Appendix A - Division C
           
        A-1A.2.1.4.      Unsafe Conditions .  Although words such as alteration, occupancy, building and unsafe            							conditions are defined in Article 1.4.1.2. of Division A, such words as
            							reconstruction, demolition, removal and relocation appearing here and
            							elsewhere in the requirements are adequately defined in dictionaries and
            							need not be repeated herein. 
      
     
        A-1A.2.1.5.      Work on Public Property .  The appropriate government authority may be federal, provincial or            							city, depending on the nature of the public property. 
      
     
        A-1A.2.1.6.      Property Changes .  Control of change of property boundaries applies to either existing            							buildings or new construction. If a building is built as close to a
            							boundary line as the regulations permit, moving the boundary could
            							reduce the fire separation below that required and thus place the
            							building in contravention, this Subsection would not apply. 
      
     
        A-1A.3.2.1.      Notice Prior to Work .  This Subsection requires the owner to inform the Chief Building            							Official of changes in responsibilities of certain employees. It is not
            							intended to limit the owner's right to change the constructor, engineer,
            							architect or inspection or testing agency, but rather to let the
            							building official know of any such change so that construction will not
            							be held up because of any misunderstanding as to who is responsible. See
            							Letters of Assurance at the end of Part 2 of Division C. 
      
     
        A-1A.3.3.3.      Uncovering Work .  The requirement to uncover and replace work will normally apply only            							if Article 1A.3.3.1. has not been complied with, that is, if work
            							requiring inspection has been covered prematurely. Complete uncovering
            							may not be necessary. Here, again, the judgment of the designated
            							official is required to determine if partial uncovering, test holes or
            							similar actions will be sufficient to indicate compliance, the purpose
            							being to promote compliance not to penalize the constructor. 
      
     
        A-1A.3.4.1.      Owner Responsible for Compliance .  Nothing relieves the owner of responsibility, whatever contractual            							arrangements the owner may have made with the constructor. If the owner
            							delegates to the constructor the responsibility of carrying out
            							construction in accordance with the requirements, the constructor would
            							be the owner's agent. These circumstances cannot be recognized by the
            							Chief Building Official, however, since the authority is not a party to
            							such arrangements. 
      
     
        A-1A.3.4.3.      Tests to Prove Compliance .  Where a manufacturer, fabricator or erector is required to conform to            							specified requirements, such as those referenced by Articles 4.3.1.2.
            							and 4.3.3.1., it is intended that proof of such compliance be filed with
            							the Chief Building Official. See Letters of Assurance at the end of Part
            							2 of Division C. 
      
     
        A-1A.4.1.3.      Responsibility .  If the constructor goes bankrupt or is unable to continue the job,            							the owner is responsible. Similarly, if the owner should become unable
            							to carry out his or her responsibilities because of bankruptcy or other
            							reasons, the constructor is responsible to comply with the requirements
            							so far as safety is concerned. The owner must assure that no unsafe
            							condition is left and that any work that is carried out in the absence
            							of the owner complies with the requirements. 
      
 
       The constructor is not responsible for the completion of the
            							building, nor is the contractor responsible under these requirements for
            							matters that are covered by appearance or maintenance
            							regulations. 
      
     
        A-1A.5.1.2.      Filing Documents .  No time period for the retention of documents is specified, because            							this depends upon the city, upon the provincial legislation and upon any
            							statute of limitations that may apply. 
      
     
        A-1A.6.1.1.      Legal Entry .  Since these requirements apply to both new construction and existing            							buildings, the Chief Building Official (i.e., the designated official)
            							has the power to enter any existing buildings as well as new
            							construction, but only for the purpose of administering or enforcing
            							these requirements. 
      
 
       In other words, if there is reason to believe that unauthorized
            							alterations or a change of occupancy has occurred or an unsafe condition
            							exists in respect of fire, structural safety or health, an inspection
            							may be made. The designated official should be informed of any unsafe
            							conditions found in the course of fire inspections. 
      
     
        A-1A.6.1.2.      Scope of Orders .  Some of these powers should be utilized only in extreme instances.            							For example, while the designated official may order the removal of a
            							building constructed in contravention of the requirements, there would
            							be no need to utilize this power if that building can be brought into
            							line with the requirements by additional construction. Similarly, if
            							work being undertaken causes an unsafe condition, the need to order
            							cessation of the occupancy would exist only if that condition could not
            							otherwise be rectified. 
      
     
        A-1A.6.1.6.      Partial or Staged Permit .  If the Chief Building Official issues a permit for a foundation            							before submission of the plans of the complete building, there is no
            							assurance that a permit will be issued for the superstructure when the
            							plans are submitted later. Such issuance will depend upon, among other
            							things, the adequacy of the foundation. This provision is included to
            							give some freedom to the owner to take risks. 
      
     
        A-1A.6.1.7.      Conditional Permits .  A conditional permit may be issued is the additional information            							required is of secondary importance and the foundation or structure is
            							not dependent on it. Information of this type might pertain to building
            							services, such as heating, ventilating, air-conditioning, electrical or
            							plumbing or to partitioning which may not be determined until leases
            							have been arranged. This provision also gives the designated official
            							the latitude to exercise good judgment. 
      
     
        A-1A.6.2.2.      Immediate Measures .  The power to take immediate measures to correct a dangerous situation            							is intended to be used only in conditions of extreme emergency, and its
            							use should be approached with caution. If, for any reason, the owner is
            							unable to act or refuses to act, laying a charge under the Criminal Code
            							will not protect the public against a dangerous situation. It is only
            							when all logical approaches have been exhausted that the designated
            							official should take action. The official should not take this provision
            							as a blanket approval to act, but should be assured in advance that
            							there are no conflicting restrictions on the official's power in other
            							city or provincial Acts. 
      
     
        A-1A.7.2.2.      Application Form .  In addition to the information required by this provision, further            							information is required by Subsection 2.3.4. of Division C, Structural
            							and Foundation Drawings and Calculations, and Subsection 2.3.5. of
            							Division C, Heating, Ventilating, Air-Conditioning and Energy
            							Utilization Drawings and Specifications. 
      
     
        A-1A.7.2.8.      Lapsed Application .  Applications for permits must be complete and properly filed. If an            							application is not proceeded with for 6 months, it must be considered
            							abandoned and can be reinstated only by re-filing after one renewal in
            							writing. 
      
     
        A-1A.8.3.1.      Occupancy Permit .  An Occupancy Permit may also be required for a temporary            							occupancy. 
      
      
       A-2.2.1.2.(1)    Structural Design. Part 4 of Division B is written on the assumption that structural design will         				be carried out by a professional who is qualified to perform such design.  Sentence 2.2.1.2.(1) is not         				intended to imply that a professional may not also be required in the application
         of
         				requirements in other Parts of the NBC.
      
      
        A-2.2.2.2.(1)      Surveys .  Every owner should provide an up-to-date survey by a Registered Land            							Surveyor for 
         
 
            -  a new building, upon completion of all foundations and
                  									footings, including the elevation of a bench mark on the front
                  									building foundation wall, to substantiate its size, location and
                  									elevation, and 
            
-  verification upon completion of the work that all such
                  									provisions have been met. 
            
 A-2.2.6.2.(1)    Information Required on Drawings and Specifications. Examples of information that should be shown on architectural drawings and         				drawings for heating, ventilating and air-conditioning systems are:
      
  
      (a)  the name, type and location of the building,
      
    
      (b)  the name of the owner,
      
    
      (c)  the name of the architect,
      
    
      (d)  the name of the engineer or designer,
      
    
      (e)  the north point,
      
    
      (f)  the dimensions and height of all rooms,
      
    
      (g)  the intended use of all rooms,
      
    
      (h)  the details or description of the wall, roof, ceiling and floor
         					construction, including insulation,
      
    
      (i)  the details or description of the windows and outside doors, including
         					the size, weatherstripping, storm sashes, sills and storm doors,
      
    
      (j)  the size and continuity of all pipes, ducts, shafts, flues and fire
         					dampers,
      
    
      (k)  the location, size, capacity and type of all principal units of
         					equipment,
      
    
      (l)  the size, shape and height of all chimneys and gas
         					vents,
      
    
      (m)  the size and location of all combustion air and ventilation openings,
         					and
      
    
      (n)  the location and fire-resistance rating of required fire
         					separations.
      
