these comparables, in the end Mr. Umlah has relied
on his analysis of the sale of the Doerr parcel to the
claimants to support his conclusion for $50,000 an acre
for the subject. We disagree with the use of this comparable.
While the Doerr parcel is located near the subject property
on the other side of the mill site, it is dissimilar
in many other respects. We note that the Doerr parcel
is 58 acres compared to 9 acres for the subject property.
Approximately 30 acres of these 58 acres are for agricultural
land use, much of it planted in vineyards. Mr. Umlah
attempts to extract the agricultural sector to arrive
at a value for the 28 acres that he says are similar
to the subject property. But he has failed to make any
adjustments for size or access. Mr. Umlah also failed
to make any time adjustment, although this sale occurred
two years before the date of valuation and one of his
sales occurred six years before.
[72] Mr. Parkhill has valued
the 0.6 acre highway sector that is at grade with Highway
97 at $250,000 an acre. He is not explicit on which
sales he has used as a basis for this valuation. Three
of Mr. Parkhill's comparables were located beside Highway
97 and have highway exposure. One of these, with an
adjusted sale price of $282,796 per acre, was a 0.93
acre parcel that was purchased to form part of a recreational
vehicle sales outlet. The second comparable was a larger
parcel of 3.99 acre with an adjusted sale price of $323,135
per acre. This lot was improved with a building containing
self storage units. The third sale was the 4.4 acre
consolidated exchange parcel that was sold to the claimants
by the respondent at the appraised value of $150,000
per acre. Three of Mr. Parkhill's other comparables
have adjusted values between $252,451 and $272,036 per
acre but these were all relatively small properties,
approximately one acre in size. We are satisfied that
there is sufficient evidence to support a value of $250,000
per acre for the 0.6 acre highway sector that is part
of a 9.118 acre parcel.
[73] Mr. Parkhill valued
the 4.0 acre high utility sector at $162,500 per acre.
The reasons for this valuation were not based on particular
comparables that he thought possessed some similarities
to the high utility sector. Rather he considered the
legal and physical attachment to the highway sector,
direct highway access and exposure and the grade separation
and two of the comparables that exhibited a difference
in their adjusted valuation of approximately 50%, a
difference that Mr. Parkhill attributed to the highway
exposure of the more valuable property. He concluded
that a somewhat higher valuation of 65% of the highway
sector or $162,500 was appropriate for the subject property.
We accept Mr. Parkhill's valuation of the 4.0 acre bench
sector before the taking at $162,500 per acre.
[74] Finally Mr. Parkhill
valued the low utility sector at 10% of the high utility
sector. The respondent submitted that there was no explanation
for this percentage but we acknowledge the difficulties
inherent in valuing this type of land and accept Mr.
Parkhill's valuation.
5.2.3 Conclusion
[75] We conclude that the
valuation of the subject property before the taking
is as follows:
Highway 97 sector |
0.600 acres @ $250,000 per
acre |
$150,000 |
High utility sector |
4.000 acres @ $162,500 per
acre |
$650,000 |
Low utility sector |
4.518 acres @ $16,250 per acre |
$ 73,418 |
Total market value estimate |
9.118 acres @ $95,791 per acre |
$873,500 |
5.3 Market Valuation
-- After the Taking
5.3.1 The Evidence
[76] The partial taking
was 2.38 acres from the northern portion of the subject
property. According to Mr. Parkhill this partial taking
consisted of the Highway 97 sector that was at grade
with the highway and 1.785 acres of the low utility
sector. The remaining 6.733 acres were 4.0 acres of
the high utility sector that were used for storage and
2.733 acres of the low utility sector. Relying on three
comparables, including the consolidated exchange parcel,
Mr. Parkhill estimated the valuation per acre for the
high utility sector at $150,000 per acre or somewhat
lower than the valuation before the taking. He estimated
the valuation of the 2.733 acres of low utility sector
at 10% of the high utility rate or $15,000 per acre.
Thus his valuation of the remaining subject property
after the taking was as follows:
After the Taking |
High utility sector |
4.000 acres @ $150,000 per
acre |
$600,000 |
Low utility sector |
2.733 acres @ $15,000 per acre |
$ 40,995 |
Total market value
estimate |
6.733 acres @
$95,202 per acre |
$640,995
or $641,000
rounded |
[77] Mr. Umlah stated that
in his opinion there was no injurious affection as a
result of the taking. As a result the estimated value
of the remainder was based on the reduction in size.
At $50,000 per acre for 6.74 acres the value of the
remainder was $337,000.
5.3.2 Analysis
[78] The difference between
the two appraisers' valuation after the taking is that
Mr. Parkhill thinks the remainder has been injuriously
affected by its loss of highway access whereas Mr. Umlah
says that there has been no injurious affection. In
addition, Mr. Parkhill's categorization of the subject
property into zones means that the loss of specific
sectors is reflected in the value of the remainder.
[79] The loss of the highway
access primarily affected the 0.6 acre highway sector
that was at grade with the highway. However, since the
entire 0.6 acre highway sector area was taken, the value
of the remainder after the taking reflects the loss
of the most valuable part of the subject property, which
derived its value from the highway access. With respect
to the existing use as a storage site for the mill Mr.
Parkhill comments that the new access using the overpass
now involves a longer return trip: 4,500 feet between
the mill site and the remainder, compared to 500 feet
before the taking. However, we note that the new access
is approximately at grade with the 4.0 acre bench and
does not involve transport trucks crossing four lanes
of highway traffic.
[80] There was evidence
that the 4.0 acre bench area was extended on both the
east and west boundaries as a result of cut and fill
work done by the claimants or Emil Anderson in connection
with the project. We understood that the usable area
after the work on the remainder was approximately similar
to the total usable area before the taking (4.6 acres).
Mr. Parkhill described the industrial utility of the
remainder considering the post-taking site fill and
preparation as excellent. This expanded bench area was
not valued by Mr. Parkhill. In our opinion this expanded
bench area should be valued because the expansion occurred
at least in part as a result of work that was part of
the project. We do not have the exact areas for the
expansion of the bench on the east and west boundaries.
Doing the best we can we estimate that 4.2 acres of
the remainder should be valued as the high utility bench
area.
5.3.3 Conclusion
[81] We conclude that when
the subject property is valued in separate zones, the
value of the remainder after the taking is
High utility sector |
4.2 acres @ $150,000 per acre |
$630,000 |
Low utility sector |
2.533 acres @ $15,000 per acre |
$ 37,995 |
Total market value
estimate |
6.733 acres |
$667,995
or $668,000 rounded |
5.4 Market Valuation
of the Partial Taking and Reduction in Market Valuation
5.4.1 The Evidence
[82] Mr. Parkhill's valuation
of the land taken together with reduction in market
value to the remainder was:
Estimated valuation before
the taking |
$873,500 |
Estimated valuation after the
taking |
$641,000 |
Value of the land taken and
reduction in value to the remainder |
$232,500 |
[83] Under subsection 40(3)
of the Act, the minimum compensation is the ratio of
the area of land taken to the total land area before
the taking times the market value of the land before
the taking. This calculation yields $228,482 (2.385
acres / 9.118 acres x $873,5000). Under subsection 40(5)
the calculation for the minimum compensation may be
adjusted to take into account that some of the land
is more valuable or less valuable than the average value
of the land that was not taken. Mr. Parkhill made the
following valuation of the taking under subsection 40(5)
using the per acreage values for each sector:
Highway 97 sector |
0.600 acres @ $250,000 per
acre |
$150,000 |
Low utility sector |
1.785 acres @ $16,250 |
$ 29,006 |
Valuation of the
taking |
|
$179,006
or $179,000 rounded |
This calculation takes into account
that while some of the land taken was from the most
valuable sector, other land taken was from the least
valuable sector. Mr. Parkhill's valuation of the land
taken and reduction in value to the remainder after
the taking at $232,500 is greater than the minimum compensation
for the land taken only at $179,000. As a result his
final valuation of the land taken and reduction in value
to the remainder after the taking is $232,500.
[84] Since Mr. Umlah has
concluded that there was no injurious affection, his
final conclusion of market valuation of the partial
taking and reduction in market valuation of the remainder
is based on the reduction in size of the subject property.
When his before and after valuations are compared the
difference is $456,000 $337,000 = $119,000. Mr.
Umlah also calculated the market valuation of the remainder
using the minimum calculation set out in section 40(3)
of the Act. This minimum calculation yields the same
result of $119,000 rounded.
5.4.2 Analysis and
Conclusion
[85] We have concluded
that the valuation of the subject property before the
taking was $873,500 while the valuation after the taking
was $668,000. This results in a valuation of the taking
and the reduction in market value of the remainder of
$205,500. We agree with Mr. Parkhill that the minimum
compensation should be calculated under subsection 40(5),
taking the value of the different sectors into account.
Thus the valuation of the land taken and reduction in
value to the remainder after the taking at $205,500
is greater than the minimum compensation for the land
taken only at $179,000. The claimant is entitled to
$205,500 for the valuation of the taking and the reduction
in market value of the remainder.
6. COMPENSATION FOR
THE DOERR PARCEL in excess of market value
[86] The claimants' position
is that as a result of the project, and the anticipated
taking of the subject property, they were driven to
purchase the whole Doerr parcel in 1997 at a price that
was in excess of its market value.
[87] The respondent says
that no compensation is owed as a result of the claimants'
purchase of the Doerr parcel for two basic reasons:
1. The claimants' purchase of the
Doerr parcel was not caused by the respondent.
2. In any event, the claimants have
not suffered a loss since they have not paid more
for the Doerr parcel than it was worth.
