B.C. Reg. 93/2025
O.C. 321/2025
Deposited June 27, 2025
effective July 1, 2025
This consolidation is current to December 9, 2025.
Link to consolidated regulation (PDF)

Renewable Energy Projects (Streamlined Permitting) Act

Renewable Energy Projects (Streamlined Permitting) Regulation

Definitions

1   In this regulation:

"Act" means the Renewable Energy Projects (Streamlined Permitting) Act;

"North Montney Transmission Line project" means the project to construct and operate an electric transmission line, and related facilities, from around the Site C Dam northwest no farther than the Buckinghorse River;

"North of Terrace Transmission Line project" means the project to construct and operate an electric transmission line, and related facilities, from around Terrace to around Bob Quinn Lake.

Streamlined projects

2   The following projects are prescribed for the purposes of section 2 (c) [streamlined projects] of the Act:

(a) wind energy projects;

(b) solar energy projects;

(c) the North Montney Transmission Line project;

(d) the North of Terrace Transmission Line project.

Level 2 streamlining

3   The streamlined projects referred to in section 2 (c) and (d) are prescribed for the purposes of section 5 (b) [application of Division 2 — level 2 streamlining] of the Act.

Application of Environmental Assessment Act

4   The streamlined project referred to in section 2 (d) is prescribed for the purposes of section 14 (d) [application of Environmental Assessment Act] of the Act.

Limits on application of Act

5   Sections 6 and 9 [application of Energy Resource Activities Act] of the Act do not apply in relation to the Treaty 8 Planning and Mitigation Regulation, B.C. Reg. 146/2023.

[Provisions relevant to the enactment of this regulation: Renewable Energy Projects (Streamlined Permitting) Act, S.B.C. 2025, c. 12, ss. 13 and 20.]