        
       A-2.2.7.    Professional Design and Review. This Section provides for the use of what are generally called Letters         						of Assurance. The letters themselves, known as Schedules A, B-1, B-2, C-A
         						and C-B and located at the end of Division C, are intended to put on paper
         						the responsibilities of the owner and various registered professionals in a
         						construction project. The Letters of Assurance do not impose any additional
         						responsibilities on the registered professionals nor are they intended to
         						alter the roles and responsibilities of the authorities having
         						jurisdiction
      
 
      The Schedules have been very carefully scrutinized by the Province of
         						British Columbia, Union of BC Municipalities, Building Officials’
         						Association of BC, Architectural Institute of BC, Association of
         						Professional Engineers and Geoscientists of B.C. and their respective legal
         						counsel. The precise wording in the letters is extremely critical and must
         						not be modified. For this reason, authorities having jurisdiction will only
         						accept copies of the original master Schedules as published in Division C.
         						Any notations on these Schedules which are absolutely necessary to suit a
         						particular project must be clearly and legibly marked in pen on the
         						copies.
      
 
      It is typical that the registered professional responsible for the
         						design is also responsible for the field review. There are instances where
         						this is not the case and having a different registered professional doing
         						the field reviews is unavoidable. Schedule C-B requires that the registered
         						professional that provides the field review provide assurance that the
         						building as finally constructed is in substantial conformance with the Code.
         						It is unreasonable to expect the field reviewer to take on the
         						responsibility for Code compliance of the design done by others. In the
         						event of transition, Schedule C-B must be clarified by the field reviewer by
         						crossing out and initialing Clause (b)(i) and providing the effective
         						transition date.
      
 
      Note that Schedules A, B-1, B-2, C-A & C-B, as required by
         						Subsection 2.2.7., must be signed and sealed and submitted to the authority
         						having jurisdiction, as applicable for each specific project. Conditional or
         						qualified Schedules are not typically acceptable. Any fire and life safety
         						deficiency that would prevent the issuance of a Schedule must be remedied
         						before the Schedule is released, not accommodated by conditions or
         						qualifications placed on the Schedule. See the Guide to Letters of
         						Assurance, available from the Building Policy Branch Web site, for more
         						details.
      
     
       A-2.2.7.1.(1)(b)    Structural Components. The reference to “structural components of buildings that fall within         						the scope of Part 4” includes the situation where a building is classified
         						under Part 9 due to its size and occupancy but also contains some structural
         						components (such as beams supporting concentrated loads) which must be
         						designed under Part 4. In this situation only Schedules B-1, B-2 and C-B for
         						the structural components are required. Schedule A and Schedules B-1, B-2,
         						C-A and C-B relating to non-structural components are not required. Refer to
         						Appendix A-9.4.1.1. and A-9.4.1.1.(3) for structural design of Part 9
         						buildings for lateral wind and earthquake loads.
      
     
       A-2.2.7.2.(1)(a)    Coordinating Registered Professional. The coordinating registered professional is responsible to ascertain         						that all Code related aspects which are relevant to the project are clearly
         						identified by each of the registered professionals in the collection of
         						Schedules B-1 and B-2. If a registered professional has crossed out any item
         						on their Schedule B-2, the coordinating registered professional must confirm
         						this item is not applicable to the project or resolve the issue with the
         						registered professional. Only under unusual circumstances should additional
         						registered professionals within a single discipline be expected to submit
         						Schedules B-1, B-2 and C-B to the coordinating registered
         						professional.
      
     
       A-2.2.7.2.(1)(b)    Schedule B-2. The purpose of Schedule B-2 is to clearly identify the appropriate         						registered professional who has the overall responsibility in each
         						discipline for compliance with the various code-related aspects of the
         						project. Detailed design of certain building components may be undertaken by
         						a second registered professional. It is common in the industry for detailed
         						sprinkler design or detailed structural design of open web steel joists to
         						be performed by a second registered professional who may be retained by the
         						contractor or the fabricator. The registered professional of record fulfills
         						their obligation for overall responsibility of Code compliance as indicated
         						in Schedule B-2 by reviewing the shop drawings which are prepared under the
         						direction of the second registered professional. Such shop drawings must
         						bear the professional seal and signature of the second registered
         						professional. Field review of these components can be undertaken by either
         						the registered professional of record or the second registered professional.
         						In the event that the second registered professional provides the field
         						review, the registered professional of record must be satisfied that such
         						reviews have been performed and is responsible for Schedule C-B.
      
       
        A-2.2.7.2.(1)(c)      Shoring Works in Street or Lane .  Where shoring works are proposed to be left in the street and/or lane            							permanently, an application for the proposal should be made by the owner
            							to the City Engineer. Where the City Engineer is satisfied as to the
            							safety and advisability of the proposal, the City Engineer may approve
            							the basis on which the shoring works may be allowed to remain. 
      
       
       A-2.2.7.2.(2)    Schedule C-A. Schedule C-A provides confirmation that the coordinating registered         						professional has completed the obligation to coordinate the various
         						registered professionals engaged in the project. It also confirms that the
         						testing of the interrelated fire and life safety systems, such as fire
         						alarms and sprinklers, have been completed and the systems function as
         						intended.
      
     
       A-2.2.7.3.    Demonstration of the Coordinated Fire & Life Safety            						Systems. The design drawings and supporting documents must clearly indicate all
         						essential details of the coordinated fire and life safety systems prior to
         						issuance of a building permit. Demonstration of the proper, integrated
         						operation of the fire and life safety systems must be conducted prior to
         						occupancy. The following is an example of the steps required to co-ordinate
         						the installation and testing of fire and life safety systems in buildings.      
    
       
         1.0. General
 
         Referencing Schedule B-2:
 
          
            - Item No. 1.12 “Functional Testing of Architecturally Related Fire
               							Emergency Systems and Devices,”
            
- Item No. 3.4 “Functional Testing of Mechanically Related Fire Emergency
               							Systems and Devices,”
            
- Item No. 4.5 “Functional Testing of Plumbing Related Fire Emergency
               							Systems and Devices,”
            
- Item No. 5.13 “Functional Testing of Fire Suppression Systems and
               							Devices,” and
            
- Item No. 6.3 “Functional Testing of Electrical Related Fire Emergency
               							Systems and Devices.”
            
The coordinating registered professional (CRP) and registered
            						professionals (RPs) must demonstrate that the fire and life safety systems'
            						design has been coordinated prior to the issuance of the building permit.
            						That is, the CRP/RPs must accumulate and submit the necessary documentation,
            						such as:
         
 
          
            - complete drawings,
- schedules,
- schematic diagrams,
- fire alarm system sequencing description (showing coordination between
               							mechanical and electrical fire protection and life safety systems),
            
- mechanical fire protection and life safety schematic riser
               							diagrams,
            
- electrical fire alarm riser diagram,
- motor data list coordinated with fire alarm system sequencing,
- other documentation, as appropriate,
to demonstrate that the interface of the fire and life safety systems has
            						been designed and coordinated so that when built correctly they will
            						function as an integrated system. Further, it is intended that when the
            						construction of the fire and life safety systems is indicated by the
            						contractor to be complete, the RPs/CRP witness the demonstration of the
            						testing of the fire and life safety systems to confirm compliance that the
            						as-built systems function as intended by the design.
         