6.1 Causation
6.1.1 Statutory basis
[88] The first issue is
whether the purchase of the Doerr parcel was caused
by the respondent. Section 40 provides:
40 |
(1) |
Subject to section
44, if part of the land of an owner is expropriated,
he or she is entitled to compensation for |
|
|
(a) |
the
market value of the owner's estate or interest
in the expropriated land, and |
|
|
(b) |
the
following if and to the extent they are directly
attributable to the taking or result from the
construction or use of the works for which the
land is acquired: |
|
|
|
(i) |
the reduction in the market
value of the remaining land; |
|
|
|
(ii) |
reasonable personal and business
losses. |
[89] Although the Doerr
parcel was purchased before the actual expropriation
in this case, Dell Holdings Ltd. v. Toronto Area Transit
Operating Authority (1997), 60 L.C.R. 81 (S.C.C.) is
authority for permitting disturbance damages that were
suffered prior to the expropriation. At para. 38 Cory
J. states:
The approach to damages flowing
from expropriation should not be a temporal one; rather
it should be based upon causation. It is not uncommon
that damages which occur before the expropriation
can in fact be caused by that very expropriation.
[90] Another relevant section
is section 34:
34 |
(1) |
An
owner whose land is expropriated is entitled to
disturbance damages consisting of the following: |
|
|
(a) |
reasonable
costs, expenses and financial losses that are
directly attributable to the disturbance caused
to the owner by the expropriation; |
|
|
(b) |
reasonable
costs of relocating on other land, including reasonable
moving, legal and survey costs that are necessarily
incurred in acquiring a similar interest or estate
in the other land. |
6.1.2 Relationship
to the loss of the subject property
[91] As we have indicated
above, the question may be put as follows: was the claimants'
purchase of the Doerr parcel directly attributable to
the taking (or to the disturbance caused to the claimants
by the expropriation) or did it result from the construction
or use of the works? Or was there a different reason
unrelated to the taking or the project? The circumstances
surrounding the claimants' use of the Doerr parcel since
the project was announced have to be examined. Because
of this lengthy time frame we find the documentary evidence
written at the time of particular assistance in fixing
the chronology of what has occurred. These documents
also reveal what the participants' reasoning appeared
to be at different times.
[92] As early as 1991 the
documents show that Gorman Bros. planned on buying the
Doerr parcel when the price was right in order to have
more space. At this time the parties contemplated that
the consolidated exchange parcel north of the mill site,
which the Ministry was acquiring piecemeal from the
residential owners, would be exchanged for the subject
property. Mr. Tracey reported that, in the fall of 1991,
there was a shortage of space for log storage.
[93] In late 1993, when
the project was on hold, the correspondence in evidence
establishes that Gorman Bros. was anxious to lease on
a temporary basis parts of both the Doerr parcel and
specific lots within what became the consolidated exchange
parcel for log storage and for rough lumber storage,
steel storage and employee parking respectively. Gorman
Bros. was successful in negotiating a two year lease
for 2.5 acres of the Doerr parcel for log storage. However,
it was unsuccessful in leasing any lots in what became
the consolidated exchange parcel because of the opposition
of residents who continued to live in the area who had
not yet been bought out by the Ministry.
[94] In 1996, it was still
contemplated that some unknown amount of the Ministry's
surplus land would eventually become the consolidated
exchange parcel and be provided to Gorman Bros. to minimize
the impact of the loss of the subject property. With
the expiry of the lease, Gorman Bros. attempted to purchase
16 acres of the Doerr parcel with one of the conditions
of sale being the Ministry's confirmation that it would
acquire the subject property. The Ministry provided
such a letter. In addition, it appeared that the Ministry
intended to obtain gravel from the portion of the Doerr
parcel that the claimants were attempting to buy and
that the two parties were exploring the mutual advantages
of this purchase. Although the project was scheduled
to go ahead at this point, the negotiations for the
sale of part of the Doerr parcel collapsed in May 1996
and the existing lease of the 2.5 acres continued on
a month to month basis. The evidence was that the final
positions of the parties on the price to be paid for
the 16 acres were $125,000 apart, namely $650,000 and
$775,000.
[95] Later in 1996, in
August, after the project was on hold, the evidence
indicates that the Ministry made some efforts to proceed
with the taking of the subject property from Gorman
Bros. in any event. The stated reason by the Ministry
was to permit Gorman Bros. to acquire an alternative
chip storage site so that more chips did not have to
be put on the subject property. Earlier in the year
when the project had been proceeding there had been
specific discussions about the existing chip pile and
the need to reduce it in order to provide vacant possession
of the subject property to the Ministry. An agreement
had been made to move the chips. As a result of this
agreement the Ministry was prepared to proceed with
the taking of the subject property. However, these negotiations
between the Ministry and Gorman Bros. broke down and
the agreement to move the chips was cancelled. In a
letter to the Ministry written at this time (three months
after negotiations for the Doerr parcel had collapsed),
Mr. Tracey stated that the potential purchase of the
Doerr parcel "is being exacerbated by the highway
project. Mr. Doerr appears to be holding [Gorman Bros.]
out to ransom on the price he expects."
[96] Finally in March 1997
Mr. Doerr delivered his ultimatum. He was going to list
the property and he wanted all logs cleared from the
property by June 1, 1997. On March 31, 1997, Gorman
Bros. reported having 100,000 cubic metres of logs,
many of which were stored on the Doerr property. The
annual logging moratorium under the Forest Practices
Code would continue through to some time in July. The
highway project was again on hold. Gorman Bros. offered
to pay $2,000,000 for the whole property on June 9,
1997 and a formal agreement of purchase and sale was
signed in this amount conditional on the rezoning of
all the land south of the ALR area as industrial. Both
the application for rezoning and the media release prepared
by Gorman Bros. stated that the acquisition of the Doerr
parcel was for log storage purposes, while the media
release provided the additional purpose that it would
reduce the impact of the project, when it happened.
[97] Thus, the documentary
evidence shows that over the ten year period, any link
between the purchase of the Doerr parcel and the potential
loss of the subject property fluctuated, depending on
the circumstances. It was strongest in 1996, but those
negotiations to acquire the Doerr parcel failed. There
was also evidence that established independent reasons
for the purchase of the Doerr parcel.
[98] In 1996 the claimants
understood that the whole subject would eventually be
taken for the project, requiring a replacement for about
4.6 acres of storage space. Gorman Bros. was particularly
concerned about losing storage space for the chip pile.
There was acknowledgement that an alternative site had
to be found for the storage of chips. The Ministry and
the claimants were cooperating in investigating the
amount of gravel on the Doerr parcel which factor would
be considered by the claimants in the negotiations as
to the price to be paid. Although there had been discussion
of the Ministry transferring some surplus land north
of the mill site in exchange for the subject property
there was no certainty about how much land would be
transferred or when. Later in 1999, after the partial
taking, a potential site for chip storage was established
on the Doerr parcel but this has never been used for
chips at the time of the hearing as conditions had changed
and there has been no requirement for chip storage to
date. This is the evidence that supports the connection
between the purchase of the Doerr parcel and the potential
loss of the subject property.
[99] However, there was
also evidence that reinforced other, independent, reasons
for the Gorman Bros.' purchase of the Doerr parcel.
Mr. Tracey described the mill as being in a tight spot,
squeezed between the highway and a steep incline. Gorman
Bros. was perhaps the only sawmill that was three storeys
high. (Gorman Bros. did have a number of sites for various
purposes that were further afield that provided them
with some flexibility.) There are several references
in the documents about Gorman Bros.' intention to buy
some or all of the Doerr parcel at some point in the
future when the price was right. The proposed terms
of the agreement to purchase 15.96 acres of the Doerr
parcel in 1996 included a right of first refusal to
acquire the balance of the Doerr parcel. Mr. Tracey
went so far as to say that Gorman Bros. had always planned
to buy some or all of the Doerr property but was not
in any hurry. There was a good chance of being able
to eventually purchase some or all of the property from
Mr. Doerr's estate (since he was an elderly owner with
no children) and as long as it was a landlocked parcel
Gorman Bros. was the only purchaser. These comments
were not in relation to the Doerr parcel being a substitute
for the subject property. In late 1993, when the project
was on hold, the documentary evidence shows that Gorman
Bros. was attempting to lease on an interim basis both
the Doerr parcel and some properties that became the
consolidated exchange parcel, for separate storage purposes
that were not related to the subject property. The evidence
establishes that the efforts to lease the two parcels
were not linked and were being pursued for different
purposes. Once the lease of the Doerr parcel was in
effect, the log inventory increased dramatically, doubling
between March 1993 and March 1995. We also note that
there was a significant increase in sawmill production
in the period during the latter 1990's and this would
logically require an increase in the supply of logs
and storage space for those logs.
[100] In addition to the
use of adjacent properties for industrial purposes,
there was also evidence that Gorman Bros. wanted to
create buffer zones between their mill operations and
any non-industrial neighbours. Approximately 20% of
the subject property had been bought to create a buffer
zone from any potential development of the property
to the south. A rock outcrop had been used to create
a buffer zone between the mill site and the residential
properties to the north that eventually were bought
and formed the consolidated exchange parcel. Mr. Tracey
testified that Gorman Bros. did not want developers
buying adjacent property and that it would be unhappy
if someone other than Gorman Bros. bought the Doerr
parcel.
[101] Mr. Tracey also agreed
that in March 1997 when Mr. Doerr's ultimatum arrived
that it was an important consideration for Gorman Bros.
to avoid the expense of moving something less than 100,000
cubic metres of logs, perhaps to some location off site,
in a short period of time and of replacing the topsoil
from the 2.5 acres of leased land. Gorman Bros.' application
for rezoning stated that the purchase of the Doerr parcel
was necessary for the continued operation of the mill
and that part of the land was for expanded log storage
as a result of changes in the Forest Practices Act and
increased production. Gorman Bros.' media release also
stressed that the purchase was for sufficient on-site
log storage, although it also acknowledged that the
purchase would reduce the impact of the loss of the
subject property. The documentary evidence shows that
surplus Ministry land to the north of the mill site
was discussed as a substitute for the subject property
in 1991 and 1996, although it was not known how much
land would be surplus. In the end as Mr. Tracey acknowledged
it was a business decision by Gorman Bros. to purchase
the Doerr parcel in June 1997 for $2,000,000 on the
facts as known at that time.
