Division B
Acceptable Solutions

Part 2 — Plumbing Systems

Section 2.3. Piping

2.3.1. Application

2.3.1.1. General
1) Intent StatementThis Section applies to the construction and use of joints and connections, and the arrangement, protection, support and testing of piping.

2.3.2. Construction and Use of Joints

2.3.2.1. Caulked Lead Drainage Joints
1) Intent StatementCaulked lead drainage joints shall not be used except for cast-iron pipe in a drainage system or venting system, or between such pipe and
a) other ferrous pipe,
b) brass and copper pipe,
c) a caulking ferrule, or
2) Intent StatementEvery caulked lead drainage joint shall be firmly packed with oakum and tightly caulked with lead to a depth of not less than 25 mm.
3) Intent StatementNo paint, varnish or other coating shall be applied on the lead until after the joint has been tested.
4) Intent StatementA length of hub and spigot pipe and pipe fittings in a drainage system shall be installed with the hub at the upstream end.
2.3.2.2. Wiped Joints
1) Intent StatementWiped joints shall not be used except for sheet lead or lead pipe, or between such pipe and copper pipe or a ferrule.
2) Intent StatementEvery wiped joint in straight pipe shall
a) be made of solder,
b) have an exposed surface on each side of the joint at least 19 mm wide, and
c) be not less than 10 mm thick at the thickest part.
3) Intent StatementEvery wiped flanged joint shall be reinforced with a lead flange that is not less than 19 mm wide.
2.3.2.3. Screwed Joints
1) Intent StatementIn making a screwed joint, the ends of the pipe shall be reamed or filed out to the size of the bore and all chips and cuttings shall be removed.
2) Intent StatementNo pipe-joint cement or paint shall be applied to the internal threads.
2.3.2.4. Soldered Joints
1) Intent StatementSoldered joints shall be made in accordance with ASTM B 828, “Making Capillary Joints by Soldering of Copper and Copper Alloy Tube and Fittings.”
2.3.2.5. Flared Joints
1) Intent StatementIn making a flared joint, the pipe shall be expanded with a proper flaring tool.
2) Intent StatementFlared joints shall not be used for hard (drawn) copper tube.
2.3.2.6. Mechanical Joints
1) Intent StatementMechanical joints shall be made with compounded elastomeric rings that are held in compression by
a) stainless steel or cast-iron clamps, or
b) groove and shoulder type mechanical couplings.
(See Appendix A.)
2.3.2.7. Cold-Caulked Joints
1) Intent StatementCold-caulked joints shall not be used except for bell and spigot pipe in a water system, a drainage system or a venting system.
2) Intent StatementCaulking compound used in cold-caulked joints shall be applied according to the manufacturer's directions.
3) Intent StatementEvery cold-caulked joint in a drainage system shall be firmly packed with oakum and tightly caulked with cold caulking compound to a depth of not less than 25 mm.
2.3.2.8. change beginStainless Steel Welded Joints
1) Welding shall conform to ASME B31.9, “Building Services Piping,” and accord with good engineering practice.
2) Butt weld pipe fittings shall have an equal or thicker section than the pipe wall specified.change end