 
         The required list of items will depend on the simplicity or complexity of
            						the project. The following is a comprehensive list of items for fire and
            						life safety systems for a complex project which need to be coordinated in
            						order to demonstrate compliance:
         
 
          Notes: It is the responsibility of the coordinating registered
               							professional (CRP) and registered professionals (RPs) to determine the
               							best method of “how to” demonstrate to the authority having jurisdiction
               							(AHJ) that the fire protection and life safety systems have been
               							coordinated for each project. That is, the method(s) used (i.e., charts,
               							drawings, matrices, tables, etc.) for demonstration purposes should be
               							project-specific and relate only to that project. 
         
 
          It is not the intent of this Appendix material to dictate or produce
               							“checklists” or other prescriptive methods for demonstrating compliance
               							since this is best left to the professional discretion of the
               							appropriate CRP/RPs. 
         
 
        
       
         
2.0 Design Phase — Building Permit Application Stage & Final
            						Construction Phase — Occupancy Permit Application Stage
         
 
       
       
         2.1 Fire Protection and Life Safety Systems
 
          
            2.1.1. Automatic Sprinkler Systems
 
             
               - design requirements to appropriate standard
  
          
            2.1.2. Standpipe Systems
 
             
               - design requirements to appropriate standard
- Class I/Class II
- locations
- coverage
- F.D. connections
  
          
            2.1.3. Fire Pump Systems
 
             
               - design requirements to appropriate standard
  
          
            2.1.4. Fire Alarm Systems
 
             
               - one/two stage system(s)
- no. of systems
- design requirements to appropriate standard
- sequence of operation
- F.A. system zoning
- location of F.A. system devices
- annunciator panel (location and design criteria)
- annunciator panel shop drawings (detail design)
- sprinkler zone/waterflow device
- smoke detectors
- smoke alarms
- manual pull stations
- signals to fire department via an acceptable central monitoring
                  								station
               
- activation of ancillary devices
  
          
            
2.1.6. Emergency Telephone System
 
          
          
            2.1.7. Emergency Power
 
             
               - design requirements to appropriate standard
- supervisory provisions for fire alarm
- emergency electrical load
- emergency generator
  
          
            2.1.8. Emergency Lighting
 
             
               - exits
- access to exits
- public corridors
- other floor areas
  
          
            
2.1.9. Exit Signs
 
          
        
       
         2.2. Additional Requirements for High Buildings
 
          
            
2.2.1. Interface Condition between Highrise and Lowrise
               							Components
            
 
          
          
            2.2.2. Smoke Control — Measure A
 
             
               - design requirements to appropriate Standard
- venting above-grade stairs
- separation of above-grade and below-grade stairs
- venting below-grade stairs
- pressurization of below-grade stairs at bottom
- above-grade elevator shaft serving below-grade protected with a
                  								"protected" vestibule
               
- additional controls at CACF (annunciator panel shop drawings)
  
          
            
2.2.3. Smoke Venting
 
          
          
            2.2.4. Fire Fighters' Elevators
 
             
               - fire fighting controls
- emergency recall
  
          
            2.2.5. Protection of Emergency Electrical Conductors
 
             
               - highrise elevator
- emergency generator(s)
- fire pump(s)
- smoke control systems
- smoke venting systems
- fire alarm and emergency voice communication systems
  
          
            2.2.6. Emergency Voice Communications
 
             
               - integrated with F.A. system
- audible to appropriate standard
- zoning of speakers
  
        
       
         
3.0. Roles and Responsibilities for the Demonstration of the
            						Coordinated Fire and Life Safety Systems
         
 
       
       
         3.1. Roles and Responsibilities for the Design, Commissioning and
            						Functional Testing of Fire and Life Safety Systems
         
 
          
            3.1.1. Design Phase
 
            RPs will clearly indicate on their drawings and supporting documents
               							the details of the fire and life safety systems for each applicable item
               							of Section 2 for their particular discipline. RPs will also coordinate
               							the design of the components in their system with the designs of other
               							RPs on the project. RPs are to indicate what functional testing, system
               							verification, etc., must be performed by the contractor or sub-trades
               							and establish the documentation to be provided.
            
 
            The CRP will act as the facilitator for the coordination of the design
               							of the fire and life safety systems among the various RPs.
            
 
           
          
            3.1.2. Construction Phase
 
            The contractor will coordinate the activities of the sub-trade
               							contractors for the installation of the fire and life safety systems in
               							accordance with the contract documents.
            
 
            RPs will provide field reviews to ascertain that the construction of
               							the fire and life safety systems substantially complies with their
               							design.
            
 
            RPs will review shop drawings of the fire and life safety systems to
               							determine that they accurately reflect their design intent. They will
               							also coordinate their reviews with those of the other RPs on the
               							project.
            
 
            The CRP will coordinate the shop drawing reviews and field reviews by
               							the RPs with the objective that the entire fire and life safety system
               							will correctly operate as an integrated system.
            
 
           
          
            3.1.3. Occupancy Phase
 
            The contractor will coordinate the sub-trade contractors for the
               							commissioning and functional testing of the fire and life safety
               							systems. The contractor will also collect all of the required occupancy
               							submission documents from the various sub-trade contractors and forward
               							them to the CRP.
            
 
            The CRP will take the lead role in coordinating the activities of the
               							RPs required for the commissioning and functional testing of the fire
               							and life safety systems. The CRP will develop the project-specific test
               							protocol and procedures in consultation with the RPs and distribute them
               							to the various parties involved in the process.
            
 
            RPs will ascertain that the appropriate commissioning and functional
               							testing of the fire and life safety systems of the components in their
               							disciplines have been satisfactorily completed by the sub-trade
               							contractors. They will also determine that the appropriate occupancy
               							submission documents have been submitted and filled in correctly.
            
 
            The CRP will be responsible for collecting all of the required
               							occupancy submission documents, reviewing them for completeness and
               							accuracy, and forwarding them to the AHJ in a complete package prior to
               							the coordinated final AHJ review.
            
 
           
        
       
         3.2. Sample Summary of Roles and Responsibilities for Demonstration of
            						the Coordinated Fire and Life Safety Systems
         
 
         The following is a sample summary (only) of the roles and responsibilities
            						for a typical highrise building with underground parking. The precise roles
            						and responsibilities for each project will vary depending on the complexity.
            						The CRP will ascertain that the appropriate roles and responsibilities for
            						each project are fulfilled by the RPs.
         
 
          
            
3.2.1. Coordinating Registered Professional
 
          
          
            Design Phase
 
             
               - Determine the appropriate RPs required for the project and make
                  								arrangements with the owner for their services.
               
- Clarify the roles and responsibilities of the various RPs.
- Coordinate the design of the fire and life safety systems by the
                  								RPs.
               
- Coordinate and develop the test protocol and procedures for
                  								functional testing of the fire and life safety systems.
               
- Coordinate the submission of the design drawings and supporting
                  								documents for the building permit application.
               
  
          
            Construction Phase
 
             
               - Coordinate and monitor the field reviews of the RPs.
- Coordinate and monitor the review of shop drawings by the RPs.
- Coordinate the information and its circulation among the RPs and
                  								contractor.
               
  
          
            Occupancy Phase
 
             
               - In conjunction with the RPs, compile the project-specific test
                  								protocol and procedures for the fire and life safety systems, and
                  								review the requirements with the contractor, sub-trades and
                  								RPs.
               
- Compile the list of project-specific occupancy permit submission
                  								documents and the schedule for submissions and confirm completeness
                  								with AHJ.
               
- Organize the "Coordinated Final Consultant Review" at least one week
                  								prior to "Coordinated AHJ Final Review."
               
- Coordinate the functional testing of the fire and life safety
                  								systems during the "Coordinated Final Consultant Review."
               
- Coordinate the RPs' review of occupancy submission documents for
                  								completeness and accuracy.
               
- Coordinate certification of equivalencies, if applicable.
- Collect all of the required occupancy submission documents and
                  								submit them in a complete package to the AHJ.
               