[102] In our opinion, given
all the circumstances leading up to and surrounding
the purchase in 1997, the claimants would have probably
bought the Doerr parcel even if the loss of the subject
property had not been anticipated. The claimants had
always intended to purchase the property but thought
that they would be able to negotiate a good price later
with Mr. Doerr's estate. The primary and urgent reasons
for the purchase in 1997 were to do with log storage
and the subject property had never been used for log
storage. The documentary evidence of the rezoning application
and Gorman Brother's media release written at the time
of the purchase contradict Mr. Tracey's allegations
that the potential loss of the subject property was
the main motivating reason for the purchase.
[103] Nonetheless, the
potential loss of the subject property was also a contributing
factor in the purchase. We accept that it was important
for the claimants to maintain their flexibility vis-à-vis
the project and the anticipated loss of the whole of
the subject property especially when there was so much
uncertainty about the amount of surplus land north of
the mill site, and when it would be available. We conclude,
that while there were a number of reasons that were
independent of the taking, and indeed we think these
reasons were sufficient, the anticipated expropriation
of the subject property was one factor in the purchase
of the Doerr parcel by the claimants. Thus, the purchase
of the Doerr parcel was in very small part attributable
to the taking.
[104] The claimants say
but for the Ministry's provision of alternate access
to the Doerr parcel they would never have had to purchase
it in June 1997. However, this reasoning does not altogether
make sense to us. First, the Ministry's provision of
alternate access was not a surprise in 1997. We are
satisfied that both parties had anticipated this access
since 1993 and that in the spring of 1996 the evidence
was clear that both parties knew the access would eventually
be provided when the project went ahead. Second, in
1996, when negotiations ultimately failed, the parties
were only $125,000 apart at $650,000 and $775,000 respectively
for 16 acres of the Doerr parcel, (out of a total of
about 28 acres that were non ALR). Both parties knew
at this time that access would ultimately be provided,
and in fact the proposed offers in 1996 were based on
this with provision for a temporary easement until the
permanent access was created. The documents indicate
that the parties had apparently agreed on everything
but price. We do not have all the evidence on why the
negotiations failed but they did fail, apparently on
the issue of the price to be paid. The claimants chose
to carry on with only a month to month lease in place
for the 2.5 acres that they were using for log storage.
This left the claimants in a vulnerable position that
it appears Mr. Doerr was able to exploit in March through
June 1997. We understand the claimants' frustration
at this turn of events and their inclination to blame
the project. But we do not find that the evidence supports
the claimants' explanation. In any event, in our opinion,
it is simply too remote to make a claim for an alleged
loss in bargaining power with a third party on the basis
of the Ministry's promise of access to the third party
as a result of the project.
6.2 Was the $2,000,000
Paid for the Doerr Parcel an Overpayment?
[105] The next issue is
whether Dunfield Holdings suffered a loss by paying
more for the Doerr property than it was worth. The claimants
make a claim for the difference between the purchase
price of $2,000,000 and the market value of the Doerr
parcel as estimated by Mr. Parkhill.
[106] Mr. Parkhill on instructions
from counsel, appraised the Doerr parcel in June 1997,
on the basis of two assumptions:
- that the claimants were not unduly motivated or
compelled to buy the Doerr property as replacement
land for the looming expropriation;
- that the claimants foreseeable off-site log storage
requirements would not significantly extend beyond
the 2.5 acres of the Doerr property that were leased.
In 1997 the Doerr property was zoned
RU2, Rural, and was designated Agricultural and Rural
Resource in the Westbank Official Community Plan. The
OCP provided that Rural Resource properties meant large
parcels of undeveloped land used for forest management,
limited grazing, and outdoor recreation. General policies
with respect to Rural Resource properties included preserving
public access and protection from subdivision and development.
There was a temporary industrial permit in place for
the 2.5 acres that had been leased to the claimants.
Mr. Parkhill concluded that the highest and best use
was as a speculative holding property with some potential
for residential lots on parts of the ALR land that afforded
views over the lake and mid to long term potential for
increased industrial utility on the southerly portion
adjacent to the claimants' mill site.
[107] Mr. Parkhill used
16 sales of properties that occurred between November
1996 and October 1999 that provided a range in value
of $6,027 to$49,920 per acre. From these sales he derived
the following estimations of value for different parts
of the Doerr parcel making the assumption stated above:
ALR impacted sector |
±25.5 acres + ±4.5
acres x $17,000 per acre |
$ 510,000 |
Low utility sector |
±10 acres x $4,000 per
acre |
$ 40,000 |
Potential industrial sector |
±18 acres x $35,000
per acre |
$ 630,000 |
Total |
±58 acres
x $20,345 per acre |
$1,180,000 |
[108] The claimants claim
compensation for that portion of the sale price for
the Doerr parcel that they say is in excess of this
market price of $1,180,000. The difference between the
purchase price of $2,000,000 and the market value of
the Doerr parcel as estimated by Mr. Parkhill at $1,180,000,
is $820,000.
[109] The respondent says
that there has been no loss suffered by the claimants.
Gorman Bros. has a particular, possibly unique, interest
in the Doerr property. If the claimants did pay more
for the Doerr property than the market value, it is
because the property is worth more to the claimants.
[110] We agree with the
Ministry that the Doerr parcel had a special value to
the claimants. It was immediately adjacent to the mill
site and approximately 18 acres of it were potentially
suitable for various industrial uses associated with
the sawmill. There was evidence that the claimants were
concerned to maintain buffer zones around the mill site.
The claimants always intended to purchase the property
for purposes that were not associated with the expropriation.
At the time of the purchase they were leasing 2.5 acres
of the property but it was only a month to month tenancy
and it would have been a nuisance and costly for them
to vacate the land as Mr. Doerr demanded. There were
no other adjacent properties except for what became
the consolidated exchange parcel.
[111] We reject Mr. Parkhill's
first assumption that the claimants were not unduly
motivated to buy the Doerr property. The Doerr parcel
was worth more to the claimants as a special purchaser
because of the unique characteristics of the property
to them.
[112] We also disagree
with Mr. Parkhill's second assumption. The need for
more log storage and other uses (but for those associated
with the subject property) was foreseeable given the
changes in the Forest Practices Code as well as the
increased production in recent years. Adopting this
assumption could result in a lower estimate of the market
value.
[113] We note that the
agreement between Gorman Bros. and Mr. Doerr to purchase
the property for $2,000,000 was subject to a condition
that the area south of the ALR land be rezoned to industrial.
In 1999, Mr. Parkhill concluded that the high utility
sector of the subject property (the 4.0 acre bench used
for storage of lumber) was valued at $150,000 an acre
after the taking when it had lost direct highway access.
This property was zoned industrial. Also in 1999, the
claimants agreed to pay $150,000 an acre for the consolidated
exchange parcel which was subsequently rezoned to industrial.
It has been used for parking and storage of lumber.
The area of the Doerr parcel that was subject to the
condition that it be rezoned industrial and was potentially
usable for industrial purposes (since it was not covered
by any covenant on use) was 18 acres. Applying the valuation
of $150,000 an acre that Gorman Bros. had accepted for
two other nearby industrial properties in 1999 to the
18 acres of the potential usable industrial sector of
the Doerr parcel in 1997 yields a sum for this portion
of the Doerr property alone of $2,700,000.
[114] Further, the loss
claimed is based on the difference between the purchase
price of $2,000,000 and the market value. There was
a lack of evidence as to the negotiations and why the
claimants suddenly agreed to pay $2,000,000 in cash
in June 1997, having refused to agree to pay $775,000
over time for 16 acres in May 1996. As we have indicated
above, we do not accept Mr. Tracey's explanation that
it was simply the Ministry's intervention in promising
better access. There has been no explanation as to how
circumstances changed between May 1996 and June 1997.
[115] In summary, we conclude
that the claimants were special purchasers who made
a business decision to purchase the Doerr parcel in
June 1997 for $2,000,000. The anticipated loss of the
subject property was, at best, one small factor in that
decision and we have specifically found that the claimants
would probably have purchased the Doerr parcel in the
absence of any anticipated loss from the subject property.
Even if the sum paid was more than the market value,
in our opinion, the claimants' special interest in the
property means that they have not suffered a loss. In
any event we have rejected Mr. Parkhill's two assumptions
and as a result his conclusion of market value of the
Doerr parcel is not accepted. Because we have found
that the claimants suffered no loss we deny their claim
for $820,000 for an overpayment on the purchase of the
Doerr parcel.
7. COMPENSATION FOR
RELOCATION OF THE OFFICE BUILDING
[116] The claimants say
that as a result of the project and the new long private
road through the consolidated exchange parcel, their
site is now unsafe. The existing office building is
no longer situated near the entrance to their site as
it was before the project and the mixing of civilian
traffic with fork lifts, loaders and large trucks causes
concerns. The claimants plan on constructing a new office
building on the consolidated exchange parcel near the
new entry to the mill site. The construction of the
new office building has not yet begun because the claimants
are waiting for the shaded area to be transferred to
them, following which appropriate setbacks can be determined.
They claim for the depreciated cost of the old office
building which they say will eventually be torn down.