2.3.3. Joints and Connections

2.3.3.1. Drilled and Tapped Joints
1) Intent StatementDrilled and tapped joints shall not be made in a soil-or-waste pipe or vent pipe and fittings unless suitable provision has been made for drilling and tapping.
2.3.3.2. Extracted Tees
1) Intent StatementTees may be extracted from the wall thickness of Types K and L copper tube used in a water distribution system provided that
a) a tool specifically designed for the purpose is used,
b) the branch is at least one size smaller than the tube in which the tee is formed,
c) the end of the branch incorporates a means to prevent it from penetrating into the run and thereby obstructing flow, and
d) the joint at the tee is brazed with a filler metal having a melting point not below 540°C.
2.3.3.3. Prohibition of Welding of Pipes and Fittings
1) Intent StatementCast-iron soil pipe and fittings shall not be welded.
2) Intent StatementGalvanized steel pipe and fittings shall not be welded.
2.3.3.4. Unions and Slip Joints
(See A-2.2.3.1.(1) and (3) in Appendix A.)
1) Intent StatementRunning thread and packing nut connections and unions with a gasket seal shall not be used downstream of a trap weir in a drainage system or in a venting system.
2) Intent StatementA slip joint shall not be used
a) in a venting system, or
b) in a drainage system, except to connect a fixture trap to a fixture drain in an accessible location.
2.3.3.5. Increaser or Reducer
1) Intent StatementEvery connection between 2 pipes of different size shall be made with an increaser or a reducer fitting installed so that it will permit the system to be completely drained.
2.3.3.6. Dissimilar Materials
1) Intent StatementAdaptors, connectors or mechanical joints used to join dissimilar materials shall be designed to accommodate the required transition.
2.3.3.7. Connection of Roof Drain to Leader
1) Intent StatementEvery roof drain shall be securely connected to a leader and provision shall be made for expansion.
2.3.3.8. Connection of Floor Outlet Fixtures
1) Intent StatementEvery pedestal urinal, floor-mounted water closet or S-trap standard shall be connected to a fixture drain by a floor flange, except that a cast-iron trap standard may be caulked to a cast-iron pipe.
2) Intent StatementExcept as provided in Sentence (3), every floor flange shall be brass.
3) Intent StatementWhere cast-iron or plastic pipe is used, a floor flange of the same material may be used.
4) Intent StatementEvery floor flange shall be securely set on a firm base and bolted to the trap flange of the fixture.
5) Intent StatementEvery joint in a floor flange shall be sealed with a resilient watertight and gas-tight seal.
6) Intent StatementWhere a lead water-closet stub is used, the length of the stub below the floor flange shall be not less than 75 mm.
2.3.3.9. Expansion and Contraction
(See Appendix A.)
1) Intent StatementThe design and installation of every piping system shall include means to accommodate its expansion and contraction caused by temperature changes, movement of the soil, building shrinkage or structural settlement. (See Appendix A.)
2.3.3.10. Copper Tube
1) Intent StatementTypes M and DWV copper tube shall not be bent.
2.3.3.11. Indirect Connections
1) Intent StatementWhere a fixture or device is indirectly connected, the connections shall be made by terminating the fixture drain above the flood level rim of a directly connected fixture to form an air break.
2) Intent StatementThe size of the air break shall at least equal the size of the fixture drain, branch or pipe that terminates above the directly connected fixture, and it shall be not less than 25 mm. (See Appendix A.)
2.3.3.12. change beginCopper Joints Used Undergroundchange end
1) Intent StatementExcept as provided in Sentence (2), joints in copper tubes installed underground shall be made with either flared or compression fittings, or be brazed using a brazing alloy within the American Welding Society's AWS-BCuP range.
2) Intent StatementCompression fittings shall not be used underground under a building.

2.3.4. Support of Piping

2.3.4.1. Capability of Support
1) Intent StatementPiping shall be provided with support that is capable of keeping the pipe in alignment and bearing the weight of the pipe and its contents.
2) Intent StatementEvery floor- or wall-mounted water-closet bowl shall be securely attached to the floor or wall by means of a flange and shall be stable.
3) Intent StatementEvery wall-mounted fixture shall be supported so that no strain is transmitted to the piping.
2.3.4.2. Independence of Support
1) Intent StatementPiping, fixtures, tanks or devices shall be supported independently of each other.
2.3.4.3. Insulation of Support
1) Intent StatementWhere a hanger or support for copper tube or brass or copper pipe is of a material other than brass or copper, it shall be suitably separated and electrically insulated from the pipe.
2) change beginWhere a hanger or support for stainless steel pipe or tube is of a material other than stainless steel, it shall be suitably separated and electrically insulated from the pipe or tube.change end
2.3.4.4. Support for Vertical Piping
1) Intent StatementExcept as provided in Sentence (2), vertical piping shall be supported at its base and at the floor level of alternate storeys by rests, each of which can bear the weight of pipe that is between it and the rest above it.
2) Intent StatementThe maximum spacing of supports shall be 7.5 m.
2.3.4.5. Support for Horizontal Piping
1) Intent StatementNominally horizontal piping that is inside a building shall be braced to prevent swaying and buckling and to control the effects of thrust.
2) Intent StatementNominally horizontal piping shall be supported as stated in Table 2.3.4.5.
Table 2.3.4.5.
Support for Nominally Horizontal Piping
Forming part of Sentence 2.3.4.5.(2)
Piping Material Maximum Horizontal Spacing of Supports, m Additional Support Conditions
Galvanized iron or steel pipe    
• diameter ≥  6 inches 3.75  
• diameter < 6 inches 2.5  
change beginStainless steel pipe    
• diameter  ≥  1 inch 3  
• diameter < 1 inch 2.5  
Stainless steel tube    
• diameter  ≥  1 inch 3  
• diameter < 1 inch 2.5change end  
Lead pipe Throughout length of pipe  
Cast-iron pipe 3 At or adjacent to each hub or joint
Cast-iron pipe with mechanical joints that is ≤  300 mm long between adjacent fittings 1  
Asbestos-cement pipe