- Organize the "Coordinated AHJ Final Review."
- Record any deficiencies identified at the "Coordinated AHJ Final
                  								Review" and monitor RPs' field review of the corrective actions by
                  								the contractor.
               
- Assist in finalizing the list of outstanding requirements which need
                  								to be met prior to occupancy.
               
  
          
            
3.2.2. Architectural
 
          
          
            Design Phase
 
             
               - Establish the conceptual design for the fire and life safety systems
                  								in consultation with RPs.
               
- Determine equivalency reports required and coordinate the
                  								implementation on the drawings and supporting documents.
               
- Clearly indicate on drawings and supporting documents:
 
                  - major occupancies and code classifications.
- fire separations and fire-resistance ratings.
- Closures:
 
                  - Fire-protection rating
- Temperature rise requirements
- Amount of glazing
- hardware
- Quick release hardware
- Hold-open devices
- Electromagnetic locks
- Egress systems.
 
                  - provisions for fire fighting access.
- interior and exterior finishes.
- elevating devices c/w integrated controls to the fire alarm
                     									panel.
                  
- signage coordinated with fire alarm system and
                     									annunciation.
                  
  
          
            Construction Phase
 
             
               - Provide field reviews of architectural components.
- Review shop drawings for architectural components and coordinate
                  								requirements with other RPs.
               
- Review shop drawings for other disciplines which may influence
                  								architectural components.
               
  
          
            Occupancy Phase
 
             
               - Ascertain that the architectural components substantially conform to
                  								the architectural drawings and supporting documents.
               
- Witnessing the functional testing of the architectural components of
                  								the fire and life safety systems.
               
- Coordinate the signage with the fire alarm annunciator and the fire
                  								safety plans.
               
- Review the architecturally-related occupancy submission documents
                  								provided by the contractor and sub-trades for completeness and
                  								accuracy.
               
- Prepare and forward to the CRP the architectural Schedule C-B and
                  								other applicable supporting documents required prior to
                  								occupancy.
               
  
          
            
3.2.3. Mechanical/Plumbing
 
          
          
            Design Phase
 
             
               - Coordinate mechanical/plumbing clearances and functional
                  								requirements with other RPs.
               
- Clearly indicate on drawings and supporting documents:
 
                  - details of the mechanical/plumbing components of the fire and
                     									life safety systems.
                  
- schematic diagram of the smoke venting system showing all fans,
                     									ducts, motorized dampers, fusible link dampers and backdraft
                     									dampers.
                  
- location and fire-protection ratings of fusible link fire
                     									dampers and fire stop flaps.
                  
- location and fire-protection ratings of motorized fire
                     									dampers.
                  
- location and fire-resistance ratings of fire-rated duct
                     									enclosures.
                  
- fire stop systems for mechanical/plumbing penetrations of fire
                     									separations.
                  
- kitchen exhaust system/suppression system.
- Mechanical fans/motorized dampers sequence of operations:
 
                  - Describe operation under normal mode.
- Describe operation under fire alarm mode.
- Indicate fire alarm initiation devices that activate change of
                     									operation.
                  
  
          
            Construction Phase
 
             
               - Provide field reviews of mechanical/plumbing components.
- Review shop drawings for mechanical/plumbing components and
                  								coordinate requirements with other RPs.
               
- Review shop drawings for other disciplines which may influence
                  								mechanical/plumbing components.
               
  
          
            Occupancy Phase
 
             
               - Ascertain that the mechanical/plumbing components substantially
                  								conform to the mechanical/plumbing drawings and supporting
                  								documents.
               
- Witnessing the functional testing of the mechanical/ plumbing
                  								components of the fire and life safety systems.
               
- Review the mechanical/plumbing related occupancy submission
                  								documents provided by the contractor and sub-trades for completeness
                  								and accuracy.
               
- Prepare and forward to the CRP the mechanical/plumbing Schedule C-B
                  								and other applicable supporting documentation required prior to
                  								occupancy.
               
  
          
            3.2.4. Fire Suppression
 
            The assurance of sprinkler systems can be accomplished under two
               							possible scenarios:
            
 
           
          
            Scenario 1
 
             
               - The engineer of record undertakes the complete detailed sprinkler
                  								system design prior to the building permit application.
               
- The engineer of record submits Schedules B-1 and B-2 with the BP
                  								application.
               
- The engineer of record provides field reviews during construction
                  								and submits a Schedule C-B prior to occupancy.
               
  
          
            Scenario 2
 
             
               - The engineer of record provides a detailed performance specification
                  								for the sprinkler system design, as well as sufficient documentation
                  								to demonstrate/assure layout feasibility and interface with other
                  								components.
               
- The engineer of record submits Schedules B-1 and B-2 with the BP
                  								application for overall coordination of the sprinkler design.
               
- The performance specifications may include a requirement that a
                  								separate sprinkler design engineer be responsible for detailed
                  								sprinkler design, preparation of sprinkler shop drawings (signed and
                  								sealed) and hydraulic calculations, letters of assurance Schedules
                  								B-1 and B-2, field reviews during construction, and Schedule C-B
                  								(for detailed design) prior to occupancy.
               
- The engineer of record reviews the detailed sprinkler design and
                  								shop drawings to ascertain that they substantially comply with the
                  								performance specifications.
               
- The engineer of record provides a Schedule C-B prior to occupancy to
                  								confirm overall coordination of the sprinkler design and
                  								installation. The engineer of record is entitled to rely upon the
                  								professional seal of the sprinkler design engineer for the detailed
                  								design and field review of the sprinkler system.
               
  
          
            
3.2.5. Electrical
 
          
          
            Design Phase
 
             
               - Coordinate with the CRP and RPs the test protocol and procedures for
                  								functional testing of the fire and life safety systems.
               
- Details of the electrical components of the fire and life safety
                  								systems.
               
- Clearly indicate on drawings and supporting documents:
 
                  - Fire Alarm System
 
                     - Location of fire alarm annunciator panel and central alarm
                        										control facility
                     
- Location of fire alarm initiating devices, e.g., smoke
                        										detectors, heat detectors, manual pull stations.
                     
- Fire alarm riser diagram c/w ancillary device
                        										connections
                     
- Audibility of fire alarm signal throughout floor area
- Zoning of fire alarm initiation devices and audible signal
                        										appliances
                     
- Monitoring of fire alarm
- Routing and method of protection of emergency
                        										conductors
                     
- Wiring methods for equipment
- Testing/verification requirements and the documentation to
                        										be submitted to the RP
                     
- Sprinkler System
 
                     - Coordinate design with fire suppression registered
                        										professional.
                     
- Sprinkler system alarm initiation and monitoring to be
                        										indicated on the fire alarm riser diagram, e.g., flow,
                        										tamper, pressure.
                     
- Detailed diagrams for freeze protection systems, e.g., heat
                        										trace monitoring, low temperature monitoring.
                     
- Fire Pump Systems
 
                     - Riser diagram to indicate monitoring of the fire pump, e.g.,
                        										pump running, power failure, phase reversal, wiring details
                        										for device connections.
                     
- Routing and method for protection of fire pump feeders from
                        										fire and power source, so that a fire from one source will
                        										not interrupt power from the other source
                     
- Electrical requirements to appropriate Standard and
                        										documents to be submitted to RP, e.g., overcurrent
                        										protection details, location of controller and transfer
                        										switches, voltage drop.
                     