[117] The claimants relied
on Ross MacDougall of Kent-Macpherson Appraisals for
an opinion of the depreciated value of the existing
office building. A quantity surveyor estimated the construction
costs for an equivalent building in 2001 at approximately
$526,000. There were allowances for other project costs
such as site development, design, demolition of the
existing building, construction insurance, provision
for new features such as an elevator and fire suppression
system required under the current building code which
brought the total development costs to $770,000 rounded.
The office building was estimated to be 18 years old
with a remaining economic life of 35 years for a weighted
depreciation in 2001 of 19%. This depreciation factor
was applied to the building cost plus 5% contingency.
There was also an allowance for depreciation of the
site improvements. After deducting these sums for physical
depreciation the depreciated replacement value of the
current office building in 2001 was estimated as $640,000.
[118] The Ministry provides
four reasons for denying this claim. First, the Ministry
submits that the real basis for this claim is that the
claimants want a newer and considerably larger office
building and that neither the project nor the respondent
is the cause of the claim. Second, in March 1999 the
claimants were provided with two options for replacement
access. The Ministry says that the claimants chose to
acquire the consolidated exchange parcel and it was
this choice that led to the existing office building
being a long way from the initial access point to the
mill property. If the claimants had chosen the other
option with the Ministry retaining the consolidated
exchange parcel and building a public road across it,
the initial access point to the mill site would be in
much the same place as it was before the taking. There
would have been no need to move the office building.
Third, the Ministry says that the contract entered into
for the purchase of the consolidated exchange parcel
gives the claimants a credit for the costs and space
required for a hypothetical public road that would end
near the existing office building. Any compensation
for the depreciation of the office building for being
in this location contains an element of double compensation.
Fourth, the Ministry points to the most recent access
permit issued to the claimants in 1973 which contained
a provision that there be "no claim against the
crown for damages arising out of changed access"
caused by any subsequent public works.
[119] We note that we are
not persuaded by this last submission. The Ministry
did not provide us with any cases where the wording
of access permits had been used to deny a claim for
compensation. The access permit was a document drafted
by the Ministry. It is applicable to the current owner
only and does not run with the land. In permitting the
use of a particular access at a particular point in
time, it attempts to unilaterally deny liability for
any damages arising from any change in access due to
any public works at any subsequent date. If the claimants
are entitled to compensation under the Act for an expropriation
of land, including compensation for damages resulting
from the project, we do not accept that the 1973 access
permit should necessarily preclude any compensation
for damages from changes in access arising from the
project.
[120] The issue that we
must decide is whether the existing office building
had to be abandoned as a direct attribution of the taking
or as a result of the project. If not, has the existing
office building experienced accelerated obsolescence
as a result of the taking or the project?
[121] One of the difficulties
in this case is that there has been a blurring between
two things: the need for a new access road to the mill
site through what became the consolidated exchange parcel
and the desire by the claimants to acquire surplus land
adjacent to the mill site for other mill functions.
The documents show that the claimants have expressed
interest in acquiring whatever surplus land the Ministry
owned beginning in 1991. In 1993 the claimants pursued
the temporary leasing of these lands and in 1996 they
retained Reid Crowther to provide various layouts for
potential access across these lands. The Ministry was
amenable to the idea of eventually providing surplus
land on the grounds that it would reduce their cost
if they exchanged this land as part of the payment for
the subject property. It was clear that new access to
the mill would have to cross this land. What was not
clear was when the project would proceed, how much land
would turn out to be surplus once the project design
was finalized, and what the principles of remuneration
should be for any such arrangement.
[122] The documents demonstrate
that the claimants proceeded on the principle that they
would eventually acquire some of the surplus land and
then build the new access road themselves. If they acquired
the surplus land, they could build the new private road
as an internal road. The internal road could be placed
by the claimants in a location that would maximize space
for the rest of the surplus land for various mill functions
other than access. The parties have agreed that a hypothetical
public road would occupy 1.48 acres. We note that a
private road across the surplus land did not have to
meet public road standards and therefore could be narrower
than a public road, leaving even more space for other
non-access functions. Since the consolidated exchange
parcel that was eventually transferred was 4.4 acres,
then this means that the claimants would acquire about
3 acres of land in addition to the new access road,
which would be available for other mill purposes. An
internal road could be used by industrial vehicles such
as loaders and fork lifts taking materials to storage
spaces on the surplus land that became the consolidated
exchange parcel.
[123] The claimants say
that the Ministry's offer to provide access in March
1999 was at the eleventh hour, shortly before the project
was scheduled to begin, and in the circumstances they
simply had no choice. The Ministry never intended to
build the hypothetical public road and had no designs
in place. The only way to ensure the mill site's operation
was to acquire the consolidated access parcel and construct
the access road themselves. It is true that the Ministry
had no designs in place. However, we note that the existing
access to the mill was not closed until October 1999.
We are satisfied that as of March 1999 the Ministry
could have put a public road in place by October, if
it had been necessary, so that mill access would not
have been interrupted.
[124] In our view what
the Ministry's last minute offer of a choice between
two options did was to separate out the issues of access
and the claimants' wish for more land. Until then the
two issues were conflated and causation for disturbance
damages related to access and the consolidated exchange
parcel were unclear. The claimants were upset by this
step and it is regrettable that it was so late in the
day. However, we have found that it was not too late
for the Ministry to have restored access if that was
the only issue. Until an agreement has been made, negotiating
positions of the parties at any particular time are
irrelevant.
[125] In March 1999, the
claimants had been assuming for some years that they
would eventually acquire the surplus land and build
the new access themselves. They had made some provisional
plans for how they might construct the new access road
and reconfigure the mill site using the surplus land.
At this time they knew that only 0.6 usable acres (2.4
acres in total) had been lost from the subject property.
Only two years earlier, in 1997, the claimants had acquired
the Doerr parcel, which had 18 acres usable for industrial
purposes. They did not need any more land as a result
of the project. But during the 1990's mill production
had risen approximately 50%. Increased production required
more space not only for logs, but for the lumber inventory
that was being processed, dried and stored. We conclude
that the real reason for the claimants' choice to acquire
the consolidated exchange parcel was to do with increased
production at the mill and the need for more space.
[126] We agree that there
is some safety concern about the present arrangement.
But we note that the new private road has become part
of the internal roadway on the mill site and its use
is under the control of the claimants. For example,
one reason for the mixture of civilian and industrial
traffic is that the claimants now use the consolidated
exchange parcel for storage. As a result loaders and
fork lifts must carry lumber on the new private road
to the storage site on the consolidated exchange parcel.
The claimants have reconfigured the mill site choosing
the route for the new private road as an internal road
and choosing how to use the additional land on the consolidated
exchange parcel on the assumption that they would relocate
the office building nearer the new entrance to the site.
On this assumption the reconfiguration did not need
to take into consideration how to make the site work
best leaving the office building where it was. We accept
that there are good reasons for having the office building
near the new entrance, but, in our opinion, some of
the deficits in the existing configuration and siting
of the office have been magnified by choices the claimants
made knowing that the office would be moved.
[127] The relocation of
the office building was recognized as something the
claimants wanted very early on. The documents show that
as far back as 1991 the claimants discussed moving the
existing office to a new location following the project
so that it would be near the proposed new entrance to
the mill site. Discussions continued in negotiations
during 1999 but nothing was ever resolved with respect
to this issue. Although physical moving of the existing
office building was discussed, it was not pursued. We
note that the new office building will be larger than
the existing office building. In our opinion, the construction
of a new office in a new location is in part because
the claimants need a larger office building and in part
because the claimants' acquired the Ministry's surplus
land as the consolidated exchange parcel. If replacement
of access had been the only concern of the claimants,
then the Ministry would have constructed a public road
across the consolidated exchange parcel. The claimants
would have had no responsibility for safety issues on
the public road and the existing office building would
have remained near the entry point to the mill site.
[128] We conclude that
the relocation of the existing office building is not
directly attributable to the taking or the closure of
the highway access. Nor does the relocation of the existing
office building result from the project.
[129] Nonetheless, it is
our view that the existing office building has experienced
some nominal functional obsolescence as a result of
the project. Before the taking the mill site layout
had the existing office building beside the highway
and adjacent to the access driveway from the highway.
If the Ministry had constructed the public road, the
entrance to the site would continue to be near the existing
office building. However, the office building would
have been angled differently to the access and the entranceway
to the site would not have worked in the same way as
it had done before the taking. We conclude a 5% reduction
in the value of the building for accelerated depreciation
is appropriate. The only evidence on the current costs
to construct the existing office building was from Ross
MacDougall. He applied his depreciation factor to $552,244
which represented the net building costs plus a 5% contingency
fee. Although the accelerated depreciation occurred
in November 1999 when the existing access to the highway
was closed we will have to apply our depreciation to
the construction costs for the existing office building
estimated almost two years later in 2001. Presumably
the construction costs in 2001 will be somewhat inflated
over what they would have been in 1999. Applying 5%
depreciation to $552,244 results in an award of $27,612.
8. DISTURBANCE DAMAGES
for various expenses and invoices
8.1 Claimants' position
[130] The claimants are
seeking reimbursement for a number of expenses that
they claim were incurred as a result of the expropriation.
