Division C
Administrative Provisions

Part 3 — Appeals, Offences and Penalties and Transition Provisions

Section 3.3. change beginTransition Provisions

3.3.1. General

3.3.1.1. Validity of Permits Issued under Previous By-law
1) Subject to the provisions of Articles 1.5.2.4. and 3.3.1.2., buildings for which permits were obtained under By-law No. 9419 may be constructed in accordance with the provisions of that By-law.
3.3.1.2. Grace Period
1) Where an owner has applied for a permit prior to January 1, 2015, a building may be constructed in accordance with By-law No. 9419 if, in the opinion of the Chief Building Official, the owner has commenced the work authorized by the permit within 6 months of the date of issuance of the permit and the owner has continued work to completion without interruption other than work stoppages which are standard in the building industry.change end