- Kitchen Exhaust/Fire Suppression System
- Emergency Generator
 
                     - Generator load calculations
- Details and wiring diagram for monitoring through the fire
                        										alarm system
                     
- Details for testing to appropriate Standard and documents to
                        										be submitted to RP
                     
- Smoke Venting Systems
 
                     - Coordinate design with the mechanical engineer
- Fire alarm riser diagram to indicate smoke venting fans and
                        										motorized dampers and HVAC/exhaust fan shutdown
                     
- Detailed wiring diagrams for fan shut-offs, exhaust fan
                        										operation, pressurization fan operation, damper operation
                        										(opening, closing, throttling)
                     
- Sequence of operation of smoke venting system in a narrative
                        										form
                     
- Describe operation under normal mode
- Describe operation under fire alarm mode
- Indicate fire alarm initiating devices that activate changes
                        										of operation/sequence
                     
- Routing methods for protection of emergency conductors
- Electromagnetic Locks and Hold-Open Devices (Security)
 
                     - Coordinate design with the architect
- Sequence of operation in both normal and fire alarm
                        										mode
                     
- Wiring diagrams for connection of devices
- Locations of devices on the floor plans
- Elevators
 
                     - Sequence of operation in a narrative form
- Wiring diagram details
- Routing and method of protection of emergency
                        										conductors
                     
- Fire stop systems for electrical penetrations of fire
                     									separations
                  
- Coordinate electrical equipment location and functional
                     									requirements with other RPs/CRP.
                  
  
          
            Construction Phase
 
             
               - Provide field reviews of electrical components.
- Review shop drawings for electrical components and coordinate
                  								requirements with other RPs.
               
- Review shop drawings for other disciplines which may influence
                  								electrical components.
               
  
          
            Occupancy Phase
 
             
               - Ascertain that the electrical components substantially conform to
                  								the electrical drawings and supporting documents.
               
- Witnessing the functional testing of the electrical components of
                  								the fire and life safety systems.
               
- Review the electrical-related occupancy permit submission documents
                  								provided by the contractor and sub-trades for completeness and
                  								accuracy.
               
- Prepare and forward to the CRP the electrical Schedule C-B and other
                  								applicable supporting documents required prior to occupancy.
               
  
        
       
         4.0. Sample Occupancy Demonstration/Witnessing Flowchart
 
             
                
                  | DEVELOP TESTING PROTOCOL/PROCEDURE
                     								(Design Phase) | 
 
                
                  | CRP/RPs develop Testing
                     								Demonstration/Witness Protocol — Issue to Authorities
                     								Having Jurisdiction & Contractor
 | 
 
                
                  | ⇓ | 
 
                
                  | DOCUMENTATION SUBMISSION | 
 
                
                  | Contractor/Sub-trades submit/deliver all
                     								appropriate documentation to CRP/RPs, including: | 
 
                
                  |  | — The original Contractor's Materials and Test Certificate
                     								for the sprinkler system — The original Contractor's
                     								Materials and Test Certificate for the sprinkler system
 — Fire Pump Flow Test Certificate(s)
 — Back
                     								Flow Prevention Certificate(s)
 — Emergency generator
                     								commissioning and verification reports
 — The original
                     								Certificate of Verification for the fire alarm system
 — Appendix "A" to the fire alarm verification report
 — ULC Certificate for Protective Signaling Service
 — Other documentation, as appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | CONTRACTOR DEMONSTRATION — CONSTRUCTION
                     								COMPLETE | 
 
                
                  | Contractor & Sub-trades (Mechanical, Electrical, Elevator, Sprinkler, Fire Alarm, etc.) as
                     								appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | COORDINATED FINAL CONSULTANT REVIEW
                     								DEMONSTRATION/WITNESSING | 
 
                
                  | CRP/RPs (Architect, Mechanical
                     								Engineer, Electrical Engineer, Sprinkler Engineer,
 Equivalency
                     								Consultant, etc.) as appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | OCCUPANCY SUBMISSION DOCUMENTS | 
 
                
                  | CRP to collect all submission documents,
                     								including Schedule Cs from RPs, and submit to AHJ in a complete
                     								package
 | 
 
                
                  | ⇓ | 
 
                
                  | COORDINATED FINAL AHJ REVIEW DEMONSTRATION/WITNESS
 | 
 
                
                  | Contractor, Sub-trades, CRP/RPs
                     								demonstrate to AHJ (Building, Fire, Mechanical, Electrical and
                     								Sprinkler)
 | 
 
                
                  | ⇓ | 
 
                
                  | OCCUPANCY | 
 
            
           
            
       A-2.3.1.    Documentation of Alternative Solutions. Beyond the purposes of demonstrating compliance and acquiring a building         				permit, there are other important reasons for requiring that the proponent of
         an
         				alternative solution submit project documentation (i.e. a compliance report) to
         the
         					Chief Building Official and for the Chief Building
            					Official to retain that documentation for a substantial period following
         				the construction of a building: the City requires that a building be
         				maintained in compliance with the codes under which it was built. Alternative
         				solutions made possible by objective-based By-law may have special
         				maintenance requirements, which would be described in the documentation.
      
 
       
         - Documentation helps consultants perform code compliance assessments of existing
            					buildings before they are sold and informs current owners or prospective buyers
            					of existing buildings of any limitations pertaining to their future use or
            					development.
         
- Documentation provides design professionals with the basic information necessary
            					to design changes to an existing building.
         
- An alternative solution could be invalidated by a proposed alteration to a
            					building. Designers and regulators must therefore know the details of the
            					particular alternative solutions that were integral to the original design.
            					Complete documentation should provide insight as to why one alternative solution
            					was chosen over another.
         
- Documentation is the “paper trail” of the alternative solution negotiated
            					between the designer and the regulator and should demonstrate that a rational
            					process led to the acceptance of the alternative solution as an
            					equivalency.
         
- It is possible that over time a particular alternative solution may be shown to
            					be inadequate. It would be advantageous for a jurisdiction to know which
            					buildings included that alternative solution as part of their design:
            					documentation will facilitate this type of analysis.
         
- Project documentation provides important information to a forensic team that is
            					called to investigate an accident or why a design failed to provide the level
            of
            					performance expected.
         
 A-2.6.3.     Demonstration of the Coordinated Fire & Life Safety
               							Systems .  The design drawings and supporting documents must clearly indicate
            							all essential details of the Coordinated Fire & Life Safety
            							Systems prior to issuance of a Building Permit. Demonstration of the
            							proper, integrated operation of the Fire & Life Safety Systems
            							must be conducted prior to issuance of the Occupancy Permit. 
      
 
       Note that Schedules A, B-1, B-2, C-A & C-B, as required by
            							Section 2.6., must be signed and sealed and submitted to the Authority
            							Having Jurisdiction, as appropriate for each specific project. 
      
 
       
         1.0. General
 
         Referencing Schedule B-2:
 
          
            - Item No. 1.14 "Functional Testing of Architecturally Related Fire
                  								Emergency Systems and Devices,"
- Item No. 3.4 "Functional Testing of Mechanically Related Fire
                  								Emergency Systems and Devices,"
- Item No. 4.5 "Functional Testing of Plumbing Related Fire Emergency
                  								Systems and Devices,"
- Item No. 5.13 "Functional Testing of Fire Suppression Systems and
                  								Devices," and
- Item No. 6.3 "Functional Testing of Electrical Related Fire
                  								Emergency Systems and Devices."
The Coordinating Registered Professional (CRP) and Registered
               							Professionals of Record (RPRs) must demonstrate that the Fire and Life
               							Safety Systems' design has been coordinated prior to the issuance of the
               							Building Permit. That is, the CRP/RPRs must accumulate and submit the
               							necessary documentation, such as:
 
          
            - complete drawings,
- schedules,
- schematic diagrams,
- fire alarm system sequencing description (showing coordination
                  								between mechanical and electrical fire protection and life safety
                  								systems),
- mechanical fire protection and life safety schematic riser
                  								diagrams,
- electrical fire alarm riser diagram,
- motor data list coordinated with fire alarm system sequencing,
- other documentation, as appropriate,
to demonstrate that the interface of the Fire & Life Safety
               							Systems has been designed and coordinated so that when built correctly
               							they will function as an integrated system. Further, it is intended that
               							when the construction of the Fire & Life Safety Systems is
               							indicated by the Contractor to be complete, the RPRs/CRP witness the
               							demonstration of the testing of the Fire & Life Safety Systems
               							to confirm compliance that the as-built systems function as intended by
               							the design.
 