2(1)

 
Asbestos-cement pipe that is ≤  300 mm long between adjacent fittings 1  
ABS or PVC plastic pipe 1.2

At the end of branches or fixture drains and at changes in direction and elevation

ABS or PVC plastic trap arm or fixture drain pipe > 1 m long

n/a

As close as possible to the trap

CPVC pipe 1  
Copper tube or copper and brass pipe, hard temper, diameter > 1 inch 3  
Copper tube or copper and brass pipe, hard temper, diameter ≤  1 inch 2.5  
Copper tube, soft temper 2.5  
PE/AL/PE composite pipe 1  
PEX/AL/PEX composite pipe 1  
PEX plastic pipe 0.8  
PP-R plastic pipe 1

At the end of branches and at changes in direction and elevation

Notes to Table 2.3.4.5.:

(1) As an alternative, asbestos-cement pipe, which is typically manufactured in 4 m lengths, may have 2 supports per length of pipe.

contentHistory

3) Intent StatementWhere PVC, CPVC or ABS plastic pipe is installed
a) the pipe shall be aligned without added strain on the piping,
b) the pipe shall not be bent or pulled into position after being welded, and
c) hangers shall not compress, cut or abrade the pipe.
4) Intent StatementWhere PEX, PP-R, PE/AL/PE or PEX/AL/PEX plastic pipe is installed, hangers shall not compress, cut or abrade the pipe.
5) Intent StatementWhere hangers are used to support nominally horizontal piping, the hangers shall be
a) change beginsupported bychange end metal rods of not less than
i) 6 mm diam to support piping 2 inches or less in size,
ii) 8 mm diam to support piping 4 inches or less in size, and
iii) 13 mm diam to support piping over 4 inches in size, or
b) solid or perforated metal straps of not less than
i) 0.6 mm nominal thickness and 12 mm wide to support piping 2 inches or less in size, and
ii) 0.8 mm nominal thickness and 18 mm wide to support piping 4 inches or less in size.
6) Intent StatementWhere a hanger is attached to concrete or masonry, it shall be fastened by metal or expansion-type plugs that are inserted or built into the concrete or masonry.
2.3.4.6. Support for Underground Horizontal Piping
1) Intent StatementExcept as provided in Sentence (2), nominally horizontal piping that is underground shall be supported on a base that is firm and continuous under the whole of the pipe. (See Appendix A.)
2) Intent StatementNominally horizontal piping installed underground that is not supported as described in Sentence (1) may be installed using hangers fixed to a foundation or structural slab provided that the hangers are capable of
a) keeping the pipe in alignment, and
b) supporting the weight of
i) the pipe,
ii) its contents, and
iii) the fill over the pipe.
2.3.4.7. Support for Vent Pipe above a Roof
1) Intent StatementWhere a vent pipe that may be subject to misalignment terminates above the surface of a roof, it shall be supported or braced. (See Article 2.5.6.5. for location of vent pipe terminals.)

2.3.5. Protection of Piping

2.3.5.1. Backfilling of Pipe Trench
1) Intent StatementWhere piping is installed underground, the backfill shall be
a) carefully placed and tamped to a height of 300 mm over the top of the pipe, and
b) free of stones, boulders, cinders and frozen earth. (See Appendix A.)
2.3.5.2. Protection of Non-Metallic Pipe
1) Intent StatementWhere asbestos-cement drainage pipe or vitrified clay is located less than 600 mm below a basement floor and the floor is constructed of other than 75 mm or more of concrete, the pipe shall be protected by a 75-mm layer of concrete installed above the pipe. (See Appendix A.)
2.3.5.3. Isolation from Loads
1) Intent StatementWhere piping passes through or under a wall, it shall be installed so that the wall does not bear on the pipe.
2.3.5.4. Protection from Frost
1) Intent StatementWhere piping may be exposed to freezing conditions, it shall be protected from the effects of freezing.
2.3.5.5. Protection from Mechanical Damage
1) Intent StatementPlumbing, piping and equipment exposed to mechanical damage shall be protected.
2.3.5.6. Protection from Condensation
1) Intent StatementPiping used as an internal leader, which may be subject to condensation, shall be installed in a manner that limits the risk of damage to the building due to condensation.

