1 In this regulation:
"Act" means the Renewable Energy Projects (Streamlined Permitting) Act;
"North Montney Transmission Line project" means the project to construct and operate an electric transmission line, and related facilities, from around the Site C Dam northwest no farther than the Buckinghorse River;
"North of Terrace Transmission Line project" means the project to construct and operate an electric transmission line, and related facilities, from around Terrace to around Bob Quinn Lake.
2 The following projects are prescribed for the purposes of section 2 (c) [streamlined projects] of the Act:
3 The streamlined projects referred to in section 2 (c) and (d) are prescribed for the purposes of section 5 (b) [application of Division 2 — level 2 streamlining] of the Act.
4 The streamlined project referred to in section 2 (d) is prescribed for the purposes of section 14 (d) [application of Environmental Assessment Act] of the Act.
5 Sections 6 and 9 [application of Energy Resource Activities Act] of the Act do not apply in relation to the Treaty 8 Planning and Mitigation Regulation, B.C. Reg. 146/2023.