These are set out as follows without GST or interest:
Reid Crowther - 20 invoices |
$ 38,969.73 |
John MacDonald - 12
invoices |
$ 26,543.64 |
Emil Anderson invoices |
$ 10,176.95 |
|
$ 23,917.50 |
T. Lewis 1999 invoice |
$ 48,475.00 |
Kent Macpherson account |
$ 343.75 |
DA Goddard invoice |
$ 250.00 |
Chip storage platform |
$ 6,520.00 |
Clermont Crane invoice |
$ 600.00 |
Paul's Fine Woodworking
invoice |
$ 160.00 |
Mitchell Mearns invoice |
$ 278.00 |
Ike Stutters invoice |
$ 612.50 |
PPT paid for consolidated
exchange parcel |
$ 7,220.00 |
Pro rata PPT for Doerr
parcel |
$ 15,580.00 |
Total |
$179,647.07 |
8.2 Respondent's
position
[131] The Ministry has
made partial payments on these disturbance damages as
follows:
Reid Crowther -- partial
payment of 4 invoices |
$6,308.10 |
John MacDonald invoice
dated September 9, 1999 |
$1,832.79 |
[132] The Ministry says
that the invoices can be grouped into a number of categories
including:
expenses relating to the
purchase of the Doerr parcel including legal expenses,
pro rata PPT, rezoning expenses, and environmental
survey by Reid Crowther
The Ministry says that these should
not be paid because the claimants' decision to purchase
the Doerr parcel was not caused by the respondent
or the project. The Ministry singled out a specific
Reid Crowther invoice to do with an ALR land swap
for part of the road on the Doerr parcel that led
to the log storage area. This invoice was to correct
a problem that pre-existed the project and was not
caused by the project. As a result the Ministry
says it should not be paid.
expenses relating to the
consolidated exchange parcel and the shaded areas
The Ministry says these Reid Crowther
expenses should not be paid because they were not
caused by the expropriation. Any obligation for
the Ministry to pay these arose out of contractual
arrangements between the two parties whereby the
claimants agreed to purchase the consolidated exchange
parcel. As a result the expenses are too remote.
The Ministry singled out a specific Reid Crowther
invoice to do with the shaded area. This invoice
was for work made necessary because of the claimants'
occupation of that area in building its access road
in part on the shaded area. Since it was not the
project that created the need for this work the
Ministry says it should not be paid.
expenses relating to access
The Ministry says that the parties
agreed that "upon the transfer of the Consolidated
Exchange Parcel on the agreed terms that the Ministry
has complied with its obligations to replace the
access taken with reasonable access". The Consolidated
Exchange Parcel has been transferred and therefore
the Ministry has replaced the lost access. Further,
the Ministry has provided a credit to the Claimants
for the cost of providing access to the office in
the agreed formula that was part of the settlement
involving the Consolidated Exchange Parcel. Any
expenses incurred by the claimants in relation to
the new access are to its own account because of
the settlement made by the parties on this issue.
8.3 Analysis
[133] Under sections 34
and 40 an owner is entitled to reasonable business losses
that are directly attributable to the taking or the
disturbance or that result from the construction or
use of the project.
[134] The board wishes
to make some general comments about the claim for the
disturbance damages. We appreciate that there was extensive
work done on the mill site that is not being claimed.
We also appreciate that it was a complex case with a
number of different claims, several of which settled.
However, there were over 50 invoices claimed and 20
of those invoices included over 60 different claims
for a total altogether of about 100 claims. It appears
that after initial difficulties the parties made little
effort to sort any of these invoices out before the
hearing. Because of the differences of opinion on causation
on the Doerr parcel and the consolidated exchange parcel
we recognize that settlement of many of these invoices
before the hearing was unlikely. However, both the hearing
and our deliberations would have benefited from a more
organized presentation of these approximately 100 claims.
In some cases the claimants were not able to provide
sufficient evidence to enable us to determine what had
been done, even though some of the invoices were discussed
a second time after telephone calls to other employees.
Given that there were about 100 claims we would have
found it of assistance if schedules had been provided
listing the invoices, the work done and the amount claimed
without GST, preferably categorized in relation to the
Doerr parcel or the consolidated exchange parcel or
ancillary access issues and arranged chronologically.
Although it is the responsibility of the claimants to
produce the evidence at the compensation hearing, and
we do not wish to encourage a multiplicity of hearings,
in order to be fair, we have adjourned some claims for
disturbance damages. If there are any difficulties for
the parties in settling those outstanding claims, they
can be brought at a future application.
8.3.1 Subject property
invoices
[135] Mr. MacDonald, the
solicitor for the claimants, did the work for registering
a new easement on the subject property for the Tingstad
property to the south. Mr. Tracey testified that this
work had only been completed a few weeks before the
hearing. Although there were 12 invoices from Mr. MacDonald
for which the claimants are seeking payment, there was
no invoice submitted for this work. However, the Ministry
acknowledged it was responsible for this work. We conclude
that it was an expense directly attributable to the
taking. Since we do not have this invoice, this claim
is adjourned.
[136] There was an invoice
for $250 from D.A. Goddard Land Surveying Inc. dated
December 1998 for "staking proposed new road boundary
for subject property". It was suggested that this
work was for the new Tingstad easement referred to above.
Given the date of the invoice we think that it is more
likely for work for the new road boundary as a result
of the taking. In either event, we conclude that the
claimants incurred this expense as a result of the taking
and are therefore entitled to reimbursement for $250.
8.3.2 Doerr parcel
invoices
[137] Under section 34(1)(b)
an owner is specifically entitled to reasonable costs
that are necessarily incurred in acquiring a similar
interest or estate in other land. This includes legal
fees related to a purchase of a similar interest and
property purchase tax.
[138] The Ministry submits
that the claimants would have bought the Doerr parcel
at some future time in any event and therefore the acquisition
costs in 1997 cannot be attributed to the taking. We
have found that there were a number of independent reasons
for the acquisition of the Doerr parcel; however, one
small factor in the purchase of the Doerr parcel in
1997 was the prospect of the taking of the subject property.
We accept that the Doerr parcel is in part a replacement
property of a similar interest to the part of the subject
property that was taken.
[139] In Patterson v.
British Columbia (Ministry of Transportation and Highways)
(1997), 62 L.C.R. 89 (B.C.C.A.), the court upheld a
board decision denying the claimant in a partial expropriation
relocation costs under section 34. However, we conclude
that the circumstances of this case are distinguishable.
Gorman Bros. needed to replace any of its property that
was required for the project, a fact that all parties
recognized from the beginning.
[140] The next issue is
how much of the Property Purchase Tax on the Doerr parcel
should be awarded to the claimants. The evidence shows
that the Property Purchase Tax paid by the claimants
for the Doerr parcel was $38,000 calculated at 1% of
the first $200,000 plus 2% of the value over $200,000.
The claimants made a pro rata claim for the Property
Purchase Tax on the Doerr parcel based on the amount
that they said was in excess of the market value or
$38,000/$2,000,000 x $820,000 or $15,580. We have found
that the market value of the subject property that was
taken together with the reduction in market value to
the remainder is $205,500. This board has limited the
claim for Property Purchase Tax in other cases to the
maximum of the Property Purchase Tax on the market value
of the expropriated property. See Ferancik v. Langley
(Township) (1996), 60 L.C.R. 123 (B.C.E.C.B.) and
Hawk Investors Ltd. v. British Columbia (Minister
of Transportation and Highways) (1999), 66 L.C.R.
94 (B.C.E.C.B.). In our opinion, with respect to this
issue, it is irrelevant that at the time the Doerr parcel
was purchased the claimants thought that the whole of
the subject land would be taken. On the basis of the
market value of the actual taking we award $38,000/$2,000,000
x $205,500 or $3,905 for the Property Purchase Tax paid
by the claimants in relation to the Doerr Parcel as
the appropriate percentage that is directly attributable
to the partial taking from the subject property.
[141] Mr. MacDonald billed
$18,138.88 excluding GST ($15,750 in fees) over five
accounts, for work done in 1997 in relation to Gorman
Bros.' purchase of the Doerr parcel. Much of this work
was for the rezoning of approximately 28 acres to I-3,
and the imposition of the non-disturbance covenant on
the approximately 8 acres that were steeply sloped.
This work was necessary if any part of the Doerr parcel
was to be used to replace the subject property. We have
found that the potential loss of the subject property
was one small factor in the acquisition of the Doerr
parcel, although there were other long standing factors,
one of which was urgent in 1997, that were independent
of the loss of the subject property. In addition, the
Doerr parcel gave the claimants much more utility than
the land taken, whether it was the usable part of the
entire nine acre subject property as contemplated in
1997 or the usable part of the partial taking of 2.4
acres of the subject property that eventually occurred
in 1999. After consideration of these factors we conclude
that 50% of Mr. MacDonald's fees or $9,069.44 should
be paid by the Ministry as the appropriate percentage
that is directly attributable to the taking. See Bayview
Builders Supply (1972) Ltd. v. British Columbia (Minister
of Transportation and Highways), (2001), 75 L.C.R.
95 (B.C.E.C.B.).
[142] The claimants claim
$48,475 for a May 1999 invoice from T. Lewis Trucking
& Bulldozing Ltd. for work that was described on
the invoice as "excavation of new yard -- blasting,
excavating and building road". This work was evidently
done on the Doerr parcel. We were told that the work
was to create a new flattened area to the north of the
area where logs were stored for the air drying of lumber.
We also understand that it would be feasible for chips
to be stored there as well, though none have been stored
there to date. The claimants have not claimed an October
1997 invoice for $26,300.60 from T. Lewis Trucking that
included some work to lower a gas pipeline and remove
a vineyard to expand the area used for log storage.
[143] The first thing that
we note is that the claimants chose to locate the potential
new chip site on a portion of the 18 acres of usable
industrial land on the Doerr parcel that needed extensive
excavation. The proposed new chip site was only 200
square feet or 0.9 acres and there were other areas
on the 18 acres that could have been chosen for this
use that would have needed no excavation or blasting
or clearing. The claimants chose to store logs on much
of the 18 acres and to place the potential chip site
in a location that required significant earth moving
work. Although the claimants may have preferred to place
the potential chip site in this location, it was not
a necessary outcome of the purchase of the Doerr parcel
as a partial replacement for the partial taking from
the subject property. Thus the expense from T. Lewis
Trucking was not directly attributable to the taking
nor did it result from the project. In addition, we
note that there was little evidence about the work on
the 1999 invoice. We did not receive any of the back
up documentation providing daily hours and descriptions
of the work such as had been attached to the 1997 invoice
from T. Lewis Trucking that was not claimed. We do not
know whether the road that was included in this work
was one that served only the potential chip pile site
or was the road used by all the logging trucks that
accessed the Doerr parcel. Further, at the time that
this invoice was incurred, the claimants knew that the
respondent had only taken 0.6 acres of usable space
from the subject property. We do not know the size of
the new yard but the photos in evidence suggest that
it is larger than the 0.6 acres of usable land that
were taken. For all these reasons the claim for this
invoice is denied.