         The required list of items will depend on the simplicity or complexity
               							of the Project. The following is a comprehensive list of items for Fire
               							& Life Safety Systems for a complex project, which must be
               							coordinated in order to demonstrate compliance:
 
         Notes: It is the responsibility of the Coordinating Registered
               							Professional (CRP) & Registered Professionals of Record (RPRs)
               							to determine the best method of "How To" demonstrate to the Authority
               							Having Jurisdiction (AHJ) that the Fire & Life Safety Systems
               							have been coordinated for each project. That is, the method(s) used
               							(i.e., charts, drawings, matrices, tables, etc.) for demonstration
               							purposes should be project-specific and relate only to that
               							project.
 
         It is not the intent of this Appendix Material to dictate or produce
               							"checklists" or other prescriptive methods for demonstrating compliance
               							since this is best left to the professional discretion of the
               							appropriate CRP/RPRs.
 
        
       
         
2.0. Design Phase — Building Permit Application Stage &
               							Final Construction Phase — Occupancy Permit Application Stage
 
       
       
         
2.1. Fire Protection and Life Safety Systems
 
       
       
         2.1.1. Automatic Sprinkler Systems
 
          
            - design requirements to appropriate Standard
  
       
         2.1.2. Standpipe Systems
 
          
            - design requirements to appropriate Standard
- Class I/Class II
- locations
- coverage
- F.D. connections
  
       
         2.1.3. Fire Pump Systems
 
          
            - design requirements to appropriate Standard
  
       
         2.1.4. Fire Alarm Systems
 
          
            - one/two stage system(s)
- no. of systems
- design requirements to appropriate Standard
- sequence of operation
- F.A. system zoning
- location of F.A. system devices
- annunciator panel (location and design criteria)
- annunciator panel shop drawings (detail design)
- sprinkler zone/waterflow device
- smoke detectors
- smoke alarms
- manual pull stations
- signals to Fire Department via an acceptable central monitoring
                  								station
- activation of ancillary devices
  
       
         2.1.6. Emergency Telephone System
 
          
        
       
         2.1.7. Emergency Power
 
          
            - design requirements to appropriate Standard
- supervisory provisions for fire alarm
- emergency electrical load
- emergency generator
  
       
         2.1.8. Emergency Lighting
 
          
            - exits
- access to exits
- public corridors
- other floor areas
  
       
         
2.1.9. Exit Signs
 
       
       
         
2.2. Additional Requirements for High Buildings
 
       
       
         
2.2.1. Interface Condition between Highrise and Lowrise Components
               							(Measure 'N' Vestibules)
 
       
       
         2.2.2. Smoke Control — Measure A
 
          
            - design requirements to appropriate Standard
- venting above-grade stairs
- separation of above-grade and below-grade stairs
- venting below-grade stairs
- pressurization of below-grade stairs at bottom
- above-grade elevator shaft serving below-grade protected with a
                  								"protected" vestibule
- additional controls at CACF (annunciator panel shop drawings)
  
       
         
2.2.3. Smoke Venting
 
       
       
         2.2.4. Fire Fighters' Elevators
 
          
            - fire fighting controls
- emergency recall
  
       
         2.2.5. Protection of Emergency Electrical Conductors
 
          
            - highrise elevator
- emergency generator(s)
- fire pump(s)
- smoke control systems
- smoke venting systems
- fire alarm and emergency voice communication systems
  
       
         2.2.6. Emergency Voice Communications
 
          
            - integrated with F.A. system
- audible to appropriate Standard
- zoning of speakers
  
       
         
3.0. Roles and Responsibilities for the Demonstration of the
               							Coordinated Fire and Life Safety Systems
 
       
       
         
3.1. Roles and Responsibilities for the Design, Commissioning and
               							Functional Testing of Fire and Life Safety Systems
 
       
       
         3.1.1. Design Phase
 
         RPRs will clearly indicate on their drawings and supporting documents
               							the details of the fire and life safety systems for each applicable item
               							of Section 2 for their particular discipline. RPRs will also coordinate
               							the design of the components in their system with the designs of other
               							RPRs on the project. RPRs are to indicate what functional testing,
               							system verification, etc., must be performed by the Contractor or
               							subtrades and establish the documentation to be provided.
 
         The CRP will develop the project-specific test protocol and procedures
               							in consultation with the RPRs. The CRP will act as the facilitator for
               							the coordination of the design of the fire and life safety systems among
               							the various RPRs.
 
        
       
         3.1.2. Construction Phase
 
         The Contractor will coordinate the activities of the subtrade
               							contractors for the installation of the fire and life safety systems in
               							accordance with the contract documents.
 
         RPRs will provide field reviews to ascertain that the construction of
               							the fire and life safety systems substantially complies with their
               							design.
 
         RPRs will review shop drawings of the fire and life safety systems to
               							determine that they accurately reflect their design intent. They will
               							also coordinate their reviews with those of the other RPRs on the
               							project.
 
         The CRP will coordinate the shop drawing reviews and field reviews by
               							the RPs with the objective that the entire fire and life safety system
               							will correctly operate as an integrated system.
 
        
       
         3.1.3. Occupancy Phase
 
         The Contractor will coordinate the subtrade contractors for the
               							commissioning and functional testing of the fire and life safety
               							systems. The Contractor will also collect all of the required Occupancy
               							Permit submission documents from the various subtrade contractors and
               							forward them to the CRP.
 
         The CRP will take the lead role in coordinating the activities of the
               							RPRs required for the commissioning and functional testing of the fire
               							and life safety systems. The CRP will distribute the test protocol and
               							test procedures, as developed in the Design Stage, to the various
               							parties involved in the process.
 
         RPRs will ascertain that the appropriate commissioning and functional
               							testing of the fire and life safety systems of the components in their
               							disciplines have been satisfactorily completed by the sub trade
               							contractors. They will also determine that the appropriate Occupancy
               							Permit submission documents have been submitted and filled in
               							correctly.
 
         The CRP will be responsible for collecting all of the required
               							Occupancy Permit submission documents, reviewing them for completeness
               							and accuracy, and forwarding them to the AHJ in a complete package at
               							least 24 hours prior to the Coordinated Final AHJ Review.
 
        
       
         3.2. Sample Summary of Roles and Responsibilities for Demonstration
               							of the Coordinated Fire and Life Safety Systems
 
         The following is a sample summary (only) of the roles and
               							responsibilities for a typical highrise building with underground
               							parking. The precise roles and responsibilities for each project will
               							vary depending on the complexity. The CRP will ascertain that the
               							appropriate roles and responsibilities for each project are fulfilled by
               							the RPRs.
 
        
       
         
3.2.1. Coordinating Registered Professional
 
       
       
         Design Phase
 
          
            - Determine the appropriate RPRs required for the project and make
                  								arrangements with the owner for their services.
- Clarify the roles and responsibilities of the various RPRs.
- Coordinate the design of the fire and life safety systems by the
                  								RPRs.
- Coordinate and develop the test protocol and procedures for
                  								functional testing of the fire and life safety systems.
- Coordinate the submission of the design drawings and supporting
                  								documents for the Building Permit application.
  
       
         Construction Phase
 
          
            - Coordinate and monitor the field reviews of the RPRs.
- Coordinate and monitor the review of shop drawings by the RPRs.
- Facilitate the information flow among the RPRs and Contractor.
  