2.3.6. Testing of Drainage or Venting Systems

2.3.6.1. Tests and Inspection of Drainage or Venting Systems
1) Intent StatementExcept in the case of an external leader, after a section of a drainage system or a venting system has been roughed in, and before any fixture is installed or piping is covered, a water pressure test or an air pressure test shall be conducted.
2) Intent StatementAfter every fixture is installed and before any part of the drainage system or venting system is placed in operation, a final test shall be carried out when requested.
3) Intent StatementWhere a prefabricated system is assembled off the building site in such a manner that it cannot be inspected and tested on site, off-site inspections and tests shall be conducted.
4) Intent StatementWhere a prefabricated system is installed as part of a drainage system or venting system, all other plumbing work shall be tested and inspected and a final test shall be carried out on the complete system when requested.
5) Intent StatementWhen requested, a ball test shall be made to any pipe in a drainage system.
2.3.6.2. Tests of Pipes in Drainage Systems
1) Intent StatementEvery pipe in a drainage system, except an external leader or fixture outlet pipe, shall be capable of withstanding without leakage a water pressure test, air pressure test and final test.
2) Intent StatementEvery pipe in a drainage system shall be capable of meeting a ball test.
2.3.6.3. Tests of Venting Systems
1) Intent StatementEvery venting system shall be capable of withstanding without leakage a water pressure test, air pressure test and final test.
2.3.6.4. Water Pressure Tests
1) Intent StatementA water pressure test shall consist in applying a water column of at least 3 m to all joints.
2) Intent StatementIn making a water pressure test,
a) every opening except the highest shall be tightly closed with a testing plug or a screw cap, and
b) the system or the section shall be kept filled with water for 15 min.
2.3.6.5. Air Pressure Tests
1) Intent StatementAir pressure tests shall be conducted in accordance with the manufacturer's instructions for each piping material, and
a) air shall be forced into the system until a pressure of 35 kPa is created, and
b) this pressure shall be maintained for at least 15 min without a drop in pressure.
2.3.6.6. Final Tests
1) Intent StatementWhere a final test is made
a) every trap shall be filled with water,
b) the bottom of the system being tested shall terminate at a building trap, test plug or cap,
c) except as provided in Sentence (2), smoke from smoke-generating machines shall be forced into the system,
d) when the smoke appears from all roof terminals they shall be closed, and
e) a pressure equivalent to a 25 mm water column shall be maintained for 15 min without the addition of more smoke.
2) Intent StatementThe smoke referred to in Clauses (1)(c) and (d) may be omitted provided the roof terminals are closed and the system is subjected to an air pressure equivalent to a 25 mm water column maintained for 15 min without the addition of more air.
2.3.6.7. Ball Tests
1) Intent StatementWhere a ball test is made, a hard ball dense enough not to float shall be rolled through the pipe.
2) Intent StatementThe diameter of the ball shall be not less than
a) 50 mm where the size of the pipe is 3 inches or more, or
b) 25 mm where the size of the pipe is less than 3 inches.

2.3.7. Testing of Potable Water Systems

2.3.7.1. Application of Tests
1) Intent StatementAfter a section of a potable water system has been completed, and before it is placed in operation, a water pressure test shall be conducted, except that an air pressure test may be used in freezing conditions.
2) Intent StatementA pressure test may be applied to each section of the system or to the system as a whole.
3) Intent StatementWhere a prefabricated system is assembled off the building site in such a manner that it cannot be inspected and tested on site, off-site inspections and pressure tests shall be conducted.
4) Intent StatementWhere a prefabricated system is installed as part of a water system,
a) all other plumbing work shall be tested and inspected, and
b) the complete system shall be pressure tested when requested.
2.3.7.2. Pressure Tests of Potable Water Systems
1) Intent StatementExcept as required in Sentence (2), every potable water system shall be able to withstand
a) without leaking, a water pressure that is at least equal to the maximum in-service pressure, or
b) an air pressure of not less than 700 kPa for at least 2 h without a drop in pressure.
2) Intent StatementIf a manufacturer states that an air pressure test is not recommended, a water pressure test shall be performed. (See Appendix A.)
2.3.7.3. Water Pressure Tests
1) Intent StatementWhere a water pressure test is made, all air shall be expelled from the system before fixture control valves or faucets are closed.
2) Intent StatementPotable water shall be used to test a potable water system.