[144] The claimants have
also claimed for work that they would need to do to
re-establish a base for a chip pile on the Doerr property.
This is claimed at 80 bone dry units of chips (to cover
an area 200 feet square -- 0.37 hectares or 0.9 acres)
x $81.50 per unit for a total of $6,520. This work has
not been done. Chips have not been stored on site since
the taking. We understand that there may be a need to
stock pile them in the future if the mill that processes
chips stops production temporarily. However, in the
absence of clear evidence that the work will be done
any claim for this work is speculative. This board has
refused to award damages for losses that are speculative
and may never be incurred. See Patterson v. British
Columbia (Ministry of Transportation and Highways)
(1994), 53 L.C.R. 88 (B.C.E.C.B.); aff'd 62 L.C.R. 89
(B.C.C.A.); Maddocks v Surrey (City) (2001),
73 L.C.R. 161 (B.C.E.C.B.); and Bayview Builders
Supply.
8.3.3 Consolidated
Exchange Parcel invoices
[145] In September 1999
Mr. MacDonald billed $1,719 excluding GST ($1,305 in
fees) for the transfer of the consolidated exchange
parcel. The Property Purchase Tax of $7,220 for this
property was also claimed.
[146] The claimants chose
to purchase the consolidated exchange parcel. We have
concluded that the claimants' reasons for wanting to
acquire the consolidated exchange parcel rather than
permitting the Ministry to build a public road to the
original mill site are to do with the increased production
at the mill and the need for more space. The claimants
entered into a contractual agreement with respect to
the purchase of the consolidated exchange parcel. As
part of the contractual agreement the claimants agreed
that "upon the transfer of the Consolidated Exchange
Parcel on the agreed terms that the Ministry has complied
with its obligations to replace the access taken with
reasonable access". The claimants did not agree
to release anything further. Nonetheless when we construe
the contract, the claim for the acquisition costs appears
to be precluded. In any event, given our conclusion
that the claimants chose the option to acquire the consolidated
exchange parcel in order to gain more space, then it
follows that the acquisition costs are not directly
attributable to the taking (or the closure of the highway
access) nor do they result from the project. We note
that we have already awarded a portion of the legal
fees and the PPT for the purchase of the Doerr parcel
since a portion of the Doerr parcel may be treated as
replacement of the subject property that was taken.
The claims for legal fees and the PPT for the consolidated
exchange parcel are denied.
[147] In March 2001 Mr.
MacDonald also billed $2,612.20 excluding GST ($1,935
in fees) for the cancellation of the statutory building
scheme and the land use contract that were still on
title after the consolidated exchange parcel had been
transferred to the claimants. The contractual agreement
provides that "the consolidated exchange parcel
will be consolidated into a single legal parcel at the
Ministry's cost". When we construe the terms of
the agreement it appears to us that the Ministry was
obligated to provide clear title for the single legal
parcel. However, as we have indicated above, costs in
relation to the consolidated exchange parcel are not
directly attributable to the taking (or the closure
of highway access) nor do they result from the project.
Thus we cannot award this claim.
[148] There were three
small claims: Paul's Fine Woodworking $160.00; Mitchell
Mearns $278.00; and Ike Stutters $612.50. Pauls Fine
Woodworking billed Gorman Bros. $2,781 excluding GST
on July 27, 1999 but only $160 of this sum is claimed.
Similarly Mitchell Mearns invoice dated July 27, 1999
is for $2,591.50 but only $278 has been claimed. Ike
Stutters' invoice dated October 1999 is for $2,340 but
only $612.50 is claimed. In all three cases an employee
of Gorman Bros. has assigned codes for portions of the
invoice. One code is for the highway and it is the sums
that were given the highway code that are being claimed.
Mr. Tracey told us that the work was to clean up the
consolidated exchange parcel and the panhandle property.
We were not provided with any further evidence. It is
not clear what work was done or why particular work
was attributed to highways. In any event, we have stated
that costs in relation to the consolidated exchange
parcel do not result from the project. As a result these
claims are denied.
8.3.4 Access issue
invoices
[149] The claimants have
requested reimbursement for a total of $34,094.54 paid
to Emil Anderson for construction work on the mill access
in August and September 1999. This work was to construct
the private road through the panhandle at the end of
Dunfield Road. The invoices also included work billed
to Ron and Jenifer Gorman and Ross and Eunice Gorman
but the claim by the personal claimants has settled
and the work that was billed to them has been excluded
from what was claimed.
[150] The claimants have
not submitted a claim for the construction of the new
private road on the consolidated exchange parcel. This
is because they have been given a credit for the cost
of constructing the hypothetical public road of approximately
$259,000. In the contractual agreement for the transfer
of the consolidated exchange parcel the claimants agreed
that "upon the transfer of the Consolidated Exchange
Parcel on the agreed terms that the Ministry has complied
with its obligations to replace the access taken with
reasonable access". The evidence shows that Gorman
Bros. chose to locate the new private road through the
panhandle as well as the consolidated exchange parcel
and that this choice was made to gain more space and
to improve the efficiency of the site for functions
other than access. We agree with the Ministry that placing
the road on the panhandle was not necessary to restore
access. It was not directly attributable to the taking
(or the closure of highway access), nor was it a result
of the project. Therefore this claim is denied.
[151] There was an invoice
from Clermont Crane dated June 1, 1999 for $600.00 to
hoist an old building that was in the path of the new
access road that had been chosen. It was not entirely
clear whether this building was on property needed for
the public Dunfield Road or the panhandle. It was also
not clear whether the building was moved to a new location
on either Ross and Eunice's property or the mill site.
Gorman Bros. decided to preserve this old shed in which
John Gorman, one of the founders of Gorman Bros., had
worked to house a museum for Gorman Bros. We have found
that Gorman Bros. chose to locate the access road through
the panhandle rather than placing it entirely on the
consolidated exchange parcel in order to increase space
and enhance the efficiency of the remainder of the consolidated
exchange parcel for purposes other than access. Choosing
to locate the access road through the panhandle required
an extension of the public road into Ross and Eunice
Gorman's property. We have already found that use of
the panhandle was not directly attributable to the taking
(or the closure of highway access), nor did it result
from the project. Any taking from Ross and Eunice Gorman
has settled and we lack jurisdiction. We must deny this
claim.
8.3.5 Miscellaneous
invoices
[152] The Kent Macpherson
invoice of $343.75 dated July 4, 2001 states that it
was for research and assembly of historic information
in preparation of Discoveries, tracking down old files
and meeting with counsel. There was agreement by counsel
that this was a disturbance damage rather than a claim
for costs. We infer that this expense was directly attributable
to the taking and award this sum.
[153] There were five invoices
from Mr. MacDonald dating between March and July 2000,
which totalled $4,072.65 excluding GST ($2,570 in fees).
Three of these invoices state that they were for work
to do with easements. Two accounts have different file
numbers and say they are to do with the Ministry of
Transportation. The time frame for the work billed on
these two accounts overlaps with the time frame for
the work in the file that is to do with easements. We
understand that the work to do with easements was for
several easements necessary for properties owned by
Ron and Jenifer Gorman and/or Ross and Eunice Gorman
as a result of the project. The evidence establishes
that one or more of these easements were through the
Doerr parcel after it had been acquired by the claimant
Dunfield Holdings. The Ministry clearly acknowledged
it would pay for Mr. MacDonald's work to put these easements
in place. We do not have evidence as to whether they
were submitted to the Ministry at the time that they
were incurred. There is evidence that the Ministry paid
$66,844.78 for costs associated with the residential
accesses but we do not know what those costs included.
These invoices from Mr. MacDonald arise out of the personal
claims. We were told that the claims of the four personal
owners against the Ministry had settled. We do not see
that we have any jurisdiction to consider them as part
of the present claim. As a result these claims are denied.
8.3.6 Reid Crowther
invoices
[154] The claimants are
claiming a total of 20 invoices from Reid Crowther the
firm that supplied engineering services to the claimants.
These invoices are dated between August 1997 and February
2001 and total $38,969.73 excluding GST. We heard evidence
from David Cullen who was a civil engineer with Reid
Crowther and who had done some of the work that was
billed. We also had the invoices, the cover letters
sent to Gorman Bros. and a breakdown of the invoices
prepared by Mr. Cullen shortly before the hearing. We
also had extensive documentation between the claimants
and the Ministry with respect to the invoices. The claimants
point out a number of references in these documents
whereby the Ministry stated that it would be responsible
for various engineering costs incurred by the claimants.
[155] As indicated above
the Ministry says that these invoices should not be
paid. The invoices can be categorized under different
headings such as being incurred in relation to access,
or the consolidated exchange parcel or more recently
for the shaded area and none of this work is caused
by the expropriation or the project.
[156] The evidence provided
to us was that only four of these invoices have been
submitted to the Ministry around the time that they
were incurred. The documentation shows that the Ministry
requested particulars of who had done the work on each
invoice, their qualifications and hourly rate and what
each of these persons had done. This information was
supplied and the Ministry's Project Director, Mr. Osborne,
categorized the engineering work into four categories.