       
         Occupancy Phase
 
          
            - In conjunction with the RPRs, finalize the project-specific test
                  								protocol and procedures for the fire and life safety systems, and
                  								review the requirements with the Contractor, subtrades and
                  								RPRs.
- Finalize the list of project-specific occupancy permit submission
                  								documents and the schedule for submissions and confirm completeness
                  								with AHJ.
- Organize the "Coordinated Final Consultant Review" at least one week
                  								prior to "Coordinated AHJ Final Review."
- Take a lead role in coordinating the functional testing of the fire
                  								and life safety systems during the "Coordinated Final Consultant
                  								Review."
- Coordinate the RPRs' review of Occupancy Permit submission documents
                  								for completeness and accuracy.
- Coordinate Certification of Equivalencies, if applicable.
- Collect all of the required Occupancy Permit submission documents
                  								and submit them in a complete package to the AHJ.
- Organize the "Coordinated AHJ Final Review."
- Record any deficiencies identified at the "Coordinated AHJ Final
                  								Review" and monitor RPRs' field review of the corrective actions by
                  								the subtrades.
- Assist in finalizing the list of outstanding requirements which need
                  								to be met for the issuance of the Occupancy Permit.
- Follow-up on minor deficiencies post-Occupancy.
  
       
         3.2.2. Architectural Design Phase
 
          
            - Establish the conceptual design for the fire and life safety systems
                  								in consultation with RPRs.
- Determine equivalency reports required and coordinate the
                  								implementation on the drawings and supporting documents.
- Clearly indicate on drawings and supporting documents:
 
               - Major occupancies and code classifications.
- Fire separations and fire-resistance ratings.
- Closures:
 
               - Fire-protection rating
- Temperature rise requirements
- Amount of glazing
- Hardware for closures
 
               - Panic hardware
- Hold-open devices
- Electromagnetic locks
- Egress systems.
- Provisions for fire fighting access.
- Interior and exterior finishes.
- Elevating devices c/w integrated controls to the fire alarm
                  								panel.
- Signage coordinated with fire alarm system and annunciation.
  
       
         Construction Phase
 
          
            - Provide field reviews of architectural components.
- Review shop drawings for architectural components and coordinate
                  								requirements with other RPRs.
- Review shop drawings for other disciplines which may influence
                  								architectural components.
  
       
         Occupancy Phase
 
          
            - Ascertain that the architectural components substantially conform to
                  								the architectural drawings and supporting documents.
- Perform an active role in witnessing the functional testing of the
                  								architectural components of the fire and life safety systems.
- Coordinate the signage with the fire alarm annunciator and the fire
                  								safety plans.
- Review the architecturally-related Occupancy Permit submission
                  								documents provided by the Contractor and subtrades for completeness
                  								and accuracy.
- Prepare and forward to the CRP the architectural Schedule C-B and
                  								other assurance letters required for the Occupancy Permit.
  
       
         3.2.3. Mechanical/Plumbing Design Phase
 
          
            - Coordinate mechanical/plumbing clearances and functional
                  								requirements with other RPRs.
- Clearly indicate on drawings and supporting documents:
 
               - Details of the mechanical/plumbing components of the fire and life
                     								safety systems.
- Schematic diagram of the smoke venting system showing all fans,
                     								ducts, motorized dampers, fusible link dampers and backdraft
                     								dampers.
- Location and fire-protection ratings of fusible link fire dampers
                     								and fire stop flaps.
- Location and fire-protection ratings of motorized fire dampers.
- Location and fire-resistance ratings of fire-rated duct
                     								enclosures.
- Fire stop systems for mechanical/plumbing penetrations of fire
                     								separations.
- Mechanical fans/motorized dampers sequence of operations:
- Describe operation under normal mode
- Describe operation under fire alarm mode
- Indicate fire alarm initiation devices that activate change of
                  								operation
 
               - Kitchen exhaust system/suppression system.
  
       
         Construction Phase
 
          
            - Provide field reviews of mechanical/plumbing components.
- Review shop drawings for mechanical/plumbing components and
                  								coordinate requirements with other RPRs.
- Review shop drawings for other disciplines which may influence
                  								mechanical/plumbing components.
  
       
         Occupancy Phase
 
          
            - Ascertain that the mechanical/plumbing components substantially
                  								conform to the mechanical/plumbing drawings and supporting
                  								documents.
- Perform an active role in witnessing the functional testing of the
                  								mechanical/ plumbing components of the fire and life safety
                  								systems.
- Review the mechanical/plumbing related occupancy permit submission
                  								documents provided by the Contractor and subtrades for completeness
                  								and accuracy.
- Prepare and forward to the CRP the mechanical/plumbing Schedule C-B
                  								and other assurance letters and documentation required for the
                  								Occupancy Permit.
  
       
         3.2.4. Fire Suppression
 
         The design of sprinkler systems can be accomplished by at least two
               							possible scenarios:
 
         Scenario 1
 
          
            - The engineer of record undertakes the complete detailed design prior
                  								to the building permit application.
- The engineer of record submits Schedules B-1 and B-2 with the BP
                  								application.
- The engineer of record provides field reviews during construction
                  								and submits a Schedule C-B prior to Occupancy Permit.
  
       
         Scenario 2
 
          
            - The engineer of record provides a detailed performance specification
                  								for the sprinkler design, as well as sufficient drawings to
                  								demonstrate/assure layout feasibility and interface with other
                  								components.
- The engineer of record submits Schedules B-1 and B-2 with the BP
                  								application for overall coordination of the sprinkler design.
                  								Schedules B-1 and B-2 can be annotated "For Performance
                  								Specification Only."
- The performance specifications may include a requirement that a
                  								separate sprinkler design engineer be responsible for detailed
                  								sprinkler design, preparation of sprinkler shop drawings and
                  								hydraulic calculations, letters of assurance Schedules B-1 and B-2,
                  								field reviews during construction, and Schedule C-B (for Detailed
                  								Design) prior to Occupancy Permit.
- The engineer of record reviews the detailed sprinkler design and
                  								shop drawings to ascertain that they substantially comply with the
                  								performance specifications.
- The engineer of record provides a Schedule C-B prior to Occupancy
                  								Permit to confirm overall coordination of the sprinkler design and
                  								installation. Schedule C-B can be annotated "For Performance
                  								Specification Only." The engineer of record is entitled to rely upon
                  								the professional seal of the sprinkler design engineer for the
                  								detailed design and field review of the sprinkler system.
For purposes of this example, Scenario 2 Roles and Responsibilities
               							are outlined below:
 
        
       
         Design Phase by Engineer of Record
 
          
            - Coordinate fire suppression spatial and functional requirements with other RPRs/CRP.
- Clearly indicate on the drawings and performance specification:
 
               - Fundamental design parameters for the fire suppression system to
                     								appropriate Standard.
- Location of fire department siamese hose connections.
- Location and size of standpipes and hose connections.
- Details of special sprinkler protection as per equivalent
                     								reports.
- Fire stop systems for pipe penetrations of fire separations.
- Zoning of the sprinkler system to be coordinated with the electrical
                     								engineer for the fire alarm annunciation and clearly identified in
                     								the performance specifications.
  
       
         Construction Phase by Sprinkler Design Engineer
 
          
            - Prepare, sign and seal shop drawings and hydraulic calculations,
                  								clearly indicating:
 
               - Details of the fire suppression components of the fire and life
                     								safety systems.
- Schematic riser diagram of sprinkler and standpipe systems c/w all
                     								devices that will be connected to the fire alarm system (flow
                     								switches, tamper switches, pressure switches, freeze monitoring,
                     								heat trace monitoring).
- Location of fire department siamese hose connections.
- Location and size of standpipes and hose connections.
- Details of special sprinkler protection as per equivalent
                     								reports.
- Zoning of the sprinkler system to be coordinated with the electrical
                     								engineer for the fire alarm annunciation and clearly identified on
                     								the sprinkler shop drawings.
- Coordinate fire suppression location and functional requirements
                     								with engineer of record/CRP.
- Provide field reviews of fire suppression components.
  