The Ministry agreed that three of these categories totalling
$6,038.10 should be paid and this sum was eventually
paid on April 11, 2000. The Ministry refused to pay
the fourth category of $11,989.58 on the basis that
the description for this work appeared to be for access
to the mill and the contractual agreement for the consolidated
exchange parcel already gave the claimant the cost of
constructing the hypothetical public road including
engineering services. Paying both would amount to double
recovery. The claimants protested this refusal and said
that the work on the hypothetical road was never done
and the actual invoices for work that resulted from
the expropriation should be paid. The remainder of the
invoices were supplied to counsel for the Ministry a
few months before the hearing, with a suggestion that
they might be settled before the hearing.
[157] A review of the 20
Reid Crowther invoices indicates that they themselves
contain little detail as to what the services are that
they cover. There is a project name: 13 of them are
named access issues, 5 are named Gorman's advisory services,
one is named site grading and one is named Gorman Bros.
ESA (an environmental assessment). There is no further
description on the invoice as what was done although
there is breakdown of staff hours and rates and disbursements.
The cover letters to Gorman Bros. enclosing the invoices
do provide a brief summary of work done during the period
of that invoice. Examples of these work summaries include
review access options, produce site plan, site review
of revised property boundary, revised drawing for property
regulations, meetings with Ministry, rezoning application,
engineering requirements for shaded areas, and access
design.
[158] Mr. Cullen testified
that Reid Crowther's work fell into three categories:
work that was done for the contractor for the project,
Emil Anderson, and was billed to them; work that was
done for Gorman Bros. that Gorman Bros. has claimed
and work that was done for Gorman Bros. that Gorman
Bros. has not claimed. Reid Crowther made no differentiation
between the latter two categories. It was someone at
Gorman Bros. who decided what should be claimed.
[159] Mr. Cullen produced
a further breakdown for the four invoices submitted
in late 1999. Shortly before the hearing he provided
a further breakdown for the remainder of the invoices.
This breakdown states that a particular employee spent
so many hours (at a given hourly rate) on specific activities
such as to prepare base plans and calculate material
volumes for the new access; to prepare rezoning and
ALR application information; to meet with the Ministry
and Gormans to discuss property and access issues; to
review options for relocation of water line on consolidated
exchange parcel; to site review of revised consolidated
exchange parcel boundary and review of revised drawings;
and to draft new plans for shaded area. The administrative
time billed on the invoices has generally been excluded
in this breakdown but the disbursements are detailed.
We note that since one invoice can cover work on up
to six different properties it is only with these breakdowns
that allocation of work to different projects is generally
possible. As Mr. Osborne pointed out some of the descriptions
remain rather general. We are not in any way implying
a criticism of Reid Crowther's invoicing procedures;
we are simply describing what information was present
and the difficulties faced by someone trying to categorize
work into different headings for the purposes of seeking
reimbursement. While we appreciate the information contained
in the breakdowns, instead of 20 invoices from Reid
Crowther, there are now over 60 separate categorizations
of work for so many hours at so much an hourly rate
not counting the disbursements.
[160] It is certainly the
case that the Ministry stated more than once that it
would be responsible for various engineering costs incurred
by the claimants. At the beginning of the project in
October 1991, the minutes reflect that a Ministry employee
asked Gorman Bros. to retain a consultant to verify
the need for capital expenditures such as moving the
office building and the scales for weighing logs. Later,
in February 1996, Mr. Menu, a property services manager
for the Ministry in a letter to the claimants stated
that a consultant was required to address the claimants'
concerns about the impact of the project. This consultant
would
"work in close concert with
Urban Systems to prepare an overall design of the
changes that need to be made to the mill site. In
addition the consultant will prepare a grading plan
for the mill site and adjoining surplus Ministry land
[that eventually became the consolidated exchange
parcel]. It is the Ministry's preference that the
consultant be retained by Gorman Bros. and be in their
employ. The costs of the consultant would be reimbursed
by the Ministry as part of an overall settlement."
[161] In November 1998
a memo written by Mr. Tracey about a meeting with the
Ministry says that Reid Crowther is to examine internal
traffic flow and access for the claimants' property
on both sides of highway and that the Ministry would
pay the cost. In December 1998 Mr. Walker, a property
agent for the Ministry who now has responsibility for
this file, writes the following to Mr. Cosburn, counsel
for the claimants:
"it is our understanding
that [Gorman Bros.] would be contracting with Reid
Crowther Engineering to undertake a design for a relocated
mill access. We had further indicated to Mr. Tracey
that the Ministry would reimburse the reasonable costs
of said engineering study."
In January 1999 Mr. Walker told Mr.
Cosburn, that "the Ministry will reimburse the
costs of the engineering study [for relocated access
through the consolidated exchange parcel]."
[162] However, all of these
comments were made prior to the agreement in principle
in March 1999, signed in June 1999, on the price for
the consolidated exchange parcel that included a credit
for the costs of constructing the hypothetical public
road including $11,000 for engineering design services.
Mr. Cullen testified that the $11,000 was calculated
as a five per cent allowance on the estimated costs
to construct the hypothetical public road. Mr. Cullen
said that no detailed engineering design was ever done
for the hypothetical public road since it was never
built. He described detailed engineering designs as
being between three and six separate plans and profiles
containing necessary geotechnical information, as well
as drainage and electrical requirements in sufficient
detail so that contractors could bid on the project.
He also said that no detailed engineering design was
ever done for the actual private road that was built,
although there were numerous general layouts prepared.
[163] We agree with the
Ministry that the claimants are not entitled to both
the engineering costs incurred to build the private
road and to a credit for the engineering costs to build
the hypothetical public road. These costs are for equivalent
things and cannot be recovered twice. In our opinion
it is irrelevant that the detailed design work for the
hypothetical public road that was never carried out
would have involved different engineering tasks than
the general layouts that were done. The claimants were
given a credit for costs for detailed design work that
they never needed to incur. Instead they incurred the
costs for different engineering work that gave them
an internal private road that integrated with the mill
site. We note that the claimants made no claim for the
construction costs to build the private road on the
consolidated exchange parcel because they had been given
a credit for the construction costs to build the hypothetical
public road. While the construction of the two roads
may have differed in layout and standard of construction,
they were for equivalent things and the claimants are
not entitled to both. The engineering costs incurred
to build the private road are similar. However, it appears
that Reid Crowther billed approximately $3,000 in November
1999 and January 2000 for work to calculate the area
and costs to construct the hypothetical public road.
These fees in our view should be treated as costs incurred
to assert the claimants' claim that are to be reimbursed
under section 45.
[164] We also agree with
the Ministry that the costs for engineering services
associated with acquiring the consolidated exchange
parcel and the shaded area were not directly attributable
to the taking (or the closure of highway access) nor
did they result from the project. We have already found
that the claimants acquired the consolidated exchange
parcel in order to maximize the space for uses other
than access. It may be true that there would have been
no shaded areas if the Ministry had built the project
on the more usual tendered design model since all the
surplus land would have been identified prior to the
project having been built. However, the fact that the
Ministry used a Design/Construct model does not entitle
the claimants to compensation for additional expenses
in acquiring more land to add to the consolidated exchange
parcel.
[165] One of the invoices
was for the engineering costs for an environmental assessment
of the Doerr parcel when it was acquired in 1997. Mr.
Cullen stated that this was an expense often incurred
for a purchaser of industrial property. We were given
no further information on this expense. Mr. Cullen's
breakdown stated that a copy of the proposal for Phase
1 ESA was attached but we were not provided with this
attachment. We do not know if the work was only on the
2.5 acres that had been leased for log storage or if
it was for the entire 18 acres with potential industrial
use, some of which was a potential replacement site
for the 2.4 acres that were eventually taken from the
subject property. Without further information we are
unable to assess whether the work on this invoice was
directly attributable to the taking or resulted from
the project. Since this claim has been adjourned, the
claimants may be able to provide more evidence to the
respondent.
[166] We also agree with
the Ministry that the costs on invoice #56464 dated
March 13, 2000 for services for rezoning and ALR application
were not directly attributable to the taking nor did
they result from the project. The evidence established
that this work was for an application on the Doerr parcel
for the access road that took logs to the Doerr parcel.
The land on which the access road was constructed was
in the ALR and the application was for a land exchange
to remove this land from the ALR and replace it with
another piece of the Doerr parcel. It appears that this
problem predated the project and had nothing to do with
the taking or the project. Similarly, we agree with
the Ministry as to the accounts to do with the application
for a permit to occupy the Ministry right of way. The
claimants had apparently been using the right of way
in two areas for a number of years and while the Ministry
did not object, it requested that the claimants acquire
a permit. This work was not directly attributable to
the taking nor did it result from the project.
[167] There may be other
items listed in the breakdown of the Reid Crowther invoices
not covered by this analysis. Given the number of claims
and the state of the evidence we adjourn the Reid Crowther
invoices so that the parties can apply the analysis
and work out what amount is to be paid to the claimants.
If the parties are not able to agree on payment they
may make an application on any outstanding invoices,
preferably by written submissions and if any further
evidence is necessary, by affidavit.
8.4 Summary of disturbance
damages
[168] In summary the board has awarded
the following invoices:
Reid Crowther invoices
adjourned |
|
adjourned |
John MacDonald invoices |
purchase of Doerr parcel |
$ 9,069.44 |
|
Tingstad easement on subject |
adjourned |
Kent Macpherson account |
|
$ 343.75 |
DA Goddard invoice |
|
$ 250.00 |
Pro rata PPT for Doerr
parcel |
|
$ 3,905.00 |
Total |
|
$13,568.19 |
9. SUMMARY
[169] The claimants have
been awarded the following:
1. |
market
value of the partial taking and injurious affection
to the remainder of the subject property |
$205,500.00 |
2. |
compensation for
the purchase of the Doerr parcel that is in excess
of market value |
nil |
3. |
compensation
for the accelerated depreciation of the
office building |
$ 27,612.00 |
4. |
disturbance
damages for various expenses that are directly
attributable to the taking or that result from
the project including: |
|
|
Reid Crowther invoices |
adjourned |
|
John MacDonald invoices |
purchase of Doerr parcel |
$ 9,069.44 |
|
|
Tingstad easement on subject
|
adjourned |
|
Kent MacPherson account |
$ 343.75 |
|
DA Goddard invoice |
$ 250.00 |
|
Pro rata PPT for
Doerr parcel |
$ 3,905.00 |
|
Total |
$246,680
rounded |
10. INTEREST
[170] The claimants are
seeking interest under sections 46 and 47 of the Act.
10.1 Section 46(1) interest,
Regular interest
[171] We have awarded the
claimants a total of $246,680. The advance payments
totalled $126,870.89: $119,000 was paid on February
9, 1999, $1,832.79 was paid on October 22, 1999 and
$6,038.10 was paid on April 11, 2000.
[172] We have awarded the
claimants $205,500 for the market value of the land
taken. Under section 46(1)(a) of the Act, the claimant
is entitled to interest on any amount awarded for the
market value in excess of any amount paid by the Ministry
under section 20(1) or (12), taking into account moneys
paid by the Ministry to the claimant on account of compensation
from time to time, with interest to be calculated annually
at the rates specified in section 46(2) and (3). Under
Section 46(1)(a) interest is due from the date that
the claimants gave up possession which we assume was
February 9, 1999, until paid, taking into account the
various advance payments.
[173] We have awarded the
claimants $27,612 for the disturbance damages or business
loss for the accelerated obsolescence of the office
building resulting from the project. Existing access
to the mill site was not lost until October 1999 and
therefore we consider that it is reasonable that interest
is payable on $27,612 from November 1, 1999, until paid.
[174] We have awarded the
claimants $13,568.19 for various expenses and losses
claimed as disturbance damages or business losses. It
appears to us under section 46(1)(b) that with respect
to the date from when interest is to run that it is
not only the date that costs were incurred by the claimants
that is relevant but when the invoices were provided
to the Ministry with a request for reimbursement. Most
of the invoices that were submitted appear to have been
incurred in 1999 and 2000, although some date from 1997
and some date from 2001. We know that one invoice from
Mr. MacDonald and four invoices from Reid Crowther on
which there was a partial payment were provided to the
Ministry. There were notations on some invoices that
lead us to assume that copies may have gone to the Ministry.
We know that the Reid Crowther invoices went to the
Ministry a few months prior to the hearing with an invitation
to settle. However, it appears that some of the invoices
that were claimed were presented for reimbursement for
the first time at the hearing. In the circumstances
we consider that it is reasonable that interest under
section 46(1) on $13,568.19 run from December 31, 1999
as the approximate midpoint of the invoices until paid.
10.2 Section 46(4),
Additional interest
[175] The advance payments
under section 20 of $126,870.89 were 51.4% of the total
compensation awarded of $246,680. Under section 46(4)
of the Act, the advance payment was less than 90% of
the total compensation awarded. In Bill's Frontier
Restaurant Ltd v. British Columbia (Minister of Transportation
and Highways) (1994), 53 L.C.R. 175 this board determined
that under section [46(4)] if business loss was to be
excluded from the compensation awarded it should also
be excluded from the advance payment made under section
[20]. In Sequoia Springs West Development Corp. v.
British Columbia (Minister of Transportation and Highways)
(2000), 71 L.C.R. 153 this board found that business
losses excluded under section 45(4) should be construed
restrictively to mean business losses following relocation
of a business under section 34(3). In our opinion, the
business losses that are excluded under section 46(4)
should be the same ones as excluded under section 45(4).
See Pay Less Gas Co. (1972) Ltd. v. British Columbia
(Minister of Transportation and Highways) unreported,
June 20, 2002, E.C.B.# 8/91/223. None of the award or
advance payment is in our view a business loss under
section 34(3) that should be excluded. As a result the
Ministry must pay additional interest, at an annual
rate of five percent, on the principal amount outstanding
at February 9, 1999 of $127,680 ($246,680 - $119,000)
and on the new principal amounts outstanding after the
further advance payments on October 22, 1999 and April
11, 2000 until the date of this decision. We note that
under section 46(4) additional interest runs on the
difference between the amount awarded and the advance
payment from the date of the first payment even if specific
portions of the award were only incurred later. This
board in Richland Farms Ltd. v. British Columbia
(Ministry of Transportation and Highways) (1991),
46 L.C.R. 66 established the basis upon which an award
for additional interest is to be made. First, while
interest under section 46(1) compounds annually, additional
interest under section 46(4) provides for simple interest
only. Second, the calculation of additional interest
runs on the outstanding difference from the date of
each advance payment.
10.3 Section 47, Penalty
interest
[176] The claimants also
claim penalty interest under section 47 for what they
say was the respondent's unreasonable delay particularly
with respect to access and the payment of the Reid Crowther
invoices. The claimants sat that they spent monies in
dealing with the expropriation and the respondent took
no steps in providing alternative access to the mill
site. Given the findings we have made there was no reason
for the Ministry to make plans to provide alternative
access to the mill site. We have expressed our view
that the Ministry's delay in transferring the consolidated
exchange parcel or rather in offering the claimants
a choice about access, was unfortunate. But we are satisfied
that the Ministry could have provided access by public
road between March 1999 and October 1999 when the existing
access was closed. As a result we do not find any basis
for unreasonable delay with respect to the provision
of access. We have adjourned the claim for the Reid
Crowther invoices. In any event, given the fact that
the claimants did not submit any more of these invoices
to the Ministry for payment until a few months prior
to the hearing we do not find any unreasonable delay
by the Ministry in paying these invoices.
11. COSTS
[177] The claimants seek
costs under section 45 of the Act and the Tariff
of Costs Regulation, B.C. Reg 189/99 (the Tariff)
at Scale 3 while the respondent's position is that Scale
2 is appropriate.
[178] We have awarded $246,680
in compensation which is 194% of the advance payments
of $126,870.89. 194% is greater than 115% of the advance
payments and as a result under section 45(4) of the
Act the claimants are entitled to their costs. In our
opinion the legal issues in this file were of more than
ordinary difficulty. It was a partial taking of the
subject property and relocated access for both the subject
property and the main mill site as well. There was an
easement on the subject property that had to be relocated.
There were steps taken to replace one of the uses of
the subject property on other land that had been acquired.
There were complicated issues of causation. As a result
we award legal costs on Scale 3. The appraisal issues
in this file with respect to the subject property were
of ordinary difficulty and therefore appraisal costs
are awarded at Scale 2. We conclude that the claimant
is entitled to its actual reasonable legal, appraisal,
and other costs until June 28, 1999 and to its costs
as prescribed in the Tariff of Costs Regulation,
B.C. Reg 189/99 after that date with legal costs at
Scale 3 and appraisal costs at Scale 2.
THEREFORE IT IS ORDERED THAT
the respondent, the Ministry of Transportation, shall
pay the Claimant Gorman Bros. Lumber Ltd.:
1. |
Compensation
in the amount of $205,500 for the market value of
its fee simple interest in the expropriated property
and the reduction in market value of the remainder
pursuant to section 40 of the Act. |
2. |
Compensation
in the amount of $27,612 for the depreciated value
of the office building pursuant to section 40 of
the Act. |
3. |
Compensation
in the amount of $13,568.19 for disturbance damages
or business losses pursuant to section 40 of the
Act. Two claims for disturbance damages have been
adjourned. |
4. |
Interest on the monies
awarded pursuant to section 46(1) of the Act as
follows: |
|
(a) |
on $205,500
for the market value of the fee simple interest
in the expropriated property and the reduction in
market value of the remainder from February 9, 1999
until paid; |
|
(b) |
on $27,612
for the accelerated depreciation of the office building
from November 1, 1999 until paid; |
|
(c) |
on $13,568.19
for disturbance damages or business losses from
December 31, 1999 until paid; |
with
adjustments to take into account moneys paid by
the respondent to the claimant as compensation pursuant
to section 20(1) and (12) of the Act. Pursuant to
section 46(2) of the Act, interest shall be calculated
annually at the following rates: |
|
|
i. |
Six
and three-quarters per cent (6.75%) from January
1, 1999 to June 30, 1999. |
|
|
ii. |
Six
and one-quarter per cent (6.25%) from July 1, 1999
to December 31, 1999. |
|
|
iii. |
Six and one-half
per cent (6.5%) from January 1, 2000 to June 30,
2000. |
|
|
iv. |
Seven and one-half
per cent (7.5%) from July 1, 2000 to December 31,
2000. |
|
|
v. |
Seven and one-half
per cent (7.5%) from January 1, 2001 to June 30,
2001. |
|
|
vi. |
Six and one-quarter
per cent (6.25%) from July 1, 2001 to December 31,
2001. |
|
|
vii. |
Four per cent (4.00%)
from January 1, 2002 to June 30, 2002. |
|
|
viii. |
Four and one quarter
per cent (4.25%) as of June 28, 2002. |
5. |
Additional
interest at five per cent (5.0%) pursuant to section
46(4) of the Act on $127,680 from February 9, 1999
until the date of this decision with adjustments
to take into account further moneys paid by the
respondent to the claimant as compensation pursuant
to section 20(1) and (12) of the Act on October
22, 1999 and April 11, 2000. |
6. |
Pursuant
to section 45 of the Act the actual reasonable legal,
appraisal and other costs for the purpose of asserting
the claims for compensation or damages until June
28, 1999 and to the reasonable costs under the Tariff
of Costs Regulation, B.C. Reg 189/99 after that
date with legal costs at Scale 3 and appraisal costs
at Scale 2. |
|