       
         Construction Phase by Engineer of Record
 
          
            - Review shop drawings and hydraulic calculations for fire suppression
                  								components to determine substantial conformance to the performance
                  								specifications.
- Provide field reviews of fire suppression components to determine
                  								substantial conformance to the performance specifications.
- Monitor the field reviews by the Sprinkler Design Engineer to
                  								determine substantial conformance with the performance
                  								specifications.
- Review shop drawings for other disciplines which may influence fire
                  								suppression components.
  
       
         Occupancy Phase by the Engineer of Record
 
          
            - Ascertain that the fire suppression components substantially conform
                  								to the performance specifications.
- Perform an active role in witnessing the functional testing of the
                  								fire suppression components of the fire and life safety
                  								systems.
- Review the fire suppression-related Occupancy Permit submission
                  								documents by the Contractor and subtrades for completeness and
                  								accuracy.
- Collect the Schedule C-B from the Sprinkler Design Engineer, review
                  								for accuracy and completeness and forward to the CRP.
- Collect other Occupancy Permit documents from the subtrade
                  								contractor (e.g., Contractor's Material and Test Certificates),
                  								review for completeness and forward to the CRP.
- Prepare and forward to the CRP the fire suppression Schedule C-B for
                  								overall coordination of the fire suppression system.
  
       
         Occupancy Phase by the Sprinkler Design Engineer
 
          
            - Ascertain that the fire suppression components substantially conform
                  								to the sprinkler shop drawings and supporting documents.
- Perform an active role in witnessing the functional testing of the
                  								fire suppression components of the fire and life safety
                  								systems.
- Review the fire suppression-related Occupancy Permit submission
                  								documents by the Contractor and subtrades for completeness and
                  								accuracy.
- Prepare and forward to the Engineer of Record the fire suppression
                  								Schedule C-B and other assurance letters and documentation required
                  								for the Occupancy Permit.
  
       
         3.2.5. Electrical
 
         Design Phase
 
          
            - Coordinate with the CRP and RPRs the test protocol and procedures
                  								for functional testing of the fire and life safety systems.
- Details of the electrical components of the fire and life safety
                  								systems.
- Clearly indicate on drawings and supporting documents:
- Location of fire alarm annunciator panel and central alarm control
                  								facility
- Location of fire alarm initiating devices (smoke detectors, heat
                  								detectors, manual pull stations)
- Fire alarm riser diagram c/w ancillary device connections
- Audibility of fire alarm signal throughout floor area
- Zoning of fire alarm initiation devices and audible signal
                  								appliances
- Monitoring of fire alarm
- Routing and method of protection of emergency conductors
- Wiring methods for equipment
- Testing/verification requirements and the documentation to be
                  								submitted to the RPR
- Coordinate design with sprinkler design engineer
- Sprinkler system alarm initiation and monitoring to be indicated on
                  								the fire alarm riser diagram (flow, tamper, pressure, etc.)
- Detailed diagrams for freeze protection systems (heat trace
                  								monitoring, low temperature monitoring, etc.)
- Riser diagram to indicate monitoring of the fire pump (pump running,
                  								power failure, phase reversal, wiring details for device
                  								connections)
- Routing and method for protection of fire pump feeders from fire and
                  								power source, so that a fire from one source will not interrupt
                  								power from the other source
- Electrical requirements to appropriate Standard and documents to be
                  								submitted to RPR (overcurrent protection details, location of
                  								controller and transfer switches, voltage drop, etc.)
 
               - Kitchen Exhaust/Fire Suppression System
- Emergency Generator
- Generator load calculations
- Details and wiring diagram for monitoring through the fire alarm
                  								system
- Details for testing to appropriate Standard and documents to be
                  								submitted to RPR
- Coordinate design with the mechanical engineer
- Fire alarm riser diagram to indicate smoke venting fans and
                  								motorized dampers and HVAC/exhaust fan shutdown
- Detailed wiring diagrams for fan shut-offs, exhaust fan operation,
                  								pressurization fan operation, damper operation (opening, closing,
                  								throttling)
- Sequence of operation of smoke venting system in a narrative
                  								form
- Describe operation under normal mode
- Describe operation under fire alarm mode
- Indicate fire alarm initiating devices that activate changes of
                  								operation/sequence
- Routing methods for protection of emergency conductors
 
               - Electromagnetic Locks and Hold-Open Devices
- Coordinate design with the architect
- Sequence of operation in both normal and fire alarm mode
- Wiring diagrams for connection of devices
- Locations of devices on the floor plans
- Sequence of operation in a narrative form
- Wiring diagram details
- Routing and method of protection of emergency conductors
 
               - Fire stop systems for electrical penetrations of fire
                     								separations
- Coordinate electrical equipment location and functional requirements
                     								with other RPRs/CRP.
  
       
         Construction Phase
 
          
            - Provide field reviews of electrical components.
- Review shop drawings for electrical components and coordinate
                  								requirements with other RPRs.
- Review shop drawings for other disciplines which may influence
                  								electrical components.
  
       
         Occupancy Phase
 
          
            - Ascertain that the electrical components substantially conform to
                  								the electrical drawings and supporting documents.
- Perform an active role in witnessing the functional testing of the
                  								electrical components of the fire and life safety systems.
- Review the electrical-related Occupancy Permit submission documents
                  								provided by the Contractor and subtrades for completeness and
                  								accuracy.
- Prepare and forward to the CRP the electrical Schedule C-B and other
                  								assurance letters and documents required for the Occupancy
                  								Permit.
  
       
         4.0. Sample Occupancy Demonstration/Witnessing Flowchart
 
             
                
                  | DEVELOP TESTING PROTOCOL/PROCEDURE
                        									(Design Stage) | 
 
                
                  | CRP/RPRs develop Testing
                        									Demonstration/Witness Protocol — Issue to Authorities
                        									Having Jurisdiction & Contractor
 | 
 
                
                  | ⇓ | 
 
                
                  | DOCUMENTATION SUBMISSION | 
 
                
                  | Contractor/Subtrades submit/deliver
                        									all appropriate documentation to CRP/RPRs, including: | 
 
                
                  |  | — The original Contractor's Materials and Test
                        									Certificate for the sprinkler system — Fire Pump
                        									Flow Test Certificate(s)
 — Back Flow Prevention
                        									Certificate(s)
 — Emergency generator
                        									commissioning and verification reports
 — The
                        									original Certificate of Verification for the fire alarm
                        									system
 — Appendix "A" to the fire alarm
                        									verification report
 — ULC Certificate for
                        									Protective Signaling Service
 — Other
                        									documentation, as appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | CONTRACTOR DEMONSTRATION —
                        									CONSTRUCTION COMPLETE | 
 
                
                  | Contractor & Subtrades (Mechanical, Electrical, Elevator, Sprinkler, Fire Alarm, etc.)
                        									as appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | COORDINATED FINAL CONSULTANT REVIEW
                        									DEMONSTRATION/WITNESSING CRP/RPRs | 
 
                
                  | (Architect, Mechanical Engineer,
                        									Electrical Engineer, Sprinkler Engineer, Equivalency
                        									Consultant, etc.) as appropriate
 | 
 
                
                  | ⇓ | 
 
                
                  | OCCUPANCY SUBMISSION DOCUMENTS | 
 
                
                  | CRP to collect all submission
                        									documents, including Schedule Cs from RPRs, and submit to
                        									AHJ in a complete package
 | 
 
                
                  | ⇓ | 
 
                
                  | COORDINATED FINAL AHJ REVIEW
                        									DEMONSTRATION/WITNESS | 
 
                
                  | Contractor, Subtrades, CRP/RPRs
                        									demonstrate to AHJ (Building, Fire, Mechanical, Electrical
                        									and Sprinkler)
 | 
 
                
                  | ⇓ | 
 
                
                  | OP ISSUED | 
 
            
           
         
      [Rev. 10, B.C. Reg. 232